CHANGE ORDER
No . 3
PROJECT Spoonbill Marsh Wetland Facility
DATE OF ISSUANCE 9/2/09 EFFECTIVE DATE 9/2/09
OWNER .- Indian River County Utilities
OWNER 's Contract No . UCP 2785 ENGINEER : Masteller & Moler. Inc .
CONTRACTOR : Timothy Rose Contractinq ENGINEER Project No , 0544LH
You are directed to make the following changes in the Contract Documents :
Description : Install added electrical services to accommodate SCADA Systems and sump pumps .
Added security fencing to the pump structure and a security pate at the entrance of the Spoonbill
Marsh site .
Reason for change order: IRCUD Request
Attachments : ( List documents supporting change ) Contractors Cost Exhibits
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Times
$ 2 112 . 870 . 00 Substantial Completion : 3/19/2009
Ready for final payment :
Das or dates
Net changes from previous Change Orders Net change from previous Change Orders
No . 1 to No . 2 No . 1 to No . 2
$ 2 112 , 870 =00 N /A days
Contract Price prior to this Change Order Contract Time prior to this Change Order
$
222419798w66 Substantial Completion : 7/31109
Ready for final payment :
Days or dates
Net Increase (decrease) in this Change Order Net Increase in this Change Order
$ 23 , 916 . 65 NIA
days
Contract Price with all approved Change Orders Contract Time with all approved Change
Orders
$
21265, 715030
Substantial Completion : 7/31 /09
Ready for final payment :
Days or dates
RECOMMENDED : APP VED : ACCEPTED :
By : By:
Engineer ( uth rize ignature) ' Owner (Autho z icnature) Contractor (Authorized Signature)
Date : C �� Date : September
22 , 2009 Date :
EJCDC No . C-700 (2002 Edition )
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General
Contractors of America
July 29, 2009
Indian River County Utilities
180127 th Street, Bldg . A
Vero Beach , FI 32960
RE : Spoonbill Marsh Wetland Facility
Contract # : UCP 2785
REQUESTED CHANGE ORDER
Change Order Proposal For The Following Items .
One ( 1 ) Stainless Steel Disconnect and
Transformer Enclosure for Scada Wiring : Add : $ 14, 059 . 00
Furnish Underground Power for Scada and Flo Meters Add : $ 11100. 00
Stainless Unistrut and Aluminum Post for Rack Add : $ 1 , 620 . 00
Three ( 3 ) Sump Pumps Add : $ 446 . 65
Three ( 3 ) Sample Points Add : $ 1, 974 . 00
Total Requested Change in Contract Amount Add : $ 19, 199 . 65
If you have any questions, do not hesitate to contact our office .
Thank you —
Vickie Wright
Timothy Rose Contracting, Inc .
August 31 , 2009
Indian River County
Attn : Art Pheiffer
RE : Spoonbill Marsh Wetland
REQUESTED CHANGE ORDER
Change Order Proposal To Add Fence & Locking Gate :
Add Vinyl Coated Fence With Locking Hatch Add : $ 3 , 524 . 00
Add 14' Gate Installed @ Berm Add : 11193000
Total Proposed Change Order $ 4, 717 . 00
If you have any questions , do not hesitate to contact our office .
Thank you —
Vickie Wright
Timothy Rose Contracting, Inc .