CHANGE ORDER a Y' t := ao _ 171
No , 1
PROJECT Vero Lake Estates Phase II
DATE OF ISSUANCE 10/01 /2008
EFFECTIVE DATE 10/01 /2008
OWNER Indian River ity Utilities Department
OWNER 's Contract No , 2958
M & M Project No . 0741
CONTRACTOR Timothy Rose Contracting Inc
ENGINEER Masteller & Moler, Inc .
You are directed to make the following changes in the Contract Documents :
Description : Addition and deduction to contract amount due to Owner directed chanes
Reason for change order: Owner directed to make changes
Attachments : ( List documents supporting change) Exhibit "A "
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Ori al Contract Times
$ 471 , 450. 00 Substa ial Completion :
Ready fo inal payment :
Da
Net changes from previous Change Orders Net change f m previous Channges rdearses
No . O to No . 0 No . _to No .
$ 0. 00
Contract Price prior to this Change Order da s
9 Contract Time prior t this ange Order
$ 4719450. 00 Substantial Completion
Ready for final paym t :
Net Increase ( Decrease) in this ChanDa s or dates
Order ge Net Increase int Change O er
$ 118 901 . 00
Contract Price with all approved Chane da s
Orders g Contract a with all approved Chan e
Orders
$ 352 . 549 . 00 Sub ntial Completion :
Re dy for final payment:
Da s or dates
RECOMMENDED : APPREp : ACCEP
By
Engineer Authoriz d Signature) Owner (Authorize Signature) ontractor (Authorized Signature)
Date : Date : mune 9 . 2009 - Date :
EJCDC No . C- 700 (2002 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of
America
Vero Lake Estates
Water Main Extension
Phase Two
Change Order 1 Exhibit
Item Description Unit Qty Unit Cost Total Chg Cost
1 12 " Water Main LF - 1570 $ 23 . 00 $ ( 36 , 110 . 00 )
2 12 " Directional Bore LF -580 $ 82 . 00 $ (47 , 560 . 00)
3 8" Directional Bore LF -80 $ 46 . 00 $ ( 31680 . 00 )
4 12 " Gate Valve EA -2 $ 2 , 080 . 00 $ (4 , 160 . 00 )
5 12"x12 " Wet Tap w/ 12 " Valve EA - 1 $ 4 , 600. 00 $ (4 , 600 . 00 )
6 12 "x8" Wet Tap W/ 8 " Valve EA - 1 $ 29900 . 00 $ (2 , 900 . 00 )
7 Fire Hydrant Assembly EA -2 $ 21630 . 00 $ ( 51260 . 00 )
8 Air Release Valves EA -6 $ 3 , 838 . 00 $ (23 , 028 . 00 )
9 S1 Asphalt Sq Yd 180 $ 17 . 40 $ 3 , 132 . 00
10 Base Rock Sq Yd 180 $ 16 . 00 $ 21880 . 00
11 lCompacted Sub-Grade Sq Yd 1 180 1 $ 6 . 50 $ 11170 . 00
12 8 " Gate Valve EA 1 $ 11215 . 00 $ 1 , 215 . 00
Total Change Order Costs $ ( 118 , 901 . 00 )
The reduction of some of materials is due to Indian River County Road and Bridge having
contracted Sheltra & Sons to perform the installation of the water main from 104th Avenue to 101st Avenue .
This reduced the amount of construction Tim Rose Construction bid on . The air release valves were deleted
at the request of Indian River County Utilities .
The addition of roadway materials is due to directional bores being replaced by open cuts at four
intersections at the request of Indian River County Utilities .
The additional 8" gate valve replaced the 12"x8" wet tap w/ gate valve .