Field and Laboratory Quality Control ( QC )
for
Roadway & Drainage Improvements to
16th Street from 74th Avenue to 66th Avenue
And
66th Avenue from 16th Street to S . R . 60
IRC Project No ' s . 9810 -A, 99209 0545
WORK ORDER NO . 1 ( Engineering Division )
FOR
FOR PROFESSIONAL GEOTECHNICAL SERVICES AGREEMENT
FOR ANNUAL GEOTECHNICAL SERVICES CONTRACT RFQ No . 2009071
WITH
UNIVERSAL ENGINEERING SCIENCES , INC .
All services performed under this contract shall be supervised and certified by a licensed
Professional Engineer ( PE ) registered with the State of Florida and staff employed directly with
your firm .
Scope of Services
All work shall be performed on a unit price basis in accordance with the attached Scope
of
Services ( Exhibit A) dated March 3 , 2009 and shall comply with Standards enumerated in the
ANNUAL GEOTECHNICAL SERVICES CONTRACT RFQ 2008071 WITH UNIVERSAL
ENGINEERING SCIENCES INC . Effective Date : December 2 , 2008 .
Minimum Specification Requirements as follows :
Soil Compaction
Concrete Compressive Strength Testing
Asphaltic Roadway Surfacing Testing
Subsurface Exploration
All work shall also comply with the current Florida Minimum Technical Standards .
COMPENSATION ,
The COUNTY agrees to pay , and the Geotechnical Professional agrees to accept , a fee for
services rendered according to the " Scope of Services " identified in the attached EXHIBIT "A"
Fee Schedule and Man Hours .
C : ADocuments and SettingsVhoaglin\Local Settings\Temporary Internet Files\OLK86\9810-A 9920 0545 - BCC Agenda WO# I UNIVERSAL
ENGINEERING 2 - 17 -09
mm . doc
WO #1
16" Street & 66th Avenue
Roadway & Drainage Improvements
IRC Project No ' s . 9810 -A, 99209 0545
A Not-to- Exceed Amount of: 144126.00 to be paid on a unit price basis for actual work
performed in accordance with the schedule of services and fees set forth in Exhibit A of
RENEWAL OF THE ANNUAL GEOTECHNICAL SERVICES CONTRACT RFQ 2008071 WITH
UNIVERSAL ENGINEERING SCIENCES INC . Effective Date : December 2 , 2008
TIME FOR COMPLETION
This work order No . 1 shall run concurrently with the construction work for the
16th Street from 74th Avenue to 66th Avenue Roadway Improvements , IRC Project #9920
66th Avenue from 16th Street to South of S . R . 60 , Roadway Improvements , IRC Project # 9810-A
66th Avenue from South of S . R . 60 to North of S . R . 60 , Roadway Improvements ,
IRC Project #0545
IN WITNESS HEREOF the parties hereto have executed these presents
This 17th day of March , 2009 .
OWNER UNIVERSAL ENGINEERING SCIENCES , INC .
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY, FLORIDA
(� nature) ( ignature)
Wesley S. Davis, Chairman Richard E . Hoaglin , P. E . , Regional Manager
Approved by BCC-1 r,_r ;h_ 17� 2009 Witnessed by :
ATTEST :
Jeffrey K. Balton , Clerk of Circuit Court
eJ cm Fn ed I &i;-
Deputy Clerk (Printed name)
", tod Le S f ii y :
�
yj �' illiam G . Colli
� U s II , County Attorney
�
J seph A. ai d , County ministrat r
C : ADocuments and Settings\rhoaglin \Local Settings\Temporary Internet Files\OLK86\9810-A 9920 0545 - BCC Agenda WO# 1 UNIVERSAL
ENGINEERING 2 - 17-09
mm . doc
UNIVERSAL
ENGINEERING SCIENCES , INC . EXIJI B 1 �`
Consultants In : Geotechnical Engineering Environmental Sciences
Construction Materials Testing • Threshold Inspection
803 South Kings Highway m Fort Pierce , Florida 34945
Phone : ( 772) 461 - 9815 Fax : ( 772) 461 - 9816
Mr. Michael J . Mezzina March 3 , 2009
Indian River County Engineering Division
184025 thStreet
Vero Beach , FL 32960
Reference : Budget Estimate Proposal for Construction Materials Testing Services
66 thAvenue and 16th Street Roadway Improvements
Indian River County , Florida
Universal Proposal Number: 1910 . 0209 . 00008 rev
DOCS Number: 753605
Dear Mr. Mezzina :
Universal Engineering Sciences , Inc . ( Universal ) is pleased to provide this proposal for
Geotechnical Engineering and Construction Materials Testing ( CMT) services at the above.
practices and the project minimum requirements .
referenced project in accordance with the generally accepted soil and foundation engineering
We are confident that our experience , quality of service , professional attitude and proximity
to the site will be of value throughout the design and construction phases of the project .
PROJECT DESCRIPTION
We understand that the project will be constructed in three phases and will consist of various
improvements along 66th Avenue and 16th Street in Indian River County, Florida . These
improvements include : stormwater utility installation , new sidewalk installation , new roadway
construction , widening and resurfacing . In addition , approximately 3 , 700 linear feet of water
main addition is planned for a portion of 66th Avenue . Three drilled shafts are also planned for
signalization improvements at the intersection of 66th Avenue and 16th Street . The
signalization improvements will include the installation of three (3 ) traffic signal masts , one
each at the northeast , northwest and southwest corners of the subject intersection . We
assume that the mast poles will have a maximum height of 25 feet and the mast arms will
extend horizontally 60 to 80 feet .
GEOTECHNICAL ENGINEERING SCOPE OF SERVICE
Based on the information provided , Universal proposes the following field services to obtain
information regarding the subsurface conditions at the site . The exploration will be performed
in general concordance with pertinent FDOT guidelines and procedures . The field services
will include the following tasks :
661" Avenue and 16«' Street Improvements EXHIBITA
Universal Proposal No. 1910. 0209. 00008 rev
Page 2
Field Services
• Drill three (3 ) SPT borings , one ( 1 ) adjacent to each of the proposed signal mast
locations , to a depth of 25 feet bls .
• Install a temporary piezometer at each boring location and obtain stabilized groundwater
level readings .
• Stake boring locations , provide utilities clearance , and obtain groundwater level readings .
All SPT borings will be drilled in accordance with ASTM D 1586 ( Standard Method for
Penetration Test and Split- Barrel Sampling of Soils ) procedures . The SPT borings will be
sampled continuously at 18 - inch intervals from ground surface to a depth of 10 feet bls and at
5 feet intervals thereafter.
The SPT borings will be performed using an ATV mounted drilling rig and/or a truck mounted
drill rig using either rotary mud techniques or continuous flight augers to termination depth .
Each recovered soil sample will be visually classified in the field and a geologic log prepared
for each soil boring . Groundwater depths and any unusual subsurface conditions will be
recorded on the boring logs . Representative portions of the recovered soil samples from each
boring location will be sealed and packaged for transportation to our laboratory for a more
detailed analysis , as required . All soil samples will be classified in general accordance with
ASTM, D 2487 ( Standard Classification of Soils for Engineering Purposes ( Unified Soil
Classification System ) ) guidelines .
Analysis and Engineering Report
Universal will prepare a geotechnical engineering report for 'the signalization portion of the
project , which will respond to the proposed property development . The report will be prepared
under the direction of a professional geotechnical engineer registered in the State of Florida .
The report will summarize the field and laboratory services performed and provide an
engineering analysis of the site soil and groundwater conditions with special attention to
potential subsurface conditions that may hinder development .
The final report will include the following :
• Methodology and results of the field exploration .
• Review of available data such as USGS Topographic maps , soil surveys and
potentiometric maps .
• Results of the laboratory testing program
• Estimates of the typical wet season groundwater level at the boring locations
• Recommendations concerning soil parameters for soil strata encountered for the design
of a foundation for the proposed structures . Notes will be made as to whether the soils
meet FDOT standard foundation criteria .
66" Avenue and 16" Street Improvements EXH ,
Universal Proposal No. 9996. 0209. 00008 rev BIT A
Pa e 3
Scheduling And Cost Estimate
The field work can be scheduled to begin , based on our Present schedule ,
within one week
after receiving the written authorization to proceed . Universal expects the field work to require
require approximately two to three days to prepare a2 working days to complete . Our laboratory testing analysis and report preparation
will
after completion of the field work . A final zation
geotechnical report should be submitted within three weeks from receiving the authori
to proceed . If this schedule needs to be amended or if special scheduling considera
required please advice us . tion is
The fee for the subsurface exploration and geotechnical engineering report is $ 2 , 593 . 00 . This
estimate will not be exceeded without prior written authorization . For specific terms of the
proposed work , please refer to our continuing services contract terms and conditions .
CONSTRUCTION MATERIALS TESTING ( CMT) SCOPE OF SERVICES
Based on review of the project documents and our experience in the area ,
provide the following : Universal will
• On -call earthwork , asphalt and concrete testing
• Engineering overview of our services
The laboratory testing will be performed out of our Fort Pierce , Florida office with additional
support from our Rockledge , Florida office , if required . During the duration of the project all
technicians and personnel involved with the construction testing and inspection will be
supervised by a Professional Engineer ( P . E . ) registered in the State of Florida .
The following assumptions were made to develop the estimated scope of services :
• Roadway construction will be phased into at least two separate operations ,
travel lane , and compaction tests will be performed every 500 linear feet . one per
• Curb pad and stabilized shoulders will be constructed as a separate operation from the
mainline roadway construction , and compaction tests will be performed every 500
linear feet .
• Stabilized subgrade will be sampled and tested for Limerock Bearing Ratio ( LBR )
every 1 , 000 linear feet per width of roadway operation and density will be checked as
a single 124ch lift .
• Base course will be sampled and tested for Limerock Bearing Ratio (LBR ) every 2 , 000
linear feet per width of roadway operation and density will be checked as two 4 - inch
lifts .
• Utility pipe and structures will be tested for compaction for the full depth of fill in 6 - inch
lifts at 100 % of a standard Proctor test (AASHTO T99 ) in accordance with the project
plans . Tests will be performed at a minimum frequency of one per every 200 linear feet
or one per pipe run .
• A minimum of three feet ( vertical ) of roadway subgrade ( embankment) will be
compacted and tested at a frequency of one per every 500 linear feet .
• No compaction testing will be required for the perforated bituminous coated corrugated
metal pipe ( BCCMP ) .
• No density compaction testing will be required for the 4- inch underdrains .
6d ' Avenue and 16`h Street Improvements EX H , B ! T A
Universal Proposal No. 9910. 0209. 00008 rev
Page 4
• The sidewalk subgrade will be tested for compaction as a single six- inch lift at a
frequency of once every 500 linear feet .
Cost of Services
The services listed herein will be invoiced on a unit rate basis per the estimated scope . Note
that the budget is an estimate of our services and may change as the result of unforeseen
events such as requested standby time , overtime , retesting , etc . Pick up charges are not
included in soil or concrete testing rates . A minimum of four density tests are required per
trip . The estimated cost of services is separated into three individual phases based on the
construction documents .
16th Street Improvements - From 74th Ave to 66th Ave
Soils
In Place Density Tests (embankment)
Estimate 70 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . $ 1 , 680 . 00
In Place Density Tests ( stabilized subgrade )
Estimate 36 each @ $ 24 . 00/each . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . $ 864 . 00
. . . . . . . . . . . . . . . . .
In Place Density Tests ( base course )
Estimate 36 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . $ 864 . 00
In Place Density Tests (sidewalk subgrade )
Estimate 10 each @ $ 24 . 00/each . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . $240 . 00
. . . . . . . . . . . . . . . .
In Place Density Tests ( utility pipe backfill )
Estimate 155 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . .
In Place Density Tests ( utility structure backfill )
Estimate 125 each @ $ 24 . 00/each . . . . . . ,
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . $ 3 , 000 . 00
. . . . . . . . . . . . . . . . . . . .
Limerock Bearing Ratio ( LBR ) Tests ( base and stabilized subgrade )
Estimate 12 each @ $ 240 . 00/each . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . $ 2 , 880 . 00
. . . .
Moisture/ Density Relationship Tests (embankment and utility backfill )
Estimate 8 each @ $ 80 . 00/each . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . $ 640 . 00
Concrete
Make and Break Concrete Cylinders ( set of 4 )
( Includes 1 hour of on site time per set )
Estimate 24 sets @ $ 80 . 00/set . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . $ 1 , 920 . 00
. . . . . . . . . . .
66" Avenue and 16"' Street Improvements � � � '
Universa! Proposal No. 1910. 0209. 00008 rev T A
Page 5
pare
Field Technician for Stand - by Time ( in excess of 1 hour per set )
Estimate 6 hours @ $ 38 . 00/ hour . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . $ 228 . 00
Sample Pickups (when no other work is performed )
Estimate 6 hours @ $ 38 . 00/hour . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . • . . . . $228 . 00
. . . . . . . . . . . . . . . . . . . . .
Asphaltic Roadway Surfacing
Extraction /Gradation Test
Estimate 12 each @ $ 160 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. 9 $ 1 , 920 . 00
. . . . . . . . . . . . . .
Asphalt Cores (6- inch diameter by 2 . 5 - inch thickness )
Estimate 24 each @ $ 37 . 50/each . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . $ 900 . 00
Asphalt Core Density
Estimate 24 each @ $ 20 . 00/each . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . $480 . 00
Sample Pickups ( when no other work is performed )
Estimate 6 hours @ $ 38 . 00/hour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
$228 . 00
Budget Estimate Subtotal . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . $ 19 , 792 . 00
66th Avenue Improvements - South of SR 60 to North of SR 60
Soils
In Place Density Tests ( embankment)
Estimate 30 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . $ 720 . 00
In Place Density Tests (stabilized subgrade )
Estimate 25 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . $ 600 . 00
In Place Density Tests ( base course )
Estimate 12 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . $ 288
. 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . .
In Place Density Tests ( sidewalk subgrade )
Estimate 5 each @ $24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . $ 120 . 00
In Place Density Tests ( utility pipe backfill )
Estimate 40 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . OMA . . . . . . . . . . . . .
. . . . . . . . $ 960 . 00
In Place Density Tests ( utility structure backfill )
Estimate 30 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . $ 720 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
66'h Avenue and 96�h Street Improvements � � � '
Universal Proposal No. 1990. 0209. 00008 rev
Page 6
Limerock Bearing Ratio ( LBR ) Tests ( base and stabilized subgrade )
Estimate 6 each @ $ 240 . 00/each . . . . NAME . . . . . . . . . . . . . ANN . . . . . . , $ 1
, 440 . 00
. OWN . . . . . . . . . . . . . . . ova worm . . . Sol * am . . . . . . . . . . .
Moisture/ Density Relationship Tests ( embankment and utility backfill )
Estimate 4 each @ $ 80 . 00/each . . . . . . . . . . . . . . $ 320 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . .
Concrete
Make and Break Concrete Cylinders ( set of 4 )
( Includes 1 hour of on site time per set)
Estimate 10 sets @ $ 80 . 00/set . . . . . . . . . . . . . . . . A 0 0 a 0 0 b 6 0 0 a a 0
. . . . $ 800 . 00
Field Technician for Stand - by Time ( in excess of 1 hour per set )
Estimate 3 hours @ $ 38 . 00/hour . . . . . . . . . . . . . . . . . . . . . . . . $ 135 . 00
Sample Pickups (when no other work is performed )
Estimate 3 hours @ $ 38 . 00/ hour . . . . . . . . . . . . . . . . . . $ 114 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . .
Asphaltic Roadway Surfacing
Extraction /Gradation Test
Estimate 4 each @ $ 160 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . . maNsovommon .
. . $ 640 . 00
Asphalt Cores ( 6 - inch diameter by 2 . 5 "- inch thickness )
Estimate 12 each @ $ 37 . 50 /each . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $
450 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Asphalt Core Density
Estimate 12 each @ $20 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . $ 240 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . .
Sample Pickups (when no other work is performed )
Estimate 4 hours @ $ 38 . 00/hour $ 1
Budget Estimate Subtotal . 5 a 6 0 a 9 a 0 a a a a a 9 M a X a a a a a a a " a 4 0 a a V a a V a a AN 0 a n H a a 9 0 N I V
U 9 a 0 0 4 a 9 a a 0 0 a a 0 A 4 a . . . . $ 7 , 699 . 00
66th Avenue Improvements - 16th Street to South of SR 60
Soils
In Place Density Tests (embankment )
Estimate 35 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . . . . . . . $ 840 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
In Place Density Tests ( stabilized subgrade )
Estimate 15 each @ $ 24 . 00/each . . . . . . . . . . . . . . . . . . Debt . . $ 360 . 00
. . . .
. . . . . . . . . . . . . . . . . . . . . . . .
66'h Avenue and 96'h Street Improvements
Universal Proposal No . 9990. 0209. 00008 rev � � � '
Pa e 7
BIT A
In Place Density Tests ( base course )
Estimate 12 each @ $24 . 00/each
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . b 0 P 6 M $288.O0
In Place . Density Tests ( sidewalk subgrade )
Estimate 5 each @ $ 24 . 00/each . . . . . . . ,
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . .
$ 120 . 00
In Place Density Tests ( utility pipe backfill )
Estimate 165 each @ $ 24 . 00/each . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . goes
. . . . . . . . . . $ 33960 . 00
In Place Density Tests ( utility structure backfill )
Estimate 75 each @ $ 24 . 00/each
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . $ 1 , 800 . 00
. . . . . . . . . . . . . .
Limerock Bearing Ratio ( LBR ) Tests ( base and stabilized subgrade )
Estimate 10 each @ $ 240 . 00/each . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . $ 2 , 400 . 00
Moisture /Density Relationship Tests (embankment and utility backfill )
Estimate 8 each @ $ 80 . 00/each
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. $ 640 . 00
Concrete
Make and Break Concrete Cylinders (set of 4 )
( Includes 1 hour of on site time per set )
Estimate 16 sets @ $ 80 . 00/set . . . . . . . . . ,
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 1
, ?_ 80 . 00
Field Technician for Stand - by Time ( in excess of 1 hour per set)
Estimate 4 hours @ $ 38 . 00/ hour . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . $ 152 . 00
Sample Pickups (when no other work is performed )
Estimate 4 hours @ $ 38 . 00/hour SEES . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
$ 152 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Asphaltic Roadway Surfacing
Extraction/Gradation Test
Estimate 6 each @ $ 160 , 00/each . . . . . . , .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . $ 960 . 00
. . . . . . . . . . . . . . . .
Asphalt Cores ( 6 - inch diameter by 2 . 5 "- inch thickness )
Estimate 15 each @ $ 37 . 50/each SSSS .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
$ 562 . 00
Asphalt Core Density
Estimate 15 each @ $20 . 00/each
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 300 . 00
Sample Pickups (when no other work is performed )
Estimate 6 hours @ $ 38 . 00/ hour . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . SSSS . . . $ 228 . 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . .
Budget Estimate Subtotal . . . . . . . . down , . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 149042 . 00
66th Avenue and 16" Street Improvements E X H ' V I T A
Universal Proposal No. 1910. 0209. 00008 rev
Page 8
CMT BUDGET ESTIMATE TOTAL . . . . . . . . . . . . . manage ensue as Reamems ones man & $ 41 , 533 . 00
General Notes
( 1 ) All unit fees are portal to portal for normal work hours Monday through Friday from
6 : 00 a . m . to 5 : 00 p . m . daily , Work performed in excess of 40 hours per week ,
nights , Saturday , Sunday and holidays will be invoiced per our annual contract .
( 2 ) Professional consultations and meetings will be invoiced at our contracted unit rates
for those services rendered .
( 3 ) If no other work is performed during the jobsite visit , sample pickups will be invoiced
at the technician ' s contracted hourly rate .
All work will be performed in accordance with this proposal and our annual contract terms
and conditions . We believe the information supplied in this proposal is satisfactory for your
current needs . If this proposal is acceptable , please issue a work order to our office .
We look forward to working with you on this project . Please contact us if you have any
questions or require additional information .
Sincerely,
Universal Engineering Sciences , Inc .
4 rl�rr
rad Faucett , P . E . '�
i and E . Hoag i 4pmt!7�
Regional Engineep �- Regional Manager
Attachments : Work Authorization Form
EXHIBIT A
Universal Engineering Sciences , Inc .
WORK AUTHORIZATION FORM
If This Proposal Is Accepted , Please Sign and Return To Universal Engineering Sciences , Inc .
E:
Universal Engineering Sciences , Inc. (UNIVERSAL) is pleased to provide the services described within this document. The purpose
of this
document is to describe the terms under which the services will be provided and to obtain formal authorization .
PROJECT NAME : 66 " Avenue and 16th Street Roadway Improvements
PROJECT LOCATION : Vero Beach , Florida DATE ; March 3 , 2009
ATTENTION : Mr. Michael J . Mezzina
CLIENT NAME : Indian River County Engineering Divsion PHONE NO : 772 . 226 . 1986
CLIENT ADDRESS : 1840 25 'h Street , Vero Beach , FL 32960 FAX NO : 772 . 778 , 9391
I . Scope of Services (See Proposal and General Conditions for the terms of this agreement) .
Universal Proposal No . 9910 . 0209 . 00008/DOCS No . 753605
Perform geotechnical engineering and construction materials testing in accordance with the
scope of services and cost of services in the proposal and the continuing services agreement
with Indian River County Engineering Division .
Geotechnical Budget Estimate Cost $2 , 593 . 00
Construction Materials Budget Estimate Cost 14L533 . 00
L-- Grand Total Budget Estimate Cost $ 44 , 126 . 00
II• Contract documents. The following documents form part of this Agreement and are incorporated herein
by referral :
A . Continuing Services Agreement with Indian River County
B . Universal Proposal Dated : March 3 , 2009
C . Plans , reports , specifications and/or other documents provided by the Client prior to this Agreement date .
C . Other exhibits marked and described as follows : _
In the event of any inconsistency or conflict among Contract Documents , the provision in the Contract Document
first
listed shall govern .
III . Authority to proceed and for payment. (To be completed by Client)
If the invoice is to be mailed for approval to someone other than the account charged , please indicate where , below:
Firm : Social Security Number or
Address :
Federal Identification No . :
IN WITNESS WHEREOF , the parties have caused this Agreement to be executed by duly authorized representatives :
CLIENT
UNIVERSAL ENG ERIN SCIE ES I
ow
BY ( Signature )
BY (Signature )
CL
TYPED NAME
TYPED NAME Richard E . Hoaglin P E
TITLE
DATE
TITLE Regional Manager
-
DATE March 3 , 2009