HomeMy WebLinkAbout2008-213 (5)Indian River County
Purchasing Division
180027 th Street
Vero Beach, FL 32960
Phone (772) 567-8000 Fax (772) 770=5140
Ext. 1416
Date.
Project Name:
Bid Number:
Bid Opening Date:
THE BI
ADDENDUM NO. 3
March 17, 2008
Wabasso Beach Park Restoration
2008032
March 26, 2008 at 2:00 pm
TE HAS B
TO MARCH
This Addendum is in Response to REQUESTS FOR INFORMATION (RFI) and consisting of
2 pages.
****************This Addendum MUST be returned with your bid*****************
All Bids must be received by the Purchasing Division office located at 1800 27ths
Street, Vero Beach, FL 32960, prior to the Date and Time shown above. Late bids
will be returned unopened.
Company Name
Name:
(Type / Printed)
Authorized Signature:
Telephone:
Title:
Date:
Fax:
TO PROSPECTIVE BIDDERS AND OTHERS CONCERNED: This ADDENDUM and all other
ADDENDUMS are intended to clarify, correct, or change the Bidding Requirements and/or the
Contract Documents. Therefore, ent .All ADDENDUMS are hereby made a part of hey hereby supersede anything to the contrary in and s
e Bidding
Requirements or Contract Doc hall be
attached to the subject Bidding Requirements and Contract Documents.
F:\Public Works\Cliff Suthard\Wabasso Beach Park\A Construction Bid Documents\Bid Documents as of 2-6-2008\Hddendum #1 #2. #3. #49 &
#5\Addendum #3.doc Page 1 of 2
3.03
into existing water bodies, must be installed, constructed or, in case of vegetative buffers,
protected from disturbance, as a first step in the land alteration process.
E. Working in or Crossing Waterways or Water Bodies: Land alteration and construction
shall be minimized in both permanent and intermittent waterways and the immediately
adjacent buffer of 25 feet from top of bank of the waterways and the buffer area whenever
possible, and barriers shall be used to prevent access. Where in channel work cannot be
avoided, precautions must be taken to stabilize the work area during land alteration,
development and/or construction to minimize erosion. If the channel and buffer area are
disturbed during land alteration, they must be stabilized within three (3) calendar days
after the in channel work is completed.
Silt curtains or other filter/siltation reduction devices must be installed on the downstream
side of the in channel alteration activity to eliminate impacts due to increased turbidity.
Whenever stream crossings are required, properly sized temporary culverts shall be
provided by the Contractor and removed when construction completed. The area of the
crossing shall be restored to a condition as nearly as possible equal to that which existed
prior to any construction activity.
F. Swales, Ditches and Channels: All swales, ditches and channel leading from the site shall
be sodded within three (3) days of excavation. All other interior swales, etc., including
detention areas will be sodded prior to substantial completion.
G. Underground Utility Construction: The construction of underground utility lines and other
structures shall be done in accordance with the following standards:
1. No more than 100 lineal feet of trench shall be open at any time;
2. Wherever consistent with safety and space consideration, excavated material shall be
cast to the uphill side of trenches. Trench material shall not be cast into or onto the
slope of any stream, channel, road ditch or waterway.
PERFORMANCE
A. Maintenance: All erosion and siltation control devices shall be checked regularly,
especially after each rainfall and will be cleaned out and/or repaired as required.
B. Compliance: Failure to comply with the aforementioned requirements may result in a fine
and/or more stringent enforcement procedures such as, but not limited to, issuance of a
"Stop Work Order".
END OF SECTION
02270 - 2
02270 — Erosion Control
SECTION 02302
EXCAVATION AND FILL
PART 1 - GENERAL
1.01 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
A. AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
1. ASTM C 33(1999; Rev. A) Concrete Aggregates
2. ASTM C 136(1996; Rev. A) Sieve Analysis of Fine and Coarse Aggregates
3. ASTM D 698(1991; R 1998) Laboratory Compaction Characteristics of Soil Using
Standard Effort (129400 ft-lbf/ft (600 kN-m/m))
4. ASTM D 1140(1997) Amount of Material in Soils Finer Than the No. 200 (75 -
Micrometer) Sieve
5. ASTM D 1556(1990; R 1996) Density and Unit Weight of Soil in Place by the
Sand -Cone Method
6, ASTM D 1557(1991; R 1998) Laboratory Compaction Characteristics of Soil Using
Modified Effort (56,000 ft-lbf/ft (2,700 kN-m/m))
7. ASTM D 2321(1989; R 1995) Underground Installation of Thermoplastic Pipe for
Sewers and Other Gravity -Flow Applications
8, ASTM D 2487(1998) Classification of Soils for Engineering Purposes (Unified Soil
Classification System)
9, ASTM D 2922(1996) Density of Soil and Soil -Aggregate in Place by Nuclear
Methods (Shallow Depth)
10. ASTM D 3017(1996) Water Content of Soil and Rock in Place by. Nuclear Methods
(Shallow Depth)
11. ASTM D 4318(1998) Liquid Limit, Plastic Limit, and Plasticity Index of Soils
B. AMERICAN WATER WORKS ASSOCIATION (AWWA)
1
1.02 DEFINITIONS
AWWA C600(1999)
Appurtenances
A. Hard Materials
Installation of Ductile -Iron Water Mains and their
02302=1
02302 - Excavation and Fill
1.03
J�V
Weathered rock, dense consolidated deposits, or conglomerate materials which are not included
in the definition of "rock" but which usually require the use of heavy excavation equipment,
ripper teeth, or jack hammers for removal.
B. Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or
foliated masses or conglomerate deposits, neither of which can be removed without
systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges,
or the use of backhoe -mounted pneumatic hole punchers or rock breakers; also large
boulders, buried masonry, or concrete other than pavement exceeding 1/2 cubic yard in
volume Removal of hard material will not be considered rock excavation because of
intermittent drilling and blasting that is performed merely to increase production.
C. Cohesive Materials
Materials ASTM D 2487 classified as GC, SC, ML, CL, MH, and CH. Materials classified
as GM and SM will be identified as cohesive only when the fines have a plasticity index
greater than zero.
D. Cohesionless Materials
Materials ASTM D 2487 classified as GW, GP, SW, and SP. Materials classified as GM
and SM will be identified as cohesionless only when the fines have a plasticity index of
zero.
SUBMITTALS
A. The following Test Reports are to be obtained and paid for by Contractor
1. Fill and backfill optimum density test where specified
2. Select material optimum density and gradation tests
3. Compaction density tests where specified
4. In-place density tests where specified
DELIVERY, STORAGE AND HANDLING OF MATERIALS
Perform in a manner to prevent contamination or segregation of materials.
PART 2 -PRODUCTS
2.01 SOIL MATERIALS
Free of debris, roots, wood, scrap material, vegetation, refuse, soft unsound particles, and deleterious
or objectionable materials. Unless specified otherwise, the maximum particle diameter shall be one-
half the lift thickness at the intended location.
A. Common Fill
Common shall consist of sandy -loam, sand, gravel, soft shale, or crushed stone. The
Engineer shall be the sole judge of what constitutes suitable and unsuitable material for
backfill from "on-site excavations."
02302 — Excavation and Fill
02302 - 2
B. Select Material
Select Fill shall consist of uniform, clean, free draining sand or sand and shell containing
less than 5% fines passing a No. 200 sieve. Laboratory test results of this fill shall be
submitted to the Engineer for his approval.
C. Topsoil
Natural, friable soil representative of productive, well -drained soils in the area, free of.
subsoil; stumps; rocks larger than 1 inch diameter; brush; weeds; toxic substances; and other
material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7.
PART 3 - EXECUTION OF WORK
3.01 SURFACE PREPARATION
A. Clearing and Grubbing
Unless indicated otherwise, remove trees, stumps, logs, shrubs, and brush within the clearing
limits. Remove stumps entirely. Grub out matted roots and roots over 3 inches in diameter to at
least 24 inches below existing surface.
B. Stripping
Strip existing topsoil to a minimum depth of 6 inches without contamination by subsoil material.
Remove all existing topsoil with organic roots and materials. Stockpile topsoil separately from
other excavated material and locate convenient to areas for soils exchange.
C. Unsuitable Material
All cleared, grubbed and demolished material deemed unsuitable shall be stockpiled on-site by
the Contractor for disposal by soils exchange with material over excavated from the proposed
stormwater management tract(s).
D. Disposal
In all areas where excavation is to be done, all earth, rock, muck and other materials shall
be removed and separated as to suitable and unsuitable material for backfill as defined
herein.
The Contractor shall temporarily stockpile all unsuitable fill and backfill material for later
disposal by soils exchange from suitable material to be over excavated from the on-site
stormwater management lakes. The stockpiled material shall be piled in an orderly manner
so as not to endanger the work or obstruct roadways or drainage within the designated job
site location. All unsuitable material shall be disposed of by over excavating an equal
volume of suitable material from the stormwater management lakes and subsequently
filling the over excavated volume with the unsuitable material. All over excavated material
shall be utilized and spread on the project site. Hazardous or waste materials shall not be
used in the unsuitable material to be exchanged. Waste, brush, refuse, stumps, roots,
timber, etc. shall be removed from the site and disposed of in an approved manner.
02302 - 3
02302 — Excavation and Fill
E. Removal of Muck, Rock and Other Unsuitable Material
All muck, rock , clay, marl, gravel, boulders, heterogeneous fill material and any other
organic or unsuitable "materials of excavation" encountered under pavement areas,
structures and utilities shall be excavated and removed. Also any "unforeseen obstacles"
such as buried trees or timbers, abandoned utilities, metal objects, concrete masses, or any
other type of debris encountered shall be removed.
All areas under proposed pavements or structures, which are indicated by testing to have
more than trace amounts of silt and/or clay within the top several feet of existing grade
shall be "proof rolled" using a vibratory compactor. Should the existing material
continuously yield or "pump" during the proof rolling, the Engineer shall be notified and a
determination made as to the amount of stripping needed to accomplish a stabilized
foundation.
Stripping shall be accomplished to clean in-place sand or other suitable material as
approved by the Engineer. Removal of unsuitable material within areas which are to
receive footings, slabs or other foundations shall be completed for the full area under such
structures and to ten feet minimum outside the maximum perimeter. Where pavement is to
be placed, said removal shall include all area under the surface and extend to the outside of
any shoulders, under any sidewalks and bike paths, or as directed by the Engineer.
All roots, stumps, logs, limbs, timbers, boulders, or any material which is not suitable for
backfill material shall be removed from the site promptly and excavated and disposed of by
the Contractor at his expense.
Removal of all "materials of excavation" and "unforeseen obstacles" will be paid for under
the heading of "Excavation and Hauling".
3.02 PROTECTION
A.
In
Sheeting and Bracing
Where excavations may endanger workmen, existing structures, utilities or other facilities,
it shall be the Contractor's responsibility to immediately install and maintain adequate
sheeting and bracing per OSHA specifications in order to protect said facility. No work
shall proceed in such excavations until the sheeting and bracing has been properly and
completely installed. The sheeting thus installed shall be removed as the work progresses
or, at the discretion of the Engineer, be cut off below finished grade and left in place.
Sheeting and bracing may be either steel or wood at the option of the Contractor.
Sheeting and bracing shall be installed in a manner that will allow for removal without
injuring or endangering workmen, the work, adjacent structures, and the like. Voids caused
by withdrawal of sheeting shall be promptly and completely filled with sand and
compacted to a degree equal to the surrounding soil.
Drainage and Dewatering
Provide for the collection and disposal of surface and subsurface water encountered during
construction.
02302 — Excavation and Fill
02302 - 4
1. Drainage
So that construction operations progress successfully, completely drain construction
site during periods of construction to keep soil materials sufficiently dry. The
Contractor shall establish/construct storm drainage features (ponds/basins) at the
earliest stages of site development, and throughout construction grade the construction
area to provide positive surface water runoff away from the construction activity and/or
provide temporary ditches, swales, and other drainage features and equipment as
required to maintain dry soils. When unsuitable working platforms for equipment
operation and unsuitable soil support for subsequent construction features develop,
remove unsuitable material and provide new soil material as specified herein. It is the
responsibility of the Contractor to assess the soil and ground water conditions
presented by the plans and specifications and to employ necessary measures to permit
construction to proceed.
2. Dewatering
All water encountered during excavation shall be promptly and completely removed to
a depth below the exposed excavation surface sufficient to provide a dry working
surface. The excavation shall be kept dry until the work to be built or placed therein
has been completed as specified. Dewatering shall be done in a manner that will not
cause sloughing or caving of the excavation walls. Water from said dewatering shall
be disposed of in a manner as will not result in violations of State water quality
standards in receiving waters, nor cause injury to public health nor to public or private
property, nor to the work completed or in progress. Any and all damage caused by
dewatering shall be promptly repaired by the Contractor at no cost to the Owner. The
receiving point for water from said operation shall be approved by the applicable
regulatory agency and the Engineer. The Contractor is responsible for obtaining all
required permits and any other approval necessary.
C. Underground Utilities
Location of the existing utilities indicated on the Drawings are approximate only. The
Contractor shall physically verify the location and elevation of the existing utilities
indicated prior to starting construction. The Contractor shall contact Sunshine One Call at
1-800-432-4770, 48 hours prior to commencement of excavation for assistance in locating
existing utilities.
D. Machinery and Equipment
Movement of construction machinery and equipment over pipes during construction shall
be at the Contractor's risk. Repair, or remove and provide new pipe for existing or newly
installed pipe that has been displaced or damaged.
3.03 EXCAVATION
Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the
specified requirements for the material type required at the intended location. Keep excavations free
from water. Excavate soil disturbed or weakened by Contractor's operations, soils softened or made
unsuitable for subsequent construction due to exposure to weather. Refill with common fill and
compact to 95 percent of ASTM D 1557 maximum density. Unless specified otherwise, refill
excavations cut below indicated depth with common fill and compact to 95 percent of ASTM D
1557 maximum density.
02302 = 5
02302 — Excavation and Fill
3.04
A. Pipe Trenches
Excavate trenches to uniform width, sufficiently wide to provide ample working room and
a minimum of 9 to 12 inches of clearance on both sides of the pipe or conduit. Grade
bottom of trenches to provide uniform support for each section of pipe after pipe bedding
placement.
B. Excavate trenches to depth indicated or required to establish indicated slope and invert
elevations and to support bottom of pipe or conduit on undisturbed soil.
1. Where rock is encountered, cavy excavation 6 inches below required elevation and
backfill with a 6 -inch layer of tamped sand or gravel prior to installation of pipe.
2. For pipes or conduit less than 6 inches in nominal size, and for flat-bottomed, multiple -
duct conduit units, do not excavate beyond indicated depths. Hand -excavate bottom
cut to accurate elevations and support pipe or conduit on undisturbed soil.
3. For pipes and equipment 6 inches or larger in nominal size, shape bottom of trench to
fit bottom of pipe for 90 degrees (bottom 1/4 of the circumference). Fill depressions
with tamped sand backfill. At each pipe joint, dig bell holes to relieve pipe bell of
loads and to ensure continuous bearing of pipe barrel on bearing surface.
FILLING AND BACKFILLING
Fill and backfill to contours, elevations, and dimensions indicated. Compact each lift before placing
overlaying lift.
B. Unsuitable Material Replacement
Fill material shall be placed and spread evenly in layers not to exceed twelve inches before
compaction. All fill material shall be free from vegetable matter, wood, and other
deleterious substances, and shall not contain rocks or clods having a diameter of more than
three inches.
B. Pre -fill Compaction
Should the pre -fill surface elevation be below that required for the base of proposed
building foundations or paving subgrade, the areas within road rights -of -ways, under
parking areas, and the areas under and within five feet of proposed buildings shall be
precompacted. This precompaction shall be performed equally on existing ground and on
surfaces which have been excavated to remove unsuitable material. The top one foot of
said areas shall be compacted to a minimum density of 95% of maximum as determined by
AASHTO T-180. The maximum spacing between density tests shall be 150 feet.
B. Compaction
Backfill material shall be compacted to 95% of maximum density per AASHTO T-180.
Equipment suitable and adequate for uniform compaction to the specified density shall be
used for backfill operations subject to the approval of the Engineer. All compaction
equipment shall be in good working order and any worn or defective equipment shall be
immediately replaced or repaired.
02302 - 6
02302 — Excavation and Fill
B. Soil Stability and Compaction Control
The Contractor shall arrange to have sufficient soil tests made by an independent testing
laboratory selected by the Engineer to demonstrate conformance of his work with the
stability and compaction levels required by these specifications. Compaction tests shall be
taken at intervals listed herein or as deemed necessary by the Engineer.
Any proposed alternative test methods to those specified herein must be approved by the
Engineer prior to testing. At the request of the Engineer, the Contractor shall provide such
documentation of a proposed alternative test method as the Engineer may require to
evaluate the method for approval.
In no case shall the Contractor proceed with construction on compacted material until the
tests prove satisfactory and approval is given by the Engineer.
In general, at least one test for maximum dry density/optimum moisture content shall be
performed on a representative sample of each inherently different material to be used for
compacted backfill or embankment fill. For material of uniform composition and textural
class, a minimum of one test per 200 cu. yd. of material shall be performed at the point of
use.
Tests for in-place density (percent compaction) shall be taken at locations designated by the
Engineer. The Contractor shall have density tests taken in four (4) separate locations. Each
location shall be tested in lifts not to exceed 12 -inches in thickness.
E. Trench Backfilling
Backfill as rapidly as construction, testing, and acceptance of work permits. Place and
compact backfill under structures and paved areas in 12 inch lifts to top of trench and in 6
inch lifts to one foot over pipe outside structures and paved areas.
1. Bedding Requirements
Except as specified otherwise in the individual piping section, provide bedding for
buried piping in accordance with AWWA C600, Type 4, except as specified herein.
Backfill to top of pipe shall be compacted to 95 percent of ASTM D 698 maximum
density. Plastic piping shall have bedding to spring line of pipe. Provide ASTM D
2321 materials as follows:
Class I: Angular, 0.25 to 1.5 inches, graded stone, including a number of fill materials
that have regional significance such as coral, slag, cinders, crushed stone, and crushed
shells.
Class 11: Coarse sands and gravels with maximum particle size of 1.5 inches, including
various graded sands and gravels containing small percentages of fines, generally
granular and noncohesive, either wet or dry. Soil Types GW, GP, SW, and SP are
included in this class as specified in ASTM D 2487,
3.05 COMPACTION
Expressed as a percentage of maximum density. Determine in-place density of existing subgrade; if
required density exists, no compaction of existing subgrade will be required.
02302 = 7
02302 - Excavation and Fill
3.06
3.07
A. General Site Backfill
Compact underneath areas designated for vegetation and areas outside the 5 foot line from
existing or proposed structures to a minimum 95 percent of maximum density per ASTM
D 1557,
B. Backfill Under Pavements and Around Structures
Compact underneath areas designated for surface pavements and around proposed
structures to a minimum 98 percent of maximum density per ASTM D 1557,
FINISH OPERATIONS
A. Grading
Finish grades as indicated on the plans to within two inches. In areas where sodding is
required, finished soil grade shall be set 3 -inches below the plan elevation to compensate
for sod thickness.. For existing grades that will remain but which were disturbed by
Contractor's operations, grade as directed.
B. Protection of Surfaces
Protect newly graded areas from traffic, erosion, and settlements that may occur. Repair or
reestablish damaged grades, elevations, or slopes.
DISPOSITION OF SURPLUS MATERIAL
The Contractor may temporarily stockpile all unsuitable fill and backfill material for later disposal.
The stockpiled material shall be piled in an orderly manner so as not to endanger the work or
obstruct roadways or drainage within the designated job site location. All unsuitable material shall
be disposed of by hauling off-site by the Contractor to a suitable disposal location. Waste, brush,
refuse, stumps, roots, timber, etc. shall be removed from the site and disposed of in an approved
manner.
Excess suitable backfill material is the property of the Owner. The Owner shall determine the
ultimate disposition of the material and may require the Contractor to relocate (haul) the material to a
site within a 10 mile drive of the project site at no additional cost to the Owner.
END OF SECTION
02302 = 8
02302 — Excavation and Fill
SECTION 02400
DIRECTIONAL BORE CROSSINGS
1. GENERAL
A. Scope
The work to be performed under this item shall include the furnishing of all H.D.P.E. pipe
and fittings for the job, equipment and labor required for the joining and installation of the
pipe as herein described and as shown on the Plans. The CONTRACTOR shall perform all
pipe work, directional drilling, backpulling and related work required for the construction of
the directional bore in accordance with the provisions set forth under the applicable items of
this Section.
B. References
Standards applicable in this Specification shall be:
1) American Society of Testing and Materials (ASTM)
a) ASTM D 2657 — Practice for Heat -Joining of Polyolefin Pipe and Fittings
b) ASTM D 3261 — Standard Specification for Butt Fusion Polyethylene (PE)
Plastic Fittings for Polyethylene (PE) Plastic Pipe and Tubing
c) ASTM D 3350 — Standard Specification for Polyethylene Plastics Pipe and
Fittings Material
d) ASTM F 714 — Standard Specification for Polyethylene (PE) Plastic Pipe (SDR -
PR) Based on Outside Diameter
e) ASTM F 1962 — Use of Maxi -Horizontal Directional Drilling for Placement of
Polyethylene Pipe or Conduit Under Obstacles, Including River Crossings
2) Plastics Pipe Institute
a) Plastic Pipe Institute Technical Report TR — 3, Policies and Procedures for
Develogi:ng Recommended Hydrostatic Design Stresses for Thermo-Dlastic Pipe
Materials
b) Plastic Pipe Institute, TR -31, "Underground Installation of Polyolefin Pipe
c) Plastics Pipe Institute, Handbook of Polyethylene Pipe, Chapter on Polyethylene
Joining Procedures, Washington, DC.
3) American Association of State Highway and Transportation Officials
a) AASHTO T-180 Density Relations of Soils using a 10 lb. Rammer and an 18 -
inch drop
02400 -1
02400 — Directional Bore Crossings
C.
4) American Water Works Association (AWWA)
a) AWWA C906 — Polyethylene (PE) Pressure Pipe and Fittings, 4 in. through 63
in., for water distribution
Quality Assurance
1) Quality
All materials shall be new and properly manufactured, and shall conform to the
requirements of any referenced standards. All materials shall be standard first -grade
quality produced by expert workmen and be intended for the use for which they are
offered. Materials which, in the opinion of the ENGINEER, are inferior or of a
lower grade than indicated, specified or required will not be acceptable.
2) Source Limitations
To the greatest extent possible for each unit of Work, the CONTRACTOR shall
provide products, materials, or equipment of a singular generic kind from a single
source.
3) Compatibility of Options
Where more than one choice is available as options for CONTRACTOR'S selection
of a product, material, or equipment, the CONTRACTOR shall select an option,
which is compatible with other products and materials already selected.
Compatibility is a basic general requirement of product/material selections.
4) CONTRACTOR/INSTALLER (C/I) Qualifications
For a C/I to be considered as an acceptable C/I, the C/I must have had at least three
(3) years active experience in the commercial installation of directional bored
polyethylene pipe and must have installed a minimum of 10,000 linear feet or 20
sections of successful large diameter (12" or greater) polyethylene pipe installations
in the United States.
To be acceptable, the C/I shall hold an active CERTIFIED or REGISTERED
UNDERGROUND UTILITIES CONTRACTOR LICENSE with the State of
Florida Department of Professional Regulation Construction Industry Licensing
Board. A copy of the CERTIFIED UNDERGROUND UTILITIES CONTRACTOR
LICENSE shall be submitted prior to excavation.
5) Right of Rejection
The ENGINEER or the OWNER, shall have the right, at all times and places, to
reject any articles or materials to be furnished hereunder which, in any respect, fail
to meet the requirements of the Contract Documents, regardless of whether the
defects in such articles or materials are detected at the point of manufacture or after.
completion of the Work at the site.
02400 — Directional Bore Crossings
02400 - 2
The CONTRACTOR shall promptly remove rejected articles or materials from the
site of the Work after notification of rejection. All costs of removal and replacement
of rejected articles or materials as specified herein shall be borne by the
CONTRACTOR.
D. Submittals
1) Along with the required bid and contract submittals, the CONTRACTOR shall
submit to the ENGINEER, for review and approval, the items a and b as listed
below:
a) Five (5) sets of the manufacturer's shop drawings, catalog cut sheets,
technical data, installation requirements and recommended methods, and
recommended repair methods. Upori approval by the ENGINEER, the
manufacturer's recommendations shall become the basis for acceptance or rejection
of actual methods of installation used in the work.
b) Certification of the manufacturer's compliance with the specified standards
and specifications for all materials.
The CONTRACTOR shall not permit any materials to be brought onto the job site
prior to obtaining approval from the ENGINEER. No pipe shall be delivered
without prior notification to the ENGINEER. Each pipe section shall be subject to
inspection by the ENGINEER immediately before it is installed. Any pipe section
judged to be defective may be rejected.
E. Safety
The CONTRACTOR shall cant' out his operations in strict accordance with all OSHA and
manufacturer's safety requirements. Particular attention is drawn to those safety
requirements involving working with hazardous/combustible material, (if needed), working
in traffic areas, entering confined spaces, and operating heavy machinery.
F. Warranty
In addition to the CONTRACTOR'S one-year warranty, the pipe shall be certified by the
manufacturer for specified material properties for this particular job. The manufacturer
warrants the pipe to be free from defects in raw materials for one year from the date of
acceptance. During the warranty period, any defects that affect the integrity or strength of
the pipe shall be repaired at the CONTRACTOR'S expense in a manner mutually agreed by
the OWNER and the CONTRACTOR.
2. MATERIALS
A. High Density Polyethylene Pipe (H.D.P.E.)
Pipe shall be new, unused, sections of polyethylene pipe having a nominal density of 0.955.
The polyethylene resin used to manufacture the pipe shall have a "Plastic Pipe Institute"
02400 - Directional Bore Crossings
02400=3
3.
material designation of PE 3408, with an ASTM D3350 cell classification of 34544C. The
pipe shall be black in color, containing approximately 2 percent U.V. stabilizer. The pipe
shall be co -extruded with a color coded sheath or have three (3) sets of colored lines at the
120° quadrants. The pipe shall be designed for a working pressure of 160 psi. Pipe shall be
extruded to the minimum wall thickness described in AWWA C906 for DRI 1. Pipe outside
dimensions shall meet that of ductile iron pipe size (D.I.P.S.). Pipe shall be provided in
nominal 40 foot long sections.
During the extrusion process, the HDPE pipe shall be continuously marked with durable
printing including the following information:
1) Nominal Size
2) Dimension Ratio
3) Manufacturer Name and Product Series
4) Cell Class
5) ASTM Basis
6) Pipe Test Category
7) Plant Identification
8) Production Date
B. Fittings
HDPE fittings shall be in accordance with ASTM D 3261 and shall be manufactured by
injection molding, a combination of extrusion and machining, or fabricated from HDPE pipe
conforming to this specification. The fittings shall be designed for a working pressure of
160 psi. The fittings shall be manufactured from the same resin type and cell classification
as the pipe itself. The fittings shall be homogeneous throughout and free from cracks, holes
foreign inclusions, voids, or other injurious defects. All fittings shall be constructed to have
a minimum D.R. 11 sidewall thickness, with a D.I.P.S. outside diameter.
C. Joints
Sections of polyethylene pipe shall be joined at the job site by the butt fusion process into
one continuous length. The joining process shall be the heat fusion method and shall be
performed in strict accordance with the pipe manufacturer's recommendations. The heat
fusion equipment used in the joining procedures should be capable of meeting all conditions
recommended by the pipe manufacturer.
EXECUTION OF WORK
Installation of the polyethylene pipeline shall be conducted using "medi" — HDD or "maxi" — HDD
equipment of intermediate size and capabilities. 'The installation guidelines and practices governing
this installation shall follow that of the "maxi" — HDD category rather than "mini" — HDD practices.
A. Preparation
1) Clearing — The CONTRACTOR shall perform all clearing necessary, where
applicable for the proper installation of the pipe at the locations shown on the
drawings. Plantings, shrubbery, trees, utility poles or structures subject to damage
02400 - 4 02400 — Directional Bore Crossings
resulting
from the
excavation shall be
transplanted, relocated, braced, shored or
otherwise
protected
and preserved unless
otherwise directed by the Engineer.
2) Delivery and Receiving Pipe — The pipe shall be delivered no more than 5 working
days prior to joining and installation. Pipe and fittings may be stored in the right-of-
way, adjacent to the boring path in the right-of-way only when they may be
maintained outside the roadway "clear zone" as determined by F.D.O.T. standards.
Appropriate unloading and handling equipment of adequate capacity must be used to
unload the truck. Safe handling and operating procedures must be observed.
Pipe and fittings must not be rolled or pushed off the truck.
When using a forklift, or forklift attachments on equipment such as articulated
loaders or bucket loaders, lifting capacity must be adequate at the load center on the
forks. Forklift equipment must be rated for the maximum lifting capacity at a
distance from the back of the forks.
Lifting equipment such as cranes, extension boom cranes, and side boom tractors,
should be hooked to wide web choker slings that are secured around the load. Only
wide web slings should be used. Wire rope slings and chains can damage
components and shall not be used. Spreader bars shall be used when lifting pipe
longer than 20"
Individual pipes may be stacked in rows. Pipes shall be laid straight, not crossing
over or entangled with each other. The base row must be blocked to prevent
sideways movement or shifting. The pipe sections shall be stacked no higher than 2
rows.
B. Joining, Pive and Stub -End
1) Joining and stringing of the pipe shall be accomplished in one continuous operation.
The joining shall begin promptly at the beginning of the work day and continue until
completed. Pipe joining and directional boring shall be the only on-site operation
allowed to continue beyond 5:00 P.M. The CONTRACTOR shall have all traffic
control devices, lane closures and signage in place and ready for use prior to start-
up.
2) Joining shall be accomplished using a hydraulically operated, microprocessor
controlled heat fusing machine, specifically designed to handle the project pipe O.D.
The operator shall have had a minimum 3 years experience in the process of
operating H.D.P.E. butt -fusion machines capable of joining at least 8 -inch diameter
pipe.
3) Joining shall generally follow these procedures:
a) Securing
Each component that is to be fused must be held in position so that it will not
move unless a clamping device moves it.
02400 — Directional Bore Crossings
02400 - 5
b) Face
The component ends must be faced to establish clean, parallel mating surfaces.
The equipment shall incorporate a rotating planer block in its facer to
accomplish this goal. Facing shall be continued until a minimal distance exists
between the fixed and movable jaws of the machine and the facer is locked
firmly and squarely between the jaws. This operation shall provide for a
perfectly square face, perpendicular to the pipe centerline on each component
end and with no detectable gap.
c) Alignment
The pipe profiles must be rounded and aligned with each other to minimize
mismatch (high -low) of the pipe walls. This shall be accomplished by adjusting
the clamping jaws until the outside diameters of the pipe ends match. The jaws
must not be loosened or the pipe may slip during fusion.
d) Melting
Ends of the components shall be heated to the pipe manufacturer's
recommended temperature, interface pressure, and time duration. By doing so,
the heat will penetrate into the pipe ends and a molten "bead" of material will
form at the pipe ends. Heating tools, which simultaneously heat both pipe ends,
shall be used to accomplish this operation. These heating tools shall be
furnished with thermocouples to measure internal heater temperature so that the
operator can monitor the temperature before each joint is made. The heater
faces, which come into contact with the pipe, shall be coated by the
manufacturer to prevent molten plastic from sticking to the heater faces.
e) Joinin¢
After the pipe ends have been heated for the proper time and to the proper
temperature, the heater tool shall be removed and the molten pipe ends shall be
brought together with sufficient pressure to properly mix the pipe materials and
form a homogeneous joint. The pipe manufacturer's instructions may specify
either interface pressure or bead size of molten material as a guide for a proper
joint.
f) Holding
The molten joint must be held immobile under pressure until cooled adequately
to develop strength. The proper cooling times for the joint are: material, pipe -
diameter, and wall -thickness dependent; and shall be as recommended by the
pipe manufacturer.
C. Strinains of Pipe and Trace Wire
The CONTRACTOR shall have appropriate rollers and a winch/cable system adequately
sized to pull the joined pipe sections into the proper position for installation.
02400 — Directional Bore Crossings
02400 - 6
Where possible, the entire length of polyethylene pipe to be installed shall be joined and
strung beyond the entrance of the bore path. hi no case shall the ingress and/or egress, to
public or private property be completely blocked. Should the stringing of an entire section
of pipe block such ingress and/or egress, the section of pipe shall be segmented in maximum
lengths beyond the entrance of the bore path.
Once strung out for insertion into the bore hole, the trace wire specified for all piping shall
be laid along the top of the pipe segment and taped to the pipe along its entire length. There
shall be no discontinuity in the trace wire, and where a splice is needed, it shall be prepared
prior to beginning the pipe back pull.
D. Separation and Clearance
1) The bore depth shall equal or exceed 10 times the bore size under F.D.O.T.
pavements.
2) When installed outside of pavement, the off set parallel to the pavement edge must
be at least 3 'h times the bore size clearance from vitrified clay pipe sanitary sewer
and any gas main.
3) Bore installations shall maintain at least 3 '/2 times the bore size clearance from
vitrified clay pipe sanitary sewer and any gas main.
4) Bore installations shall maintain at least 18 -inches of separation between any sewer
line crossings.
E. Directional Boring
Boring of the pipeline hole shall follow applicable sections of the recommended standards of
ASTM F 1962 "Use of Maxi -Horizontal Directional Drilling for Placement of P.E. Pipe or
Conduit Under Obstacles, Including River Crossings". The CONTRACTOR shall have
adequately sized boring/pullback equipment, self-contained drilling fluid recycling system
equipment and a properly trained crew with classroom and field experienced personnel
manning the primary job positions.
1) Machine Size & Capability — The size and capacity of the drilling equipment must
be compatible with the thrust and torque required to perform the drilling, reaming,
and pipe pullback operations. The estimated forces applied to the pipe_ may be
considered a minimum equipment requirement.
The CONTRACTOR'S equipment shall be capable of drilling through consolidated
or loose sands and clay as well as cemented layers of lime rock (commonly known
as "cap rock") that may vary from loose fragments to 2 or 3 foot thick sections.
The CONTRACTOR'S equipment must include a self-contained, mobile slurry
system, capable of pumping and recycling the drilling fluid. Cuttings from the
drilling process shall be hauled and disposed of by the CONTRACTOR. Should the
County desire the cuttings for fill, the CONTRACTOR shall haul the material to the
desired disposal site. The disposal site shall be within a 10 mile drive from the
furthest bore location. All drilling fluid, mud, clay, etc. shall be hauled and disposed
of by the CONTRACTOR at an acceptable disposal site.
02400 = 7
L
02400 - Directional Bore Crossings
F
2) Drill Unit Positioning — The drill rig unit shall be positioned within the right-of-way
or Owner's property to provide the desired bore route and pipe depth. Proper
equipment anchoring is especially important for the existing sandy soils.
3) Drill Rods — The drill rods should be as least as strong as the equipment capability.
The drill rod capabilities shall also be compatible with the planned bore route with
respect to cumulative fatigue stresses. .
4) Drilling Fluid Usage — Drilling fluid shall be used to provide lubrication during the
pilot boring, reaming and pullback operations to reduce the required torque and
thrust of pullback loads. In addition, the drilling fluid shall stabilize the bore hole,
cool the drill head (and internal circuitry), and remove cuttings and spoils. The crew
must be trained in the proper use of drilling fluids and the appropriate types for
various ground conditions. The Engineer shall be notified if excessive drilling fluid
pressures or volumes are noticed.
5) Location and Tracking — In order to maintain the actual bore along the planned path,
the pilot bore must be carefully tracked, and path confirmation established at least
once each 15 ft interval. For paths with horizontal and vertical turns, or in critical
areas including the vicinity of other obstacles, shorter intervals of 10 ft shall be used.
Any misdirection of the drill head shall be corrected immediately.
6) Back Reaming — Where necessary, back reaming shall be performed to produce a
hole size sufficiently large to readily install the pipe. Back reaming shall allow the
bore hole to be created in stages, reducing the required torque and thrust loads at the
machine. Back reaming operations shall help ensure that the capability of the
machine is not exceeded due to the combined forces of increasing the hole diameter
while pulling the pipe. Appropriate cutters and compactors compatible with the soil
conditions shall be employed including proper usage of drilling fluid. Back reaming
shall be used to reduce the possibility of voids or surface heaving or settlement,
including unanticipated drilling fluid appearances. Hole diameter increments should
be restricted to approximately 10 -inches or less during a single pass. The final hole
diameter shall be 20% but in no case larger than 50% greater than the outer diameter
of the pipe to provide clearance for pipe grips, allow spoils flow, and reduce the
required loads during the pipe pullback operation. During back reaming, additional
drill roads must be available at the pilot bore exit that are connected to a swivel at
the rear of the reamer and pulled into the hole to maintain the path.
Pipe Pullback
1) Gripping of Pipe — Due to the distance of the operation and the high pullback loads
generated, secure gripping procedures must be used. Basket -type or internal only
grips will not be allowed. The gripping method selected must allow the full tensile
rating of the pipe to be developed. Appropriate types may include an
internal/external clamping or bolting device, or a fused PE pipe adapter with a built-
in pulling eye. In the latter case, a smaller diameter section of the adapter may serve
as a breakaway link protecting the main section of pipe.
2) Swivel — A swivel is required between the reamer or compactor preceding the pipe
to prevent the transmission of torsional loads to the pipe. The rating of the swivel
02400 — Directional Bore Crossings
02400 - 8
should be larger than the lower of the pull force capability of the drill rig or the total
strengths of the pipe to be installed, but not excessively greater.
3) Breakaway Link — In general, the recorded pulling forces as indicated at the drill rig
will exceed the tensions experienced by the pipe or conduit throughout most of the
pullback process. It is recommended that individual breakaway links be provided
between the main swivel and the grip at the pipe, to ensure that the pipelines are
installed within allowable load levels. Broken links will require removal of the pipe
from the entry end. If a breakaway swivel is used as the breakaway link, and not
specifically designed for direct exposure with soil, this item should be cleaned well
after each application. The use of such a breakaway swivel does not eliminate the
need for the main swivel described earlier.
4) Handling the Pipe — Extreme care must be exercised when handling the pipe to
ensure that it is not subject to excessively sharp bends which may cause a kink or
other damage to the pipe. Particular areas of concern typically include the pipe entry
and exit points. It is important to minimize bending of the pipe as it enters the bore
hole, and to ensure low friction on the portion of the pipe outside the hole. This may
be accomplished by the use of appropriate lifting equipment and roller stands to
reduce friction. Due to the potentially high tensile load at the pipe exit, it is
especially important to avoid sharp bends at this point.
G. As -Built Drawings and Information
A record of the actual as -built bore path, including plan and profile views and vertical and
horizontal deviations, indicating the relation to the planned path, must be submitted to the
Engineer. Any information obtained during the initial bore regarding soil characteristics,
etc. should be added. The experiences gained during the initial bore may be used to provide
guidance for the backreaming operating, as well as for subsequent operations in the project
area. Additional information should also be included, such as steering or correction
commands, drilling fluid usage, and the type of drill head being used. Regarding the
reaming and pullback operations, the pipe insertion velocity, duration, type and size of
reamers (cutters or compactors), final bore hole size, drilling fluid usage, and required
pullback forces should be recorded.
H. Connection to Upstream and Downstream Piping
Where the directional bored pipe is joined to bell and spigot, mechanical, or other types of
unrestrained joints, the forces caused by shortening of the polyethylene pipe when under
pressure must be counteracted per AWWA Technical Bulletin No. 8. The joint between the
polyethylene pipe and any push type connection shall be mechanically restrained as well as
the appropriate number of upstream and downstream joints as indicated on the Drawings.
I. Completion and Cleanup
1) Pipe Cut -Off and Cleanup — The pipe shall be allowed to achieve mechanical and
thermal equilibrium with its surroundings prior to cutting at either end. Premature
cutting of the pipe may allow the ends to shrink back into the hole. The pipe may be
cut after it has been verified that there has been insignificant movement at the pipe
entry end and negligible residual tensile load at the drill rig end. If the bore ends are
02400 - 9
02400 — Directional Bore Crossings
to remain in place for more than 48 hours prior to final connection and burial, the
pipe ends shall be cut off above grade, and an appropriate plug shall be installed
after thorough cleaning of the pipeline.
2) Pipe Cleaning — The CONTRACTOR shall utilize a hydraulic cleaning and vactor
truck to remove all cuttings and drilling fluid from the pipe.
3) Site Cleanup — After inspection and approval by the Owner or his representative, the
surface area disturbed by construction of this project must be restored to its original
condition. The site must be cleaned of equipment, tools, and spoils. All drilling
fluid must be cleaned from the site or its vicinity and properly disposed of.
4) Disposal — Pipe cuttings shall be disposed of by the CONTRACTOR at a solid waste
disposal site or other disposal area, acceptable to the Owner.
END OF SECTION
02400 - Directional Bore Crossings
;6'Z41111 [%
I L
SECTION 02440
CONCRETE DRIVEWAYS, CURBS, SLABS ON GRADE AND SIDEWALKS
PART 1 -- GENERAL
1.01 SUMMARY
A. Provide all labor, materials, equipment and transportation required for the construction of
the concrete driveway, curbs, slabs on grade, and walks to the lines and grades as shown
on the Drawings and specified herein.
1.02 QUALITY ASSURANCE
A. Testing and inspections: See Section 02752.
B. Materials and methods shall comply with the standards indicated.
C. Obtain concrete from a plant currently certified to comply with approval of requirements of
the Concrete Materials Engineering Council, or the Florida Department of Transportation,
or the Check List for Plant Certification of the National Ready Mixed Concrete
Association.
1.03 SUBMITTALS
The following shall be submitted to the Engineer:
A. Concrete mix design.
B. Product literature for joint sealer, joint filler and curing compound.
C. Product literature for synthetic fiber reinforcement.
D. Concrete cylinder strength test results.
E. Slump test results.
F. Ready mixed concrete: Provide delivery tickets orweigh master's certificate perASTM C-
94, including weights of cement and each size of aggregate. Amount of water in
aggregate, and amount of water added at the plant. Write in amount of water
added on the job.
PART 2 ==PRODUCTS
2.01 MATERIALS
A. Concrete: Concrete for slabs on grade, walks, driveway, and curbs shall be structural
Class I that conforms to the requirements of FDOT Standard Specifications for Road and
Bridge Construction, 2007, Section 346, Portland Cement Concrete, with 28 -day
compressive strength of 3000 psi unless shown otherwise on the Drawings.
02440=1 02440 — Concrete Driveways, etc...
Be Admixtures are permitted in accordance with FDOT Standard Specifications for Road
and Bridge Construction, 2007, Section 346-2.5.
Co Except where shown on the plans, slabs on grade, and walks shall be reinforced with
Fibermesh, as manufactured by SI Concrete Systems, or approved equal.
D. Use forms of either wood or metal with a depth equal to the Plan dimensions forthe depth
of concrete being deposited against them, as shown on the construction drawings. Forms
shall be straight, free from warp or bends, and of sufficient strength when staked to resist
the pressure of the concrete without deviation from line and grade. Clean the forms each
time they are used, and oil or saturate with water prior to placing the concrete.
E. Preformed Joint Filler: Preformed joint filler shall be nonextruding and resilient
bituminous type and shall conform to the requirements of Section 932-1, FDOT Standard
Specifications for Road and Bridge Construction, 2007.
F. Joint Sealer: Joint sealer shall conform to the requirements of Section 932-1.2, FDOT
Standard Specifications for Road and Bridge Construction, 2007,
G. Membrane Curing Compound: Membrane curing compound shall conform to the
requirements of Section 925.2, FDOT Standard Specifications for Road and Bridge
Construction, 2007,
PART 3 -- EXECUTION
3.01 PREPARATION
A. The foundation shall be excavated or backfilled to the required depth. Compact the
foundation material upon which the slabs on grade or sidewalk is to be set to, at least 98
percent of the maximum density as determined by AASHTO T-180 or 100 percent of the
maximum density as determined by AASHTO T-99,, with an even surface, true to line,
grade and cross section, and soaking wet at the concrete is placed.
Be Forms: Set the forms straight, free from wrap or bends, and true to line and grade.
C. Slipforming: The slipforming method will be allowed, provided that an acceptable finished
product, true to line, grade, and cross section is consistently produced.
3.02 MIXING CONCRETE
A. Concrete shall be mixed in accordance with FDOT Standard Specifications for Road and
Bridge Construction, 2007, Section 346-7.
3.03 INSTALLATION
A. Placing Concrete:
02440-2 02440 — Concrete Driveways, etc...
J
1. The concrete shall be distributed on the subgrade to such depth that, when it is
consolidated and finished, the thickness required by the Drawings will be obtained
at all points and the surface will at no point be below the grade specified for the
finished surface. The concrete shall be deposited on the subgrade in a manner
which will require as little rehandling as possible. Placing of the concrete shall be
continuous between transverse joints, without the use of intermediate bulkheads.
2. Concrete shall be thoroughly consolidated against and along the faces of all forms
by means of vibrators. Vibrators (if needed) shall not be permitted to come in
contact with the subgrade or a side form. Vibration at any one location shall not
continue so long as to produce puddling or the accumulation of excessive grout on
the surface. In no case shall the vibrator be operated longer than 15 seconds in
any one location.
B. Striking -Off, Consolidating And Finishing Concrete:
1. Immediately after the placing, the concrete shall be struck off, consolidated and
finished, to produce a finished product conforming to the cross section, width and
surface finish required by the Drawings and Specifications.
2. After the concrete has sufficiently set a minimum of 12 hours, the Contractor shall
remove the forms and shall backfill the space on each side. The earth shall be
compacted and graded in satisfactory manner without damage to the concrete
work. Honeycombs shall be filled with sand cement mortar. Plastering will not be
allowed on the face of the curb. Rejected curb, curb and gutter or valley gutter
shall be removed and replaced without additional compensation.
Co Final Finish: As soon as the water sheen has disappeared and just before the concrete
becomes nonplastic, a light broom finish shall be given to the surfaces, except curbs.
D. Joints: Joints shall be constructed where shown on the DRAWINGS.
1. Transverse Construction Joints: Transverse construction joints shall be
constructed at the end of all pours and at other locations where the pouring
operations are stopped for as long as 30 minutes. Construction joints, however,
shall not be placed within ten feet of any other transverse joint or of either end of a
section of curb. If sufficient concrete has not been placed to form a slab at least
ten feet long, the excess concrete, back to the last preceding joint, shall be
removed. The joints shall be the full depth of the pavement and shall be formed
by placing a wood or metal bulkhead accurately and securely in place, in a plane
perpendicular to the profile and center line of the pavement.
2. Transverse Contraction Joints: Transverse contraction joints shall be constructed
along curbs, slabs on grade, and walks at the intervals specified in 3.03 D4 below,
where shown on the DRAWINGS, and shall consist of planes of weakness created
by sawing the surface of the pavement or tooling the joint.
a. It shall be the Contractor's responsibility to see that the sawing
equipment does not damage the curb, slabs on grade, or walk and
to saw the transverse contraction joints as soon as the concrete has
hardened to the degree that tearing and raveling are not excessive
and within a maximum time of 12 hours after the pour. If, at any
time, uncontrolled cracking occurs, the Contractor will be required to
replace the affected sections and modify his methods.
02440=3 02440 — Concrete Driveways, etc...
L
3. Transverse Expansion Joints: One half-inch expansion joints shall be
formed by placing preformed joint filler topped with joint sealant at the ends
of each radius return, around all structures, and at intervals specified in
3.03 D4 below and as shown on the DRAWINGS.
4. Spacing of transverse contraction and expansion joints.
Walk,Slab Width Contraction Joint Expansion Joint
Spacinq Spacing
4' 4' 40'
5' 5' 40'
6' 6' 42'
8' 8' 40'
10' 10' 40'
Provide isolation joints between slabs on grade and sidewalks adjacent to
fixed objects including curbs, inlets, etc.
E. Finishing
1. Strike off the concrete by means of a wood or metal screed used
perpendicular to the forms in order to obtain the required grade, and
remove surplus water and laitance.
2. Broom -finish the concrete surface. The surface variations shall not be
more than 1/4 inch under a 10400t straight edge. Carefully finish the edge
of the slabs on grade and sidewalk with an edging tool having a radius of
1/2 inch.
F. Curing:
1. After the finishing operations have been completed and as soon as the
concrete has hardened sufficiently that marring of the surface will not occur,
the entire surface and the edges of the newly placed concrete shall be
covered and cured with membrane curing compound.
2. Curing compound shall be uniformly applied to the surfaces to be cured, in
a single coat, continuous film, at the rate of one gallon to not more than 200
square feet, by a mechanical sprayer.
3. Curing compound shall not be applied during periods of rainfall. Curing
compound shall not be applied to the inside faces of joints to be sealed.
Should the film become damaged from any cause within the required curing
period, the damaged portions shall be repaired immediately with additional
compound. Upon removal of side forms the sides of the slabs exposed
shall immediately be coated to provide a curing treatment equal to that
provided for the surface.
G. Backfilling and Compacting: After the concrete has set sufficiently, refill the spaces
adjacent to the concrete to the required elevation with suitable material. Place and
thoroughly compact to 98 percent of the maximum density as determined by AASHTO T-
180.
024404 02440 — Concrete Driveways, etc...
3.04 REQUIRED TESTS
A. Obtain one strength test per day for each 50 cu. yds. or fraction thereof. A minimum of
one test shall be taken from each batch of concrete delivery to the sight and used.
Obtain one set of three (3) standard cylinders for each strength test. Mold and cure
cylinders under standard temperature and moisture conditions in accordance with ASTM
C31. Test one cylinder at 7 days, one cylinder at 28 days and retain the third cylinder for
later testing, if required. Testing shall be done in accordance with the requirements of
ASTM C39.
B. Perform and record the results of a slump test on a sample of concrete at the same
location and time concrete is obtained for the cylinders for the compressive strength test
in accordance with ASTM C94, Section 19. Also obtain the unit weight of the concrete
and perform an air test if the concrete is air entrained. The Engineer may require slump
tests to be made more frequently.
3.05 CONCRETE FAILING TO MEET STRENGTH REQUIREMENTS
A. Concrete having a 2&day strength of less than the minimum required strength shall be
removed and replaced with concrete meeting the strength requirements, at the
Contractor's expense.
+ + END OF SECTION + +
02440-5 02440 — Concrete Driveways, etc...
L
SECTION 02510
STABILIZED SUBGRADE
PART 1 - GENERAL
1.1 SCOPE
A. The work specified in this Section consists of furnishing all material, transportation,
tools, labor, and equipment to construct a firm and unyielding subgrade and all
items called for or that can be reasonably inferred from the Drawings, including
adding material, mixing, stabilizing, compacting, grading, testing, and other work as
required for a complete job. This does not include subgrade for pump station
driveway which is included in Section 02714,
PART 2 - PRODUCTS
2.1 PRODUCTS
A. MATERIAL - Use local or hauled -in clean sand or sand and clay.
Be STABILIZERS - Use high -bearing -value soil, sand -clay, ground limestone, crushed
limerock, oyster shell, coquina shell, or rock screenings. Do not use muck, trash or
hardpan.
C. If soil cement paving is proposed do not use local yellow sand.
D. In addition to these Specifications, the materials shall be in accordance with Section
914, "Materials for Subgrade Stabilization," of the DOT Standard Specifications for
Road and Bridge Construction, latest edition. In the event of a conflict, the more
stringent specification shall govern.
PART 3 - EXECUTION
3.1 EXECUTION
A. When completed, the stabilized subgrade shall conform to the sections shown on
the Contract Drawings.
Be If the natural soils are acceptable for subgrade material, but do not meet the
required stability, approved stabilizing material may be brought in and uniformly
mixed with the existing material to the depths shown on the Contract Drawings to
produce the required bearing values, in accordance with Section 160-5.3 "Mixing" of
the DOT Specifications for Road and Bridge Construction,
02510-1 02510 — Stabilized Subgrade
C. The required density and cross section of the subgrade shall be maintained until
the base has been laid. If the final grade becomes rutted or displaced, regardless
of the reason, re -grade and re -compact it at no additional expense to the OWNER.
All ditches, drains, and swales shall be maintained along the completed subgrade
section after their construction.
D. All drainage culverts, conduits, water and sewer lines, and all other construction to
be placed under the pavement shall be installed before the final shaping and
compaction of the subgrade.
3.2 COMPACTION
A. FLORIDA BEARING VALUE - Unless otherwise specified or shown on the Plans,
the stabilized subgrade shall have a minimum Florida Bearing Value of 50 psi. All
subgrade material shall also meet minimum 40 LBR, compacted to 98% maximum
density per AAS HTO -180.
Be The subgrade shall be shaped to within 1/4 inch of the cross section grade shown
on the DRAWINGS prior to taking density tests. Work shall not proceed until all
required density tests have passed.
C. All subgrade shall be compacted to minimum 98 percent of the maximum dry
density per AASHTO T-180.
D. Compaction shall be accomplished with a self-propelled steel drum or pneumatic
tired roller weighing at least 8 tons. Fill all hollows or depressions forming due to
rolling with appropriate suitable material. Repeat grading and rolling until
depressions no longer develop.
3.2 COMPACTION TESTS
A. Take compaction tests at the locations specified herein or at locations selected by
the ENGINEER or his authorized representative.
Be As a minimum, Florida Bearing Value tests shall be taken at 300 linear foot
intervals.
C. Density tests (Modified Proctor Test) per AASHTO TA 80 shall be taken at minimum
300 linear foot intervals. Each subgrade material which is inherently different in
composition from other subgrade material shall require an additional modified
Proctor Test.
+ + END OF SECTION + +
02510-2 02510 — Stabilized Subgrade
SECTION 02511
BASE COURSE
PART 1 - GENERAL
1.1 SCOPE
A. The work specified in this Section consists of the construction of a base course
composed of limerock constructed on prepared subgrade in accordance with these
Specifications and in conformity with the lines, grades, notes, and typical cross
sections shown on the Contract Drawings.
PART 2 - MATERIALS
2.1 MATERIALS
A. All limerock shall comply with Section 911 "Limerock Material for Base and
Stabilized Base" or Section 915 "Cemented Coquina Shell Material of the DOT's
Standard Specifications for Road and Bridge Construction latest edition. All
limerock used on the project shall be of the same grade and from the same source.
Be The cemented coquina shell material shall have a minimum LBR of 100.
Co Before placement, 97 percent of the material shall pass a 3A/2 inch sieve and it
shall be graded uniformly down to dust.
PART 3 - EXECUTION
3.1 DUMPING AND SPREADING
A. Transport the limerock to the point where it is to be used over rock previously
placed, and dump on the end of the last spread. In no case shall rock be dumped
directly on the subgrade.
Be Base material shall not be placed until the stabilized subgrade has passed all
required compaction testing and been approved by the Engineer or his authorized
representative.
C. Spread the limerock uniformly. Remove and replace all segregated areas of fine or
coarse rock with well -graded rock.
D. When the specified compacted thickness of the base is greater than 6 inches,
construct the base in two courses. The thickness of the first course shall be
02511-1 02511 — Base Course
approximately one-half of the total thickness of the finished base, or enough
additional to bear the weight of the construction equipment without disturbing the
subgrade.
3.2 FINISHING
A. For double -coarse bases, blade the first course if necessary to secure a uniform
surface and compact to the density specified herein immediately prior to spreading
the second course. No other finishing of this course is required.
Be After all spreading is completed, scarify the entire surface and shape it to produce
the exact grade and cross section after compaction. For double -course bases,
scarifying shall slightly penetrate the surface of the first course.
C. If at anytime, the subgrade material becomes mixed with the base course material,
excavate and remove the mixture, reshape and compact the subgrade, and replace
the materials removed with clean base material, shaped and compacted as
specified herein.
3.3 MOISTURE CONTENT
A. If the base material does not have the proper moisture content to obtain the
specified density, wet or dry it as required. When water is added, mix it uniformly
with the limerock. If wetting or drying is required, these operations shall involve the
manipulation of the entire width and depth of the base course before compaction.
3.4 COMPACTION
A. All limerock base shall be compacted to a minimum of 98 percent of the maximum
density as determined by AASHTO T-180.
Be Compaction shall be accomplished with a self-propelled steel drum or pneumatic
tired roller weighing at least 8 tons. All areas which are low and do not conform to
the design template after rolling shall be scarified, filled with well -graded base
material and the grading and rolling continued until the base conforms to the design
grade and section.
C. During final compaction operations, if blading of any area is necessary to obtain the
true grade and cross section, complete the compacting operations for such area
prior to making the density tests on the finished bases.
D. If cracks or checks appear in the base, remove them by rescarifying, reshaping,
refilling with limerock where needed, and recompacting, at no cost to the OWNER.
02511-2 02511 —Base Course
3.5 DENSITY TESTS
A. Compaction tests shall be taken at the locations specified herein or at locations
selected by the ENGINEER or his authorized representative.
Be All tests shall be taken at 300 linear foot intervals (minimum) or a minimum of 5
tests as requested by the Engineer.
3.6 TESTING THE FINISHED SURFACE
A. The finished surface of the base course shall be checked with a template cut to the
required cross section and with a 15 foot straight edge laid parallel to the centerline
of the road. Correct all irregularities greater than plus or minus 1/4 inch by scarifying
and removing or adding base, as may be required, after which the entire areas shall
be compacted as specified herein.
3.7 THICKNESS
A. After the base is complete, the Engineer or the soils laboratory shall take cores at
intervals of 300 linear feet or less. Completely fill said core holes with a sand
cement grout before the base is primed, or else completely fill said core holes with 3
or more equal layers of base material and adequately compact each layer using a
short steel rod and hammer. Where the base is more than 1/2 inch deficient in
thickness, correct such areas by scarifying and adding limerock. Scarify to a depth
of at least 3 inches and add more base material for a distance of 100 feet in each
direction from the edge of the deficient area, so that after proper compacting the
thickness will conform to the DRAWINGS.
3.8 PROTECTION AND MAINTENANCE
A. "Hard -plane" the base with a blade grader immediately prior to the applications of
prime coat to remove thin -glazed or cemented surfaces, leaving a granular or
porous condition that will allow free penetration of the prime material. Remove all
materials planed from the base area.
Be Protect the base in accordance with Section 02518, "Prime and Tack Coats for
Base Courses". This surface shall have a minimum curing time of one week before
the wearing course is applied.
Co Maintain the true crown and grade with no rutting or other distortion until the surface
course is applied.
+ + END OF SECTION + +
02511-3 02511 — Base Course
SECTION 02514
GATE VALVES
PART 1 -SCOPE
1.01 GENERAL
The work to be performed under this item shall include furnishing and installing gate valves as
specified by the Engineer and as shown on the Plans.
1.02 REFERENCES
Standards applicable in this Specification shall be:
A. American Water Works Association (AWWA)
1. AWWA Cl l l-80 - Rubber -Gasket Joints for Ductile Iron and Gray -Iron Pressure Pipe
and Fittings.
2. AWWA C509-87 - Resilient -Seated Gate Valves for Water and Sewerage Systems.
B. American Society of Testing and Material (ASTM)
1. ASTM A126-84 - Gray -Iron Castings for Valves, Flanges and Pipe fittings.
1.03 SUBMITTALS
A. Shop Drawings - Prior to any fabrication or installation work, the Contractor shall
furnish to the Engineer, for review and approval five (5) sets of shop drawings for the
following items. All drawings shall be reviewed, approved and stamped by the Contractor
pursuant to the provisions of the General Conditions.
1. Gate Valve
2. Valve Box
PART 2 - MATERIAL
2.01 GATE VALVES (SIZES 4" TO 12")
Gate valves shall be of the solid wedge type with resilient seats. Gate valves shall be mechanical
jointed and meet the requirements of AWWA C509-87.
Valves shall be iron bodied, bronze mounted, utilizing "O-ring" seals. Resilient seat shall be applied
to the gate and shall seal against an epoxy coated metallic surface.
The stem shall be of the non -rising type, operated by a standard AWWA, 2 -inch wrench nut. All
valves shall open to the left, using a counterclockwise motion. The stem shall be sealed with a dual "O-
ring" system designed such that the seal above the stem collar can be replaced with the valve
under pressure in the fully open position.
02514 — Gate Valves
02514-1
Valves shall be rated for a minimum 150 psi working pressure and a minimum body test pressure of
300 psi. When closed, the valve shall be drip -tight under rated pressure differential applied alternately
to each side of the gate.
The interior of the valve shall be epoxy lined in accordance with AWWA C550. The exterior of the
valve shall receive a minimum of two, 2 mill dry film thickness, asphaltic coating. All exterior exposed
bolts, studs, and nuts shall be corrosion resistant, zinc -coated in conformance with ASTM A153.
2.02 VALVE BOXES
All buried valves shall have cast two or three piece valve boxes with cast iron covers. Valve boxes shall
be provided with suitable heavy bonnets and extend to an elevation at or slightly above the valve
bonnet. The barrel shall be one or two-piece, screw type, having 5 -1/4 inch shaft. Covers shall have
"WATER" cast into the top for all water main. All valves shall have actuating nuts extended to within
six inches of the top of valve box cover. All valve boxes shall be set in a square concrete valve box
bonnet in accordance with the Drawings.
PART 3 - EXECUTION OF WORK
3.01 Gate valves shall be installed as typical sections of the pipeline. The requirements for pipeline
foundation and backfill shall be followed in all regards when installing buried service gate valves.
3.02 Care shall be taken so that the valve box does not transmit loads directly to the valve body. Valve boxes
shall be installed perpendicular and flush with the ground surface as shown on the Plans.
3.03 All gate valves shall be mechanically restrained to the attached pipe sections. Pipe sections both
upstream and downstream of each valve shall be restrained the minimum required length as that shown
for a plug in the Restraint Length Detail on the Drawings.
END OF SECTION
02514 — Gate Valves
02514- 2
SECTION 02515
MISCELLANEOUS WATER APPURTENANCES
PART 1 -GENERAL
1.01 All types of valves and appurtenances shall be products of well established reputable firms who are
fully experienced and qualified in the manufacture of the particular equipment to be furnished. The
equipment shall be designed, constructed and installed in accordance with the best practices and
methods and shall comply with these specifications as applicable.
1.02 All valves and appurtenances shall have the name of the maker and the working pressure for which
they are designed cast in raised letters upon some appropriate part of the body.
1.03 All valves and appurtenances shall be of a manufacturer and/or model number as listed in SECTION
15, "APPROVED MANUFACURES'S PRODUCTS LIST" from the most recent edition of
INDIAN RIVER COUNTY UTILITY DEPARTMENT WATER & WASTEWATER
STANDARDS,
PART 2 - PIPE TAPPING SADDLES
2.01 WATER SERVICE TAP
Tapping saddles shall be manufactured of high strength ductile iron bodies, coated with a minimum
12 mills of fusion bonded epoxy. The body shall incorporate a Buba- N rubber gasket conforming to
ASTM -132000 and be provided with a F.I.P. threaded top. The saddle shall be double bolted, with
the band, bolts and all hardware of type 304 stainless steel. The tapping saddles shall be "Ford"
model FC202, or approved equal.
2.02 WATER MAIN TAP AND VALVE
Tapping sleeves shall be long body, mechanical joint end with flanged outlet, ductile iron
construction, split in two sections and designed for assembly around the main without halting
service. The sleeve shall be suitable for use with the type and O.D. of pipe being tapped.
Tapping valves ends shall be a standard flange (for bolting to the sleeve) by mechanical joint.
Valves shall have oversized seat rings to permit entry of the tapping machine cutters and, except as
otherwise specified, shall be similar in construction and operation to AWWA C509 gate valves
(NRS). Tapping valves and sleeves shall be cold water pressure rated at 200 psi minimum for valve
sizes up to 12 inches or less and 150 psi minimum for valve size over 12 inches. Tapping sleeves
and valves shall be "Mueller" or approved equal.
PART 3 - CORPORATION STOPS
Corporation stops for use with polyethylene pipe shall be of the ball type, constructed of 85-5-5-5
brass alloy conforming to ASTM -1362. The corporation stop shall have an M.I.P.T. end by
compression end with split gland retainer. Corporation stop shall meet AWWA-C800 standards.
Corporation stops shall be "Ford", model FB 1101, or approved equal.
02515- Miscellaneous Water Appurtenances
02515-1
PART 4 -CURB STOP
Curb stop for connecting the polyethylene water service line to P.V.C. pipe shall be of the ball type,
constructed of 85-5-5-5 brass alloy conforming to ASTM -B62. The curb stop shall have a
compression end by F.I.P.T. end. The curb stop shall meet AWWA-C800 standards. Curb stop
shall be a "Ford", model KV43, or approved equal.
PART 5 - FLEXIBLE COUPLINGS
4.01 Flexible couplings shall be either the split type or the sleeve type as shown on the Drawings or as
further specified hereafter.
Sleeve type couplings shall be used with all buried piping. The couplings shall be of steel and shall
be Dresser Style 38, Smith Blair Style 413, Baker Allsteel, or equal. The coupling shall be provided
with hot dipped galvanized steel bolts and nuts unless indicated otherwise.
All couplings shall be furnished with the pipe stop removed.
Couplings shall be provided with gaskets of a composition suitable for exposure to the liquid within
a pipe.
PART 6 - POLYETHYLENE WATER SERVICE PIPE
Potable water service pipe shall be single piece, SDR9, PE -3408 polyethylene pipe, conforming to
AWWA-C901. Polyethylene pipe ends shall be provided with stainless steel tube stiffeners.
Joints for plastic tubing shall be of the compression type, utilizing at totally confined grip seal
and coupling nut, along with a split clamp locking device.
END OF SECTION
02515 — Miscellaneous Water Appurtenances
02515 - 2
SECTION 02519
TESTING AND DISINFECTING WATER SYSTEM
PART 1 - DISINFECTING POTABLE WATER PIPELINES
1.01 The new water system shall remain disconnected from existing water lines except for the temporary
jumper connection. All water used to fill and test the new water system shall be obtained through the
temporary jumper connection. Flushing shall be accomplished through the new connection only under
direction by the Utility Authority and only after installation of upstream and downstream pressure
gauges.
1.02 Before pressure testing against existing water system valves, and before being placed into service,
potable water pipelines shall be chlorinated in accordance with the latest edition of AWWA C-651,
"Standard Procedure for Disinfecting Water Mains". The procedure shall be approved by the Engineer.
The location of the chlorination and sampling points will be as shown on the Drawings. Taps for
chlorination and sampling shall be uncovered and backfilled by the Contractor as required.
1.03 The pressure required for the field hydrostatic pressure test shall be 50 percent above the normal
working pressure but not less than 150 psi. The Contractor shall provide temporary plugs and
blocking necessary to maintain the required test pressure. Corporation cocks at least 3/4 -inches in
diameter, pipe riser and angle globe valves shall be provided at each pipe dead-end in order to bleed air
from the line. Duration of pressure test shall be at least 2 hours. The cost of these items shall be
included as a part of testing.
1.04 The leakage test shall be conducted concurrently with the hydrostatic pressure test and shall be of not
less than 2 hours duration. All leaks evident at the surface shall be repaired and leakage eliminated
regardless of total leakage as shown by test. Lines which fail to meet tests shall be repaired and
retested as necessary until test requirements are complied with. Defective materials, pipes, valves and
accessories shall be removed and replaced. The pipe section to be tested shall be between valves or in
such sections as may be directed by the Engineer by shutting valves or installing temporary plugs as
required. In no case shall the section of line to be hydrostatically tested exceed 2000 feet in
length. The line shall be filled with water and all air removed and the test pressure shall be
maintained in the pipe for the entire test period by means of a force pump to be furnished by the
Contractor. Accurate means shall be provided for measuring the water required to maintain this
pressure. The amount of water required is a measure of the leakage.
1.05 The Contractor must submit his plan for testing to the Engineer for review at least five (5) working
days before starting the test. The Contractor shall remove and adequately dispose of all blocking
material and equipment after completion and acceptance of the field hydrostatic test, unless
otherwise directed by the Engineer. Any damage to the pipe coating shall be repaired by the Contractor.
Lines shall be totally free and clean prior to final acceptance.
1.06 The Engineer or the Engineer's representative must be present during testing.
PART 2 - PRESSURE AND LEAKAGE TESTS OF UNDERGROUND PRESSURE PIPING
2.01 Hydrostatic pressure and leakage tests for ductile iron pipe shall conform with Section 4 of AWWA
Standard C-600, with the exception that the Contractor shall furnish all gauges, meters, pressure
pumps and other equipment needed to test the line. PVC pipe shall be tested in accordance with
02519 -1
02519 — Testing and Disinfecting Water System
AWWA Standard C605, "Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and
Fittings for Water". Engineer shall be present during all testing, and final inspections. No hydrostatic
testing against existing system valves shall be allowed until the section to be tested has been
bacteriologically cleared.
2.02 The new water system shall remain disconnected (connecting valve to be locked in the closed position)
from existing water lines except for the temporary jumper connection. All water used to fill and test the
new water system shall be obtained through the temporary jumper connection. Flushing shall only be
conducted in accordance with the plans.
2.03 The general procedure for chlorination shall be first to flush all dirty or discolored water from
the lines, and then introduce chlorine in approved dosages in accordance with Table 11-1 through a
tap at one end, while water is being withdrawn at the other end of the line. The chlorine solution
shall remain in the pipeline for no less than 24 hours.
2.04 Following the chlorination period, all treated water shall be flushed from the lines at their extremities
and replaced with water from the distribution system. Bacteriological sampling and analysis of the
replacement water shall then be made in the presence of the Engineer in full accordance
with the AWWA Standard C-651. The Contractor will be required to re -chlorinate, if necessary. The
line shall not be placed in service until the requirements of the State and County Public Health
Department are met.
2.05 The Contractor shall make all arrangements necessary with an independent commercial laboratory
approved by the Department of Health and Rehabilitative Service (HRS) for the collection and
examination of samples of water from disinfected water mains. These samples shall be examined for
compliance with HRS requirements. Sampling shall be made daily and continuously until two
successive examinations are found satisfactory. Should three examinations be found unsatisfactory,
the line shall be flushed and disinfected again. Certified copies of all laboratory analyses shall be
provided to the Owner. The cost of all sampling, flushing, and disinfecting shall be included in the
contract price and no additional charge shall be made to the Owner for this work. County personnel
shall operate all valves and be present to determine volume of water used for flushing.
(continued on next page)
02519 - 2
02519 — Testing and Disinfecting Water System
TABLE 11-1
Chlorine Required to Produce 25-mg/L Concentration
in 100 ft. of Pipe by Diameter
Pipe 100 -Percent 1 -Percent
Diameter Chlorine Chlorine Solution
in. lb. gal.
4
0.013
0.16
6
0.030
0.36
8
0.054
0.65
10
0.085
1.02
12
0.120
1.44
16
0.217
2.60
END OF SECTION
02519 - Testing and Disinfecting Water System
02519 = 3
SECTION 02520
ASPHALTIC CONCRETE PAVEMENT
PART 1 - GENERAL
1.1 SCOPE
A. The work consists of the construction of an asphaltic surface course composed of a
mixture of aggregate mineral filler (if necessary) and asphalt cement to produce the
desired stability hereinafter described, properly laid and compacted upon a
prepared base, or an existing surface course in accordance with these
Specifications and in conformity with the lines, grades, thickness and typical cross
section shown on the Contract Drawings.
PART 2 - PRODUCTS
2.1 PRODUCTS
A. The asphaltic concrete pavement shall be type S-1 and conform with Section 334,
of the Florida Department Of Transportation Specifications for Road and Bridge
Construction (hereinafter referred to as the FDOT Specifications).The following are
exceptions to the FDOT Specification Section 334:
1. In Section 334-1.1 for 330-8.5 where referenced via Section 300, substitute
Section 02518,
2. Except 330-12.5.2
3, Except RAP will not be used as a mix component
4. Except 334-7 and 334-8
PART 3 - EXECUTION
3.1 LIMITATIONS OF LAYING OPERATIONS
A. Apply the asphaltic concrete only when the temperature in the shade is 50 degrees
Fahrenheit and rising. The CONTRACTOR may lay bituminous mixtures which
have been rained upon in transit, at CONTRACTOR's risk. However, if local
conditions indicate that rain is imminent, no work shall be started. Under no
circumstances shall the mixture be laid while it is raining, or when there is water on
the base. If the wind is blowing such that sand, dust, etc. are being deposited on
the surface being paved to the extent that the bond between layers will be reduced,
the asphalt shall not be spread on the surface.
B. Supply thermometers so that the ENGINEER may determine the temperature of
02520-1 02520 — Asphaltic Concrete...
the bituminous materials as they are applied. Do not lay the bituminous materials
unless they are the proper temperature.
3.2 TACK
A. If required, a tack coat shall be applied per Section 02741 of these Specifications.
3.3 PLACEMENT OF ASPHALTIC CONCRETE
A. Asphaltic concrete mix shall be placed in accordance with FDOT specifications
Sections 320 and 330, with the following exceptions:
1. Substitute "Resident Project Representative" for Engineer.
2. Delete all phrases such as "when directed by the Engineer" that
implicitly or explicitly indicate that the Engineer or Resident Project
Representative shall have authority to supervise or direct performance
of the work or authority to undertake responsibility contrary to the
provisions of paragraph 9.10 of the "Standard General Conditions of
the Construction Contract Section 00700".
Be Unless otherwise approved by the Engineer, the Contractor shall saw -cut edges of
existing pavement where (a) existing pavement is to be removed, and (b) new
pavement is to be placed against existing pavement.
3.4 FINISHED CROSS SECTION
A. The finished surface shall not vary from the approved section on the Plans by more
than 1/4 inch from a 10 foot straight edge applied both parallel and perpendicular to
the centerline of the pavement. The parallel measurement shall not be required if
the road centerline is sloped to the grades shown on the Plans. The parallel
measurement will be required only on flat (zero slope) grades. Areas with improper
cross sections shall be corrected to the proper cross section as specified herein.
3.5 PAVEMENT THICKNESS
A. All new pavement shall be 2 Y2" thick asphalt Concrete type S-1
Be To achieve finished grades, the Contractor shall apply 1" thick asphalt Concrete
type S-1 over existing pavement.
C. The finished pavement thickness shall vary by no more than plus or minus 1/4 inch
from the thickness called for on the Plans. Corrections of deficiencies in pavement
thicknesses shall be in strict accordance with the above FDOT Specifications.
02520-2 02520 — Asphaltic Concrete...
3.6 TESTS
A. The testing laboratory shall provide the following:
1. Verify performance of the CONTRACTOR's proposed mix with these
Specifications.
2. Perform in -plant testing of aggregate, gradation, and bitumen content.
Perform at least one test per 100 tons of asphaltic concrete produced or part
thereof during each day of operation.
3. Using a nuclear gage, determine the density of the finished pavement
as compared to the density of the design mix. Fill and compact all
core holes to match the pavement properly.
4. Take core borings as specified above, to determine pavement thickness. Fill
and compact all core holes to match the pavement properly.
+ + END OF SECTION + +
02520-3 02520 — Asphaltic Concrete...
J
PART 1 - GENERAL
1.01 SCOPE
SECTION 02530
GRAVITY SANITARY SEWER PIPING
The work to be performed under this item shall include the selling and delivering and
the installing of polyvinyl chloride gravity sewer mainline pipe and service laterals as herein
specified. Installation of service laterals shall follow the installation of service wye or tee in
the main within seven (7) calendar days.
1.02 REFERENCES
Standard applicable in these Specifications shall be:
A. American Society for Testing and Materials (ASTM).
1. ASTM D3034-81 Standard Specification for Type PSM (Polyvinyl Chloride)
PVC Sewer Pipe and Fittings.
2, ASTM D2321-80 Standard Recommended Practice for Underground
Installation of Flexible Thermoplastic Sewer Pipe.
3. ASTM F477-76 Standard Specification for Elastomeric Seals (Gaskets) for
Joining Plastic Pipe.
4, ASTM
D3212-81
Standard
Specification for Joints for Drain and Sewer
Plastic
Pipes Using
Flexible
Elastomeric Seals.
B. American Association of State Highway and Transportation Officials,
1. AASHTO T-180-74 Moisture -Density Relations of Soils Using a 10 lb.
(4.54 kg.) Rammer and an 18 -inch (457 mm) Drop.
2. AASHTO T-99-74 The Moisture -Density Relations of Soils Using a 5.5 lb.
(2.5 kg.) Rammer and a 122 -inch (305 mm) Drop, as modified by T-99-801
(Dated 1981).
1.03 SUBMITTALS
A. Shop Drawings - Prior to any fabrication or installation work, the Contractor shall furnish
to the Engineer, for review and approval five (5) sets of shop drawings for the following
items. All drawings shall be reviewed, approved and stamped by the Contractor prior to
submission to the Engineer.
1. Pipe length and class, fittings and special pieces.
2. Joint method to be used.
3. Manufacturers' data on identification tape and electronic location trace wire to
be supplied.
02530-1
02530 — Gravity Sanitary Sewer Piping
PART 2 - MATERIALS
2.01 DIRECTIONAL BORED POLYETHYLENE PIPE
A. Polyethylene pipe used for directional bored sanitary sewer shall meet the specifications of
SECTION 02400, paragraph 2.A. Pipe shall be co -extruded with green colored sheath or
green striping.
2.02 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS
A. PVC Pipe (SDR26) - PVC pipe shall meet ASTM D-3034 requirements. The joints shall
consist of an integral bell with elastomeric gasket. The gasket shall be locked securely in
the bell. The pipe shall be approximately 12.5' or 20' lengths. Pipe shall be green in color.
The pipe must meet or exceed the testing procedure per ASTM D-2412, D -3212-73T and
D-2444. The pipe shall be manufactured from clean virgin, Class 11332-B PVC
compound conforming to the latest ASTM Standard C-1784. Connections to pipes of
other materials or to pipes with dimensions not compatible with SDR 26 pipe shall be
made using couplings of rigid P.V.C. construction with elastomeric gaskets, as
manufactured by "Harco", or equal.
2.03 SERVICE LATERAL MARKER SYSTEM
A. Each lateral installed by the nderground contractor shall have an electronic marker location
ball taped to the unconnected end of the service lateral. Also, a stake shall be placed at the
end of each service lateral and shall be 4" x 2" pine, 4 feet long. The stake shall be
pressure treated lumber, painted green at the top.
2.04 BURIED IDENTIFICATION TAPE
Detectable buried identification tape shall be installed for all trenched pipe.
Tape shall be 2 inches minimum width, consisting of a minimum 5 mil overall thickness with a
solid aluminum foil core. Construction shall be 2 mil clear film, reverse print laminated to
aluminum foil to 2 mil clear film, making the film permanently printed.
Tape shall be furnished in manufacturers' standard roll length, meeting the "American Public
Works Association" (APWA) color code, and shall be imprinted continuously with the
following words, unless otherwise approved:
"GRAVITY SEWER"
Detectable buried warning tape shall be equal to or better than "PRO -LINE" underground
utility marking tape as manufactured by Pro -Line Safety Products Co., 1099 Atlantic Drive,
Unit #1, West Chicago, IL.
2.05 DETECTABLE BURIED TRACE WIRE
Trace wire shall be continuous #10 THHN, stranded conductor copper wire. PVC color
sheathing shall meet the color code of the "American Public Works Association" (APWA).
02530 — Gravity Sanitary Sewer Piping
02530-2
2.06 FOUNDATION ROCK
A sieve analysis of the limerock shall conform to the following limits:
Passing
1"
Passing
3/4"
Passing
3/8"
Passing
#4
Passing
#8
PART 3 - INSTALLATION
3.01 GENERAL REQUIREMENTS
100%
- 90 - 100%
- 20 - 55%
- 0 - 10%
- 0 - 5%
A. All work shall be proved to be in first class condition and constructed properly in
accordance with the Drawings and Specifications. All defects and leaks disclosed by
required testing shall be remedied. All tests shall be performed by the Contractor and
observed by the Engineer.
B. All pipe and structures shall be installed on dry, firm bedding. The free water surface
shall be shall be lowered to at least 12 inches below the bedding surface prior to placing
pipe or structures and shall be maintained at that depth throughout bedding, haunching,
and initial backfilling of the work. During subsequent backfilling, the water level shall
be kept sufficiently below the working surface to allow compaction of backfill to the
required density, and until required density tests have been performed.
C. Temporary supports shall be installed for adequate protection and maintenance of all
underground and surface structures, water lines, drains, and other obstructions
encountered in the progress of the work. Any structure which may have been disturbed
shall be restored upon completion of the work.
D. Blasting shall not be permitted except by written approval of the Engineer.
E. Trenching and subsequent backfilling within the general construction site shall be
accomplished as expeditiously as possible in order to prevent trench decay and
maintain a clear operational area.
F. Prior to any excavation or trenching outside the designated limits of the work site, the
Contractor shall secure the necessary permits and/or authorization from the applicable
Owner, or confirm that such has been previously obtained. The stipulations of said permit
or authorization shall be completely followed and, prior to construction operations,
notice shall be provided to the appropriate Owner and Engineer.
3.02 HANDLING MATERIALS
A. Pipe, fittings, and accessories shall be loaded and unloaded by hand or skidding so as to
avoid shock or damage. Under no circumstances shall such materials be dropped. Pipe
handled on skidways shall not be skidded or rolled against pipe already on the ground.
B. In distributing the material at the site of the work, each piece shall be unloaded opposite or
near the place where it is to be laid in the trench.
02530- 3
0
02530 — Gravity Sanitary Sewer Piping
3.03 ALIGNMENT, GRADE AND COVER FOR BURIED PIPING SYSTEMS
A. Gravity sewers shall be laid and maintained to the required lines, depths, and
grades.
B. Wherever obstructions not indicated on the Drawings are encountered during the progress
of the work and interfere to such an extent that an alteration in the Drawings is required,
the Engineer will order a deviation from the line and grade or arrange with the Owners
of the structures for the removal, relocation, or reconstruction of the obstructions.
C. The maximum permissible deflection for pipe and fittings shall be as recommended by the
manufacturer.
D. Installation of gravity sewers shall be controlled by use of a laser to maintain proper grade.
The Contractor shall also be responsible for verifying elevations of the pipe, as
indicated on the Drawings, at sufficient points during progress of the work to identify
discrepancies between actual and plan elevations due to laser misalignment, equipment
error, etc., and to correct the work as required to conform to the Drawings.
3.04 PIPE TRENCH EXCAVATION
A. Trench Dimensions
1. The minimum width of the trench shall be equal to the outside diameter of the pipe at
the joints plus 8 inches for unsheeted trenches, or 12 inches for sheeted trench, and
the maximum width of trench, measured at the top of the pipe, shall not exceed
the nominal pipe diameter plus two feet, unless otherwise shown on the Drawing
details or approved by the Engineer. Trench walls shall be vertical from the bottom
of the trench to a line measured one foot above the top of the pipe. From one foot
above the top of the pipe to the surface, the trench walls shall be as nearly
vertical as soil conditions will permit, unless otherwise detailed on the Drawings.
Spaces for joints, fittings, manholes and other structures shall be maintained
unless otherwise approved by the Engineer, or alternate methods are detailed on
the Drawings. Should the specified maximum width of trench be exceeded, the pipe
shall be adequately reinforced as directed by the Engineer, at the Contractor's expense.
2. Trench grade for utilities or structures not requiring special bedding material shall
be defined as the grade of the bottom surface of the utility or structure to be
constructed or placed within the trench. Such shaping of the trench bottom, as
may be required to provide suitable bedding, shall be considered to be a part of this
work. Trench grade in non -cushioning material shall be defined as 6 inches below the
outside of the bottom of the utility, which 6 inches shall be backfilled with suitable
bedding material. Unauthorized excavation below trench grade shall be backfilled to
trench grade and suitably compacted by the Contractor without additional cost to the
Owner. Final trimming and grading of trench bottom shall be done manually.
3.05 BACKFILL AND BEDDING MATERIALS
A.
TYPE 1
- Type 1 material shall be
either well -graded crushed stone
or
crushed
gravel
meeting
the requirements of ASTM
Designation C33 -71a, Gradation
67
(3/4 inch
to No.
02530 — Gravity Sanitary Sewer Piping
02530- 4
J
4 Sieve) or air cooled blast furnace slag along or in combination with crushed stone
and/or crushed gravel conforming to ASTM Designation C33 -71a requirements. This
material shall be used primarily for pipeline and manhole foundations.
B. Type 2 - Type 2 material shall be unclassified material obtained from the Contractor's
excavations and approved by the Engineer. The material shall be substantially free
from wood, roots, humus, peat, muck, and other organic materials, and shall not contain
clods, stones, masonry rubble, and the like, greater than 6 inches through the largest
dimension. In general, the material shall consist of sand, loam, sandy- loam, clayey -sand,
gravel, or crushed stone.
C. Type 3 - Type 3 material shall be select granular material, free from organic matter, of
such size and gradation that the desired compaction can be readily attained and shall meet
the requirements for A3 material according to the Revised Bureau of Public Roads
Classifications. Material from the Contractor's excavations may be used, if it meets the
above requirements. Otherwise it must be imported.
3.06 BEDDING AND FOUNDATIONS
A. Ordinary Bedding
The bottom of the trench shall be hand shaped to provide a firm bedding for the
utility pipe. The utility shall be firmly bedded in undisturbed firm soil. The bedding shall
be shaped so that the pipe will be in continuous contact therewith for its full length and
shall provide a minimum bottom segment for the pipe equal to 0.6 of the outside
diameter of the barrel. Excavation under the bell shall be sufficient so that the bell does
not support the pipe and the joint can be made without interference.
B. Unsuitable Bedding Material
Class C Bedding shall be used for all pipeline construction unless otherwise shown on
the Drawings or unless unsuitable material is encountered at the bedding surface. In the
event that the materials encountered at normal bottom of trench excavation are,
in the judgment of the Engineer, unsuitable to act as foundation for the pipe, such
material shall be excavated for the full width of the trench to the depth necessary to
obtain a suitable foundation. The Engineer will notify the Contractor, in writing, of the
necessity for and extent of the material to be removed and the Contractor shall
remove such unsuitable material as soon as possible and backfill in accordance with the
requirements for Class B Bedding. All unsuitable material shall be disposed of by the
Contractor.
3.07 PIPE TRENCH BACKFILL
A. Initial Backfill
1. Initial backfill shall be placed as soon as possible after laying the pipe and shall
maintain a pace with the pipe laying so that no more than five pipe joints separate
laying and backfilling operations. Initial backfill shall include all haunching and
backfill from the top of the bedding to a compacted depth of twelve inches
over the pipe. All haunching and backfilling shall be done in the dry.
2. Initial backfill shall be done as specified below:
02530n5
02530 — Gravity Sanitary Sewer Piping
2.1 Haunching of the pipe shall be by hand placement and compaction of
material in maximum 4 inch layers from the bottom of the trench to the
springline of the pipe, taking care to fill all voids below and around the
pipe. Backfilling shall be carefully continued in layers not exceeding 6
inches in thickness for the full trench width until the compacted fill is 12
inches above the top of the pipe.
2.2 During initial backfilling the fill shall be deposited evenly along both sides
of the pipe from a height not to exceed 2 feet above the top of pipe, and
fill shall not be dropped directly on the unprotected pipe surface.
2.3 Where thrust blocks, encasement, or other cast -in-place concrete items are
below grade, no backfilling shall start until the specific items have
been inspected and approved by the Engineer or his authorized
representative.
2.4 The backfill to one foot above the top of the utility shall be thoroughly
compacted with curved end tamping bars under and on each side of the pipe
and flat tamped between the pipe and trench wall and shall be completed
before the remainder of the trench is backfilled. Initial backfill shall be
compacted to 100 percent of maximum density as determined by AASHTO
T-180. No subsequent backfill will be permitted until the initial backfill
has been accepted by the Engineer or his authorized representative.
B. Subsequent Backfill
1. Subsequent backfill is that backfill between the initial backfill and the finished
ground level or bottom of subbase.
2. Subsequent backfill material shall be placed full trench width in horizontal layers
not exceeding 12 inches loose depth and compacted by power -operated tampers,
rollers, or vibratory equipment to a density equal to 98 percent of the maximum
density as determined by AASHTO T-180 for pipe placed under and adjacent to
roadways or paved surfaces, and 95 percent under areas where no pavement is to
be constructed and vehicular traffic is not to pass over the pipe. Each layer shall
be compacted to the specified density prior to placing subsequent layers. The
thickness of the loose layer may be increased when in-place density tests show
that the specified density can be obtained.
C. Backfill Material
1. Type 2 material shall be used for initial backfill and subsequent backfill with the
following conditions: Initial backfill shall be predominately sandy material free
from rock or stone greater than 1 1/2 inches diameter, and the maximum allowable
dimension of a stone or rock fragment for subsequent backfill shall be 6 inches.
If in the opinion of the Engineer the Type 2 material will not provide adequate and
uniform support for load distribution to the pipe, the Contractor shall obtain and
place either Type 1 or Type 3 backfill as determined by the Engineer.
2. All excavated material not suitable for backfill shall be placed on site at an
acceptable location, by Owner, or hauled off the job at the price set forth in the
02530 — Gravity Sanitary Sewer Piping
02530&6
L
accepted Bid Documents. All material that is brought in from other sources for
backfill shall be at the price set forth in the Contract.
3. Excavated material to be used for backfill shall be neatly deposited at the sides
of the trenches where space is available to protect against caving or sloughing into
the trench. Where stockpiling of excavated material is required, the Contractor
shall coordinate the site location with the Engineer and shall maintain his
operations to provide for natural drainage and not present an unsightly appearance.
No excavated material shall be placed on private property without the consent of the
property owner.
D. Compaction Methods
1. Mechanical compaction shall be accomplished using pneumatic or gasoline -powered
tampers or flat -plate vibrators. Self propelled rollers may be used with the exception
that the first two feet of backfilling over the pipe shall be compacted by hand-
operated tamping devices.
2. Flooding or puddling with water to consolidate backfill is not acceptable, except
where sand is encountered below unpaved areas only, and only with prior approval
by the Engineer. The flooding or puddling operation shall be repeated with each
two feet of backfill placed.
E. Density Tests
1. The Contractor shall arrange to have sufficient soil tests made by an independent
testing laboratory selected by the Engineer to demonstrate conformance of his
work with the stability and compaction levels required by these specifications.
Compaction tests shall be taken at intervals listed herein or as deemed necessary
by the Engineer. All test results shall be signed and sealed by a Florida
Registered Engineer, and a copy provided to the Owner and Engineer.
2. Any proposed alternative test methods to those specified herein must be approved
by the Engineer prior to testing. At the request of the Engineer, the Contractor
shall provide such documentation of a proposed alternative test method as
the Engineer may require to evaluate the method for approval.
3. In no case shall the Contractor proceed with construction on compacted
material until the tests prove satisfactory and approval is given by the
Engineer.
4. In general, at least one test for maximum dry density/optimum moisture content
shall be performed on representative samples of each inherently different material
to be used for compacted backfill or embankment fill. For material of uniform
composition and textural class, a minimum of two test locations per
mainline run between manholes shall be performed.
5. As a minimum, in-place density tests shall be performed at the following rates
on the compacted backfill, and shall be taken in one foot intervals beginning
at one foot above the pipe and ending at the final grade. Test locations shall be
as directed by the Engineer or his authorized representative. For material of
uniform composition and textural class, a minimum of one test location per
02530-7
02530 - Gravity Sanitary Sewer Piping
mainline run between manholes shall be performed. If any test results are
unsatisfactory, the Contractor shall re -excavate and recompact the backfill, at
his expense, until the required compaction is obtained.
6. The costs of all sampling, proctor and density testing shall be paid for by the
Contractor.
3.08 PIPE SYSTEM LAYING AND JOINTING
A. General
1. Unless otherwise specified herein or directed by the Engineer, all pipe and
fittings shall be laid and joined in accordance with the appropriate
manufacturer's directions with regard to allowable barrel and joint deflection,
spigot seating depth, gasket placement, lubrication, bolt torque, field
cutting/trimming, and pushing/pulling methods for joint assembly.
2. Prior to placing in the trench, each pipe section, joint, and fitting shall be
checked for damage or defects such as cracks, blisters, coating/lining
separation, gouges, and the like. Any damage or defective materials
found shall not be installed unless approved by the Engineer, and shall be
marked "REJECTED" and immediately removed from the work site.
3. Prior to installation, the interior of all pipe and fittings shall be inspected for
debris, sediment accumulation, sand, and the like, and shall be cleaned as
required to remove such foreign matter. Joint surfaces such as gaskets, gasket
grooves, spigots, and bells shall be cleaned of sand and grit prior to joining.
4. Gasket lubricants shall be stored and applied in a manner that will prevent
significant contamination or pick-up of sand and grit.
5. The pipe spigot shall be centered in and aligned with its mating bell prior to
insertion and forced evenly in a straight line to seating depth, taking care
not to over -bell the joint. Where required, deflections shall be made after
the joint is seated.
6. Joining shall generally be done by hand or by push -bar with a cushion block
whenever pipe size and weight permit. When a mechanical
pushing/pulling device such as chain -puller, come -along, and the like is
required, the device shall be used in a manner that will not deform gouge,
chip, or otherwise damage the pipe or cause significant disturbance of the
prepared bedding. In no case shall joints be made by "popping -on" or swinging
the spigot into the bell to seat the joint.
7. Fittings and appurtenances shall be fully, independently supported on the bedding
or on a permanent foundation so as not to bear on the pipe upon completion of
the installation.
8. The installed piping system shall be kept free of dirt, trench water, and
other foreign matter during the progress of the work, and all open ends of the
line shall be sealed with watertight plugs whenever work is not in progress.
02530 — Gravity Sanitary Sewer Piping
02530- 8
4
L
9. Empty installed pipe shall be secured against flotation due to potential trench
flooding by timely placement of sufficient backfill or approved anchoring
devices sufficient to resist pipe buoyancy.
3.09 INSTALLATION OF FITTINGS
A. Fittings, plugs, and caps shall be set and jointed to pipe in the manner heretofore specified
for cleaning, laying and jointing pipe.
B. Installation of manholes shall conform to the details as shown on the Drawings and,
unless otherwise specified, shall conform with Section 425 of the 1986 Edition of the
Florida D.O.T. Standard Specifications for Road and Bridge Construction. Backfill shall
be placed in lifts not to exceed 12 inches loose depth and compacted to 95 percent of
maximum density per AASHTO T-180 in unpaved areas and to required subgrade
density in areas of paving or curbing.
C. Density tests shall be taken on the compacted backfill at all manholes. There shall be a
minimum of one test location for each manhole. The test location shall be taken at the
location designated by the Engineer's representative. The density tests shall be taken at
each location at one foot intervals beginning at the bottom of the excavation and ending at
the final grade. The costs of all testing shall be paid for by the Contractor.
3.10 INSTALLATION OF DETECTABLE BURIED WARNING TAPE
Tape shall be attached to the pipe for its entire length. Tape shall also be placed at a maximum
depth of 12 inches below finished grade directly above the pipe centerline. Following
placement of tape, the trench shall be backfilled with due caution to prevent displacement or
damage to the tape.
3.11 INSTALLATION OF DETECTABLE BURIED TRACE WIRE
Trace wire shall be installed on all pipe and fittings, with splices, branches, connections and
terminations as shown on the plans.
3.12 AS -BUILT DRAWINGS
During the installation of gravity sewer lines, the Contractor's Registered Florida Surveyor
and Mapper shall keep accurate records of the As -Built construction showing the
location of all changes in elevation, alignment, services, utility crossings, structures
and similar data. Items shall be located from permanent objects such as centerline of street,
manholes, valves, etc. Immediately upon completion of the sanitary sewer inverts and prior to
placement of roadway base, the Contractor shall deliver to the Engineer an As -Built Drawing,
signed and sealed by a Florida registered surveyor, showing the manhole separations, inverts and
rim elevations.
END OF SECTION
02530-9
6
02530 — Gravity Sanitary Sewer Piping
SECTION 02531
GRAVITY SEWER MANHOLES
PART 1 - GENERAL
1.01 SCOPE
The work to be performed under this item shall include the furnishing of all materials, equipment
and labor required for the installation of pre -casts gravity sewer manholes as herein described and as
shown on the Plans. The Contractor shall perform all excavation, backfilling, and related work
required for the construction of the gravity sewer manholes in accordance with the provisions set
forth under the applicable items of this Specification.
1.02 REFERENCES
Standard applicable in this Specification shall be:
A. American Society for Testing and Materials (ASTM)
1. ASTM A48-76 - Specifications for Gray Iron Castings.
2. ASTM C478 -82a - Standard Specification for Pre -cast Reinforced Concrete
Manhole Section
1.03 SUBMITTALS
A. Shop Drawings - Prior to any fabrication or installation work, the Contractor shall
furnish to the Engineer, for review and approval five (5) sets of shop drawings for the
following items. All drawings shall be reviewed, approved and stamped by the
Contractor prior to submittal to the Engineer.
1. Pre -cast manholes
B. Manufacturer's Data - Prior to any fabrication or installation work, the Contractor shall
furnish to the Engineer, for review and approval, manufacturer's data for the following
items:
1. Manhole frames and covers
2. Manhole rainguard boots
3. Press seal pipe connectors
4. "Ram-Nek" mastic joint sealer
PART 2 - MATERIALS
2.01 MANHOLES
A. Pre -cast Manholes - Pre -cast manholes shall conform with the typical manhole details as
shown on the Plan and shall consist of a pre -casts reinforced base, cast monolithically
with a minimum two foot length of barrel section, additional barrel sections and manhole
cones. All concrete used in the construction of pre -cast manholes shall be Type H with a
28 -day compressive strength of 4000 psi.
02531 — Gravity Sewer Manholes
02531-1
Pre -cast manhole sections shall be circular and formed with male and female ends so that
when assembled they will make a continuous, uniform manhole.
Joints shall be of such design as will permit effective jointing by using a continuous keyed
construction joint. Keyed sections shall be joined and sealed using "Ram-Nek" or other
mastic sealant approved by the Engineer and capable of preventing leaks between the
sections. After placement of the manhole sections, anti -hydro grout shall be used to point
all remaining joint surfaces and lifting holes. Alternate designs will be permitted only
when they have received approval from the Engineer prior to their fabrication.
Pre -cast concrete manholes shall conform with the requirements of ASTM Designation
C478, except that the minimum acceptable wall thickness shall be 8 -inches. Manhole
steps will not be provided.
After the manhole is assembled and before backfilling, all joints shall be filled with anti -
hydro grout and pointed to form a dense hard joint.
Two coats (minimum of 8 mil dry thickness per coat), of Coal Tar Epoxy coating, or
approved equal, shall be applied to the entire surface, inside and outside, of the manhole.
These coatings shall be applied in accordance with the manufacturer's directions.
Brick collars, above the roof slab or manhole cone, to bring the manhole to finished grade,
shall be laid to the thickness and dimensions shown on the Plans. All brick shall be
thoroughly wetted before laying and shall be laid in a full bed and joint of mortar.
B. Manhole Frames and Covers
Manhole frames and covers shall be close -grained gray cast iron castings conforming to
ASTM A48, Class 30 iron.
Castings shall be of uniform quality, free from blow holes, porosity, hard spots,
shrinkage, defects, cracks or other injurious defects. They shall be smooth and well
cleaned by shot blasting and, unless otherwise specified shall be coated with coal tar
pitch varnish of a type which will make a smooth coating, tough and tenacious when cold,
not tacky and not brittle.
Frame and covers shall have a minimum total weight of 400 pounds. Manhole covers
shall have a minimum thickness along the rim of 2 inches. Covers shall have concealed
watertight pick holes.
All frames and covers shall be U.S. Foundry and Manufacturing Corporation, No. 420
"B" or approved equal, marked "Sanitary Sewer".
C. Resilient Pipe Connectors for Precast Concrete Manholes
The connection of any pipe to an existing manhole shall be performed utilizing a
resilient connector conforming to ASTM C923-84. All metallic components of the
connector shall be stainless steel. Acceptable manufacturers shall be as listed in
SECTION 15, "APPROVED MANUFACURES'S PRODUCTS LIST" from the
most recent edition of IRCDUS WATER & WASTEWATER STANDARDS.
02531a2
WP
02531 - Gravity Sewer Manholes
PART 3 - EXECUTION
3.01 Foundations
The standard foundation for pre -cast manholes shall be as follows:
A. Undisturbed, existing in-place, natural granular soils consisting which have been finished
graded by hand to final elevation. No over excavation shall be permitted.
B. For manholes not placed on undisturbed, existing, in-place natural granular soils, a 12
inch layer of 3/8" to 3/4" crushed rock shall be placed on the prepared trench bottom, and
compacted. A two inch layer of high early strength cement grout may be placed on top of
the rock base for leveling. The manhole base shall be set on the foundation, to the proper
invert elevation, while the grout is still workable, so that the grout will fill all voids
beneath the manhole base.
3.02 Manholes
All workmanship shall conform to best standard practice. Manholes shall be built accurately to the
dimensions shown on the Plans. The top of the manholes shall be brought accurately to grade with
masonry.
Manholes shall be completed (with inverts, frames and covers) as the work progresses.
Particular care shall be taken that no water rises on the masonry until the mortar is thoroughly set.
Any masonry damaged in this manner shall be removed upon the order of the Engineer.
All pipes or castings to be embedded in masonry work shall be accurately set and if so required,
headers shall be laid around the casting so embedded. Spurs and stubs for branch lines shall be built
in the manholes where shown on the Plans or otherwise required by the Engineer. They shall be
closed with vitrified plugs.
3.03 Watertight Workmanship
The entire work of constructing manholes must be carried on in a manner to insure watertight work.
Any leaks in manholes shall be caulked, repaired or the entire work shall be removed and rebuilt.
3.04 Disposal of Water from Excavations
All water pumped or bailed from excavations shall be conveyed in a proper manner to a suitable
point of discharge by the Contractor at his own expense.
The Contractor shall provide for the disposal of water removed from excavations in a manner that
will not cause injury to public health, private or public property, any portion of the work completed
or in progress, the surface of the streets, or cause any impediments to the reasonable use of the site
by other Contractors. The Contractor shall be responsible for complying with all the local
regulations of the Department of Environmental Regulation regarding pollution of the canals. The
Contractor shall take special precautions to eliminate any odor problems resulting from the
discharge of sulfide water, such as submerged discharge outlets and overflow basins.
02531 — Gravity Sewer Manholes
02531- 3
3.05 Bedding and Backfill
Except for additional foundation rock as indicated above, each manhole shall be bedded and
backfilled in accordance with the specification for "Gravity Sewer Piping". Density tests shall be
taken at each manhole structure installed on the project.
3.06 Inverts
Invert channels shall be constructed smooth and semi -circular in shape conforming to the inside of
adjacent sewer sections. Changes in direction of flow shall be made in a smooth curve of as large a
radius as possible. Changes in size and grade of channels shall be made gradually and evenly.
Invert channels shall be formed by one of the following methods:
A. Form directly into concrete manhole base.
B. Lay half tile in concrete.
C. The Manhole floor outside of channels shall be made smooth and sloped toward channels.
3.07 Field Quality Control
Testing - Tests for water tightness shall be made by the Contractor in the presence of the Engineer.
The tests and measurement of infiltration/exfiltration shall be conducted in a manner as accepted
�y and approved by the Engineer. All visable leakage shall be plugged and repaired by the Contractor.
END OF SECTION
02531- 4
02531 — Gravity Sewer Manholes
APPURTENANCES FOR GRAVITY SEWER SERVICES
PART 1 - SCOPE
This section describes the materials for appurtenances to be used in construction of gravity
sewerage services as shown on the Plans and specified.
PART 2 - SEWER CONNECTIONS AT MANHOLES AND WET WELLS
The first joint shall be not more than 24" from the outside of the manhole. PVC pipe must
enter the manhole through an elastomeric manhole coupling as manufactured by Kor-N-Seal,
Inc. or approved equal.
PART 3 - CLEAN OUTS
Clean -outs shall be provided immediately prior to the service lateral end and where shown or
specified. Clean-out sizes for pipe 8 inches or larger in diameter shall be not less than 6
inches in diameter. Clean out sizes for pipe less than 8 inches in diameter shall be of the
same diameter as the pipe except at the ends of service laterals where they may be 4 inch
in diameter as shown on the Drawings.
Materials for Clean-out construction shall be as shown on the drawings.
SDIRC Middle School "BB"
END OF SECTION
02532-1
02532 - Appurtenances for Gravity Sewer
J
SECTION 02533
TESTING OF GRAVITY SEWER SYSTEM
1.01 GENERAL
The Contractor shall perform testing of all sanitary gravity sewers as set forth in this section and
shall conduct the tests in the presence of a authorized County representative and the project
Engineer. The Contractor shall schedule the tests with the County at least five days in advance.
1.02 LAMPING
Lamping shall be conducted as installation of the line progresses. The installed sewers shall be
visually inspected by "lamping" between each manhole, lamphole, or other structures in order to
ascertain that they are clear, to correct alignment and have no visual bellies. The concentricity of the
lamp image received shall be such that the diameter of said image shall have no vertical or horizontal
reduction from that of the pipe inside diameter.
1.03 PRE — T.V. DEFLECTION TESTING
Deflection testing shall be performed on all flexible pipe (thin wall PVC, HDPE, etc.) after the final
backfill has been in place a minimum of 30 days. A rigid ball or mandrel shall be used which shall
have a diameter at least 95 percent of the base inside diameter or average inside diameter of the pipe,
depending on the specified ASTM pipe specification. The test shall be performed without
mechanical pulling devices. No pipe shall exceed a deflection of 5 percent. If deflection exceeds 5
percent, the pipe shall be replaced or corrected in accordance requirements in the approved
specifications.
1.04 T.V. INSPECTION
Upon completion of deflection testing, gravity sewer mainline between manholes will be inspected
by the Contractor, using a television camera. TV inspection will be done at a point in time that the
area of pipe construction has been compacted and road material compacted to support heavy trucks.
Service laterals shall be thoroughly flushed. Mainlines shall then be jet cleaned prior to inspection.
Any sand or dirt found in the sewers shall be removed by the Contractor. All leaking joints or
fittings shall be replaced, encased with concrete or sealed from the inside with grout as determined
by the Engineer and Owner. All cracked or defective pipe shall be replaced by the Contractor.
Bellies in the pipe or at the joints which retain more liquid that allowable shall be replaced. TV re-
inspection as required by the Engineer or the Owner will be at Contractor's expense.
1.05 INFILTRATION/EXFILTRATION TESTING
All sewer mains, house laterals and manholes shall be subjected to infiltration and/or exfiltration
tests. In general, infiltration testing shall be performed on sewers lying below the ground water table
and exfiltration testing shall be performed on sewers lying above the groundwater table. (The Owner
and project Engineer shall agree which type of test shall be utilized for each section of pipe being
tested.
A. Infiltration Test: Infiltration testing shall be conducted in a dry system prior to the system
being filled with water. Testing shall proceed for a continuous period of four hours with
infiltration amounts measured by a weir or other approved method by the City. In no case
02533-1
k
L
02533 — Testing Gravity Sewer System
shall the infiltration exceed 50 gal/day/inch of pipe diameter/mile of pipe (or 0.4
gal/hr/in/ 1000 ft).
B. Exfiltration Test: Exfiltration testing shall be conducted by filling the system with water
and measuring the amount of exfiltration. Water shall be added to the system until the
manhole with the lowest top elevation (test manhole) of that portion of the system being
tested is filled to within 24 inches of its top. Testing of the system shall be segmented
such that the difference between the top elevation of any two manholes being tested does
not exceed 2 feet. Testing shall proceed for a continuous period of four hours with
exfiltration amounts measured by adding known amounts of water to the beginning
water level in the test manhole. In no case shall exfiltration exceed 100 gal/day/inch of
pipe diameter/mile of pipe (or 0.8 gal/hr/in/1000 ft). Leakage from any manholes shall
be included in the pipe exfiltration determination.
C. Air Leakage Test: Air leakage tests may be required in lieu of infiltration/exfiltration at
the option of the Owner. Air leakage tests on PVC gravity sewer pipe shall conform to
ASTM F-1417. The testing shall be by compressed air from manhole to manhole. Plugs,
caps and branch connections must be secured against blow -off during the test. The pipe
and manholes shall be free of water during the test. The pipe shall be tested at 3.5 psi in
excess of the groundwater pressure above the pipe. For each foot of water above the
pipe at the deepest point, the air pressure shall be increased by 0.43 psi. The minimum
time for the air pressure to drop by 0.5 psi shall be:
Pipe Size Time in Minutes
6
inch
4.0
8
inch
5.0
10
inch
6.5
12
inch
7.5
15
inch
9.5
D. Test Failures: Should a test failure occur, necessary repairs shall be accomplished by the
Contractor and the test repeated until within the established limits. The Contractor shall
furnish the necessary labor, water, and all other items required to conduct the required
testing and shall perform the necessary system repairs required to comply with the
specified test. If the water supply is from the County's potable water system, a meter is
required. Contractor is responsible for all costs associated with retesting.
END OF SECTION
02533 - Testing Gravity Sewer System
02533= 2
J
SECTION 02534
SANITARY SEWER FORCE MAINS
imei31 1p1:7\fw
A. Scope
The work to be performed under this Item shall include the furnishing of all materials,
equipment and labor required for the installation of force mains as herein described and as
shown on the Plans. The Contractor shall perform all excavation, backfilling, compacting,
testing and related work required for the construction of these mains in accordance with the
provisions set forth under the applicable items of this Specification.
B. References
Standards applicable in this Specification shall be:
1) American Water Works Association (AWWA) and American National Standards
Institute (ANSI).
a. AWWA C104 (ANSI A21.4) Cement -Mortar Lining for Ductile -Iron and
Gray -Iron Pipe and Fittings for water.
b. AWWA (ANSI) C110 Gray -Iron and Ductile -Iron Fittings, 34nch through 48 -
inch for water and other liquids.
C. AWWA C111 (ANSI A21.11) Rubber Gasket Joints for Ductile -Iron and Gray -
Iron Pressure Pipe and Fittings.
d. AWWA C150 (ANSI A21.50) Thickness Design of ductile -Iron Pipe.
e. AWWA C151 (ANSI A21.51) Ductile -Iron Pipe, Centrifugally cast in Metal
Molds or Sand Lined Molds for water or other liquids.
f. AWWA C153 (ANSI A21.53) Ductile -Iron Compact Fittings, 3 -inch through
112 -inch for water and other liquids.
g. AWWA (ANSI) C600 Installation of Gray and Ductile Cast Iron Water Mains
and Appurtenances.
h. AWWA (ANSI) C900 Standard for Polyvinyl chloride (PVC) Pressure Pipe,
4 -inch through 12 -inch.
i. AWWA (ANSI) C905 Standard for Polyvinyl Chloride (PVC) water
transmission pipe, nominal diameters 14 -inch through 36 -inch.
2) American Society for Testing and Materials (ASTM)
a. ASTM D-1248 Polyethylene Plastics Moldings and Extrusion Materials.
3) American Association of State Highway and Transportation Officials
02534— Sanitary Sewer Force Mains
02534 -1
a. AASHTO T-99 (2.5 kg.) Rammer and a 12- inch (305 mm) Drop, as modified
by T-99-801 (Dated 1981).
b. AASHTO T-180 Density Relations of Soils using a 10 lb. Rammer and an 18 -
inch drop.
C. Submittals
1) Shop Drawings - Prior to any fabrication or installation work, the Contractor shall
furnish to the Engineer, for review and approval five (5) sets of shop drawings for the
following items.
a. Material specifications for all pipe types, fittings, joints, joint restraint, and
specials.
All drawings shall be reviewed, approved and stamped by the Contractor pursuant to
the provisions of the General Conditions, Article 6.24 through 6.28.
2. MATERIALS
A. Pipe
1) Ductile Iron Pipe - All ductile iron pipe shall conform to AWWA C151, ANSI A21.51
and have a rated working pressure of 350 psi (minimum). All pipe shall be factory
lined and coated. The pipe interior shall receive a 40 mil lining of "Protecto 401".
The exterior of the pipe shall have a minimum 10 mil. thick bituminous coating in
accordance with AWWA C 151.
The pipe shall be marked the entire length with three color coded stripes. These stripes
shall be applied in the manner as the required ASTM coding using paint and with the
word "Force Main" in %-inch high letters appearing one or more rimes every 21 -
inches. As an alternative to lettering, buried pipe may be continuously spiral wrapped
with plastic identification tape marked "Force Main". Lettering or identification
tape shall be brown in color for force main.
Ductile Iron Pipe shall conform to the following classes:
a. Ductile Iron Pipe under roadways shall be minimum pressure class 350.
b. Flanged Ductile Iron Pipe shall be minimum thickness class 53.
C. Ductile Iron Pipe in roadway shoulders or in unimproved areas shall be
minimum pressure class 350.
Unless otherwise indicated on the Drawings, ductile iron pipe shall be furnished in
standard 18 or 20 foot laying lengths.
2) Polyethylene pipe used for directional bored sanitary sewer shall meet the
specifications of SECTION 02400, paragraph 2.A. Pipe shall be co -extruded with green
colored sheath or green striping.
02534— Sanitary Sewer Force Mains
02534 - 2
B. Fittings
All underground fittings shall be ductile iron with mechanical or manufacturer's
mechanically restrained joints. Fittings shall conform to the following:
1) Fittings for pipe shall be compact ductile iron conforming to AWWA C 153. Fittings
shall have a minimum pressure rating of 350 psi. All fittings and the appropriate
number of downstream and upstream joints must be restrained.
2) All fittings shall be lined and coated as specified for ductile iron pipe.
3) Retainer glands or thrust blocks for restraint shall not be permitted.
C. Joints
1) Push on Joints - Joints for D.I. pipe shall be bell and spigot, rubber gasket
compression, push -on type as specified in AWWA C111 (ANSI A21.11). Special
fittings and joints shall be considered for specific installation.
2) Mechanical Joints - Mechanical joints may be used for downstream restrained joint
pipe. In this circumstance, the joint shall be restrained in accordance with the
following paragraph C.3) d.
3) Restrained Joints - Fittings used for changes in alignment, size reduction, valves and
plugs shall all be restrained along with the appropriate number of downstream and
upstream joints. Restraint shall be by the use of mechanical methods. As indicated
on the drawings, pipe lengths located upstream and downstream of restrained fittings
shall also be restrained. Method of joint restraint shall be as follows:
a. Ductile iron pipe with manufacturer's mechanical restrained joints using
locking rings or wedges may be utilized. These restraints shall be American Pipe
"LOK-FAST" joints, McWane "SUPER LOCK" or approved equal.
b. Ductile iron pipe and fittings with mechanical joint ends shall be restrained
with Ebba Iron "MEGA -LUG" grip type restrainers, series 1100.
C. Ductile iron pipe with push -on joint ends shall be restrained with "UNI -
FLANGE", large diameter, series 1390 restrainers, or approved equal.
d. Retainer glands or locking gaskets shall not be approved as mechanical
restraints.
4) Gaskets - All gaskets shall be manufactured of an elastomeric material. The gasket
shall provide a positive, tight seal under all combinations of joint and gasket
tolerances. Installation and lubrication of gaskets shall be as directed by the
manufacturer.
D. Foundation Rock
02534 - 3
02534- Sanitary Sewer Force Mains
E.
A sieve analysis of Foundation Rock shall conform to the following limits:
Passing 3/4" - 100%
Passing 3/8" - 20 - 55%
Passing #4 - 0 - 10%
Passing #8 - 0 - 5%
Buried Trace Wire
All mainlines, fittings and appurtenances installed underground shall have #10 gauge, type
THHN stranded copper trace wire attached for locating purposes. Trace wire shall have a
brown colored sheath for wastewater force mains.
3. EXECUTION OF WORK
The
installation and testing of the mainlines shall be
done in
accordance with AWWA (ANSI) C600,
plus
the additional requirements described herein or as
shown
on the Plans.
A. Preparation
1) Clearing - The Contractor shall perform all clearing necessary, where applicable, for
the proper installation of all mainlines and appurtenances in the locations shown on
the drawings. Plantings, ornamental shrubbery, protected trees, utility poles or
structures subject to damage resulting from the excavation shall be transplanted,
relocated, braced, shored or otherwise protected and preserved unless otherwise
directed by the Engineer. Protected trees shall be considered as all trees outside five
(5) feet either side of the mainline to be installed. Only under special circumstances
with Engineer's written approval may trees outside these limits be considered for
removal. All debris generated from the clearing process shall be disposed of by the
Contractor at a disposal site approved by the Engineer.
B. Trenching
1) Pavement Cutting - Asphaltic pavements shall be cut by pneumatic hammers or
mechanical pavement cutters; saws, or other method approved by the Engineer.
Concrete pavement or concrete base pavement shall be sawed. Both types of pavement
shall be cut and removed prior to any excavation.
2) Excavation - The excavation in which the pipes and appurtenances are to be
constructed shall be excavated in open cut, except where otherwise stated on the Plans,
in such a manner to such depths and widths as will give suitable room for bracing,
supporting, pumping, draining and for removing from the excavation any material
which the Engineer may decide is inadequate for foundation. The maximum trench
width at the top of the pipe shall be in accordance with the trenchingdetails.
The Contractor may, where it will not interfere with the work or adjacent structures or
property, slope the sides of excavation. The sides of the trench may only be sloped
from a point in compliance with the trenching details. No compensation will be
allowed for such excavation and the Contractor shall include its cost in the prices bid.
The materials of excavation shall include all materials encountered, such as clay, sand,
rock, marl, muck, gravel, boulders, heterogeneous fill materials, old timbers, or any
combination of these. Any unforeseen obstacles such as buried trees or timbers,
02534- Sanitary Sewer Force Mains
02534 = 4
abandoned utilities, metal objects, concrete masses or any debris encountered shall be
removed. All "materials of excavation" and "unforeseen obstacles" will be considered
as incidental to construction and no additional compensation will be allowed.
All roots, stumps, logs, limbs, boulders or any material which is not suitable for
backfill material shall be removed from the site promptly as excavated and disposed of
by the Contractor at his expense.
3) Length of Trench to be Opened - The length of trench to be opened or the area of
surface to be disturbed and unrestored at any time will be limited by the Engineer with
regard to expeditious construction and the convenience of the Owner. Excavation shall
not advance more than 100 feet ahead of the pipe laying without the consent of the
Engineer.
4) Sheeting and Bracing - The Contractor shall be responsible for properly supporting the
sides of all trenches and excavations with timbers or other supports wherever necessary
or required to properly safeguard the trenches, adjacent properties and structures and at
restricted right-of-way. The cost of all necessary timber, sheeting and bracing
whatsoever (left in place or removed), shall be included in the unit prices bid for
mainlines.
Portions of the timber sheeting driven below the elevation of the top of the pipe shall
not be disturbed or removed.
Timber sheeting and bracing shall be left in place if so ordered by the Engineer and/or
where shown on the Plans to avoid undermining or otherwise endangering the work or
adjacent structures.
All sheering left in place shall be cut off or driven at least 18 -inches below finished
grade, unless otherwise ordered.
Great care shall be exercised in the selection of sheeting and bracing of adequate
design, type, size and strength. The adequacy of the timber used for all supporting and
bracing purposes shall be the responsibility of the Contractor, who shall use only men
of seasoned experience for this type of work. The sizes and lengths of the timber used
shall conform closely to the needs of the work and oversizing as well as undersizing
should be avoided.
In placing and driving the sheeting, proper workmanship and equipment shall be used
to achieve a true alignment and close contact of the sheeting boards. Timber sheeting
shall be straight and sound, free from shakes, cracks, large or loose knobs and other
defects impairing its strength and durability. It shall be squared to the required
dimension throughout its entire length. If required for the proper execution of the work
where running sand, quicksand or other semifluid material difficult to handle is
encountered, the timber sheering shall be tongue and groove.
The Contractor may, in lieu of sheeting, bracing and shoring to maintain the allowable
trench widths, use a "trench box" ("trench shield" or "mule") provided pipe sections
are secured downstream by a cable(s) stretched through and secured to the end section
of pipe by means of a timber and a cable clamp, all materials being of adequate size
and strength. The cable shall be held taut during the process of advancing the "box".
02534 - 5
02534— Sanitary Sewer Force Mains
This procedure may be used so long as, in the opinion of the Engineer, the work is
proceeding satisfactorily. The Engineer may revoke permission to use the "trench box"
at any time he feels unsatisfactory or inadequate work is being performed and the
Contractor shall, without appeal, immediately begin using sheeting, bracing and
shoring to maintain the allowable trench widths.
At all times, when soil conditions permit, the bottom edge of the "trench box" shall be
no lower than the springline of the pipe, so as to disturb the trench compaction when
advancing the "trench box".
5) Placing of Excavated Material - All excavated materials shall be placed where
indicated by the Engineer in such a manner as not to endanger the work and so that free
access will be maintained at all times to all parts of the trench and to all fire hydrants
and their gate valves in the vicinity. Such material shall be neatly piled so as to
interfere as little as possible with traffic.
6) Drainage - The Contractor shall furnish sufficient pumping or other dewatering
equipment and shall provide at his own expense satisfactory drainage whenever needed
in trenches and other excavations during the progress of the work and its completion
for inspection. Water shall not be allowed to flow over or raise upon any concrete,
masonry or pipe until work has been inspected and the mortar or concrete has properly
set.
Unless otherwise permitted by the Engineer, the water table shall be lowered by the use
of a well point system. Open trench pumping may be permitted only upon approval by
the Engineer of the method of pumping and drainage to be used. If open trench
pumping is approved, the water must be conveyed entirely through approved coarse
material placed below the bottom of the foundation. The depth of this coarse material
shall be determined by the Contractor and approved by the Engineer.
Materials and workmanship used for the well point system shall be in keeping with the
approved standard practice. The well point system shall function so as to enable pipe,
concrete cradle and appurtenances to be installed without interference from running or
standing water at the bottom of the trench. The Engineer shall make the final decision
as to the acceptability of the well point system or any part thereof.
Where necessary, pea gravel or graded sand shall be used in conjunction with the well
points as they are installed in insure continuous pumping in the dewatering of fine
material.
The cost of dewatering shall be included in the various unit prices bid under the
mainlines.
7) Disposal of Water from Excavations - All water pumped or bailed from trenches or
other excavations shall be conveyed in a proper manner to a suitable point of discharge
by the Contractor at his own expense.
The Contractor shall provide for the disposal of water removed from excavations in a
manner that will not cause injury to public health, private or public property, any
portion of the work completed or in progress, the surface of the streets, or cause any
impediments to the reasonable use of the site by other Contractors. The Contractor
shall be responsible for complying with all the local regulations and those of the
02534- Sanitary Sewer Force Mains
02534 - 6
Department of Environmental Protection regarding pollution of waterways. Should the
size of Contractor's dewatering equipment, or the quantity of disposed water, or the
method of disposal require a St. Johns' River Water Mgmt. District permit, the
Contractor shall obtain such permit at no additional expense to the Owner and with no
additional time added to the Contract. The Contractor shall take special precautions to
eliminate any odor problems resulting from the discharge of sulfide water, such as the
use of submerged discharge outlets and overflow basins.
8) Preparation of Trench - Trenching as shown on the Plan details shall be standard for
this project. The trenches shall be constructed by excavating to the depth indicated on
the Plans. The trenches shall then be manually shaped to fit the bell and lower
quadrant of the pipe barrel.
Mechanical excavation shall be limited to provide an undisturbed trench bottom for the
lower quadrant and bell of the pipe. Final excavation shall require hand shaping for
placement of the pipe. If mechanical over cutting occurs, the pipe bedding shall consist
of four (4) inches of washed and graded sand or crushed rock on undisturbed soil.
C. Laving_of Pipe
All pipe, fittings and valves shall be installed according to AWWA Specification C600. Prior
to installation, all pipe and appurtenances shall be examined for damage and defects. Under no
circumstances shall defective pipe be installed. All lumps, blisters and excess coating materials
shall be removed from the socket and plain ends of each pipe. While being placed in the
trench, care shall be taken to prevent foreign material from entering the pipe.
As each length of pipe is placed in the trench, the joint shall be assembled and the pipe brought
to correct line and grade. At times when pipe laying is not in progress, the open end of the pipe
shall be closed by a watertight plug. When practical, the plug shall remain in place until the
trench is pumped completely dry. When it is necessary to deflect the pipe from a straight line
in either the vertical or horizontal plane, or where long radius curves are permitted, the amount
of deflection shall not exceed that of Table 5 and 6 in AWWA Specification C600.
1) Thrust Restraint - All dead ends, valves, tees, and fittings for changes in alignment
shall be appropriately restrained against pipeline thrust. All changes in alignment
shall require the fitting and appropriate length of upstream and downstream pipe to be
mechanically restrained with approved devices.
2) Backfill
a. General - Where the trench has been dewatered, backfilling must progress
sufficiently before pumps are shut off to prevent flotation of pipe. Any pipe that has
been displaced perceptibly from its correct position shall be removed and relaid
properly at the Contractor's expense. Backfilling shall follow pipe laying within 100
feet, unless otherwise directed by the Engineer, but shall not be performed in any case
until the Engineer has approved the line for backfilling. Water shall not be added
except as required to obtain Optimum Moisture Content and "flooding' or "puddling"
for compaction will not be allowed.
Backfill material shall be free of roots, logs, limbs, clays, large rocks or any material or
debris determined to be unsuitable by the Engineer. The Engineer may reject any
material which he considers unsuitable for backfill. The compaction procedures
02534 - 7
02534— Sanitary Sewer Force Mains
3)
specified herein shall be considered "minimum procedures" to prevent after -settlement
and the Contractor shall reopen, refill and recompact any trenches indicating improper
backfill procedures or after -settlement.
All road crossings shall be backfilled immediately, made passable and maintained
passable until the permanent repair is made.
b. All Other Areas Under Pavements - The initial lift shall consist of clean, fine,
select materials, not exceeding 3/4" in diameter under the haunches of the pipe. The
material shall be placed in layers not to exceed 4". The initial lift shall be manually
compacted to 95% of the maximum density as determined by AASHTO T-180.
Subsequent lifts to 12" above the pipe shall be constructed as specified for the initial
lift, except that had operated mechanical tampers may be used. Additional lifts from
12" above the pipe to the top of subgrade shall be carefully backfilled with material
free from organic material and stones or clumps exceeding 3 -inches (2 -inches in the
final 6 -final layer) in diameter, and compacted in 6 -inch layers to an average maximum
density of 95% as determined by AASHTO T-180.
C, Areas
Outside
of
Pavements - Backfill
of all
areas outside of pavements shall
be constructed
as specified above for "all other
areas
under pavements" except that the
additional lifts
shall be constructed as specified
to the
finished grade.
d. Density Testing - The Contractor shall arrange to have sufficient soil tests
made by an independent testing laboratory approved by the Engineer to demonstrate
conformance of his work with the stability and compaction levels required by these
specifications. Compaction tests shall be taken at intervals listed herein or as deemed
necessary by the Engineer.
In no case shall the Contractor proceed with construction over compacted material until
the tests prove satisfactory and approval is given by the Engineer.
In general, at least one test for maximum dry density/optimum moisture content shall
be performed on a representative sample of each inherently different material to be
used for compacted backfill or embankment fill.
As a minimum, in-place density tests shall be performed at the rate of one test location
per 200 lineal feet (or fraction thereof) of trench on the compacted backfill and under
each drive lane at all open cut, roadway crossings. Tests shall be taken in one foot lifts
beginning at one foot above the pipe and ending at the final grade. Test locations shall
be as directed by the Engineer or his authorized representative. If any test results are
unsatisfactory, the Contractor shall re -excavate and recompact the backfill, at his
expense, to the extent directed by the Engineer until the required compaction is
obtained. The cost of all proctor and density tests shall be the responsibility of the
Contractor and shall be included in the cost of installed and completed water main.
Installation of Trace Wire
02534 - 8
02534- Sanitary Sewer Force Mains
Trace wire shall run continuously along the pipeline from valve to valve or fitting. All
splices shall be hot -soldered to provide continuity along the entire installation.
Installation and splicing shall be in accordance with the details shown on the following
insert.
4) Separation Requirements
Force mains shall be laid at least ten (10) feet horizontally from any existing or
proposed water main. Force mains crossing water mains shall be laid to provide a
minimum vertical clearance of 18 inches between the outside of the water main and the
outside of the force main. Where the force main passes over the water main, there shall
be no joints within 10 feet of the water main.
D. Field Quality Control
1) Hydrostatic Tests - The Contractor shall provide all necessary testing materials and
shall perform all work required in connection with the test. All pipe shall be tested to a
hydrostatic pressure of 100 p.s.i. for force mains and 150 p.s.i. for reuse mains. The
required pressure as measured at the point of highest elevation shall be applied for not
less than two hours, and all pipe, fittings, valves and joints shall be made water tight if
leakage is evident. At a maximum, mains shall be tested from shut-off valve to shut-off
valve. New mains shall be temporarily plugged or valved and pressure tested prior to
tie-in or modification of existing pressure mains.
No ductile iron pipe installations will be accepted unless and until the leakage is less
than that as specified under Section 4.2 of the AWWA (ANSI) C600, P.V.C. pipe
installations shall meet the leakage requirements of AWWA M23 as applicable.
E. Adjusting and Cleaning
1) Restoring Surfaces - The top surfaces of the backfill shall be restored to the original
or planned conditions. Trenches shall be carefully examined upon the completion of
backfilling and surface irregularities that are dangerous or obstructive to traffic are to
be removed. Paved sections shall conform in grade with adjacent areas and shall be
of at least equal quality. Design mixes for flexible pavement shall be subject to
approval by the Engineer. All damaged or undermined areas of existing pavement, not
previously removed, shall be removed and restored to original conditions or in the
specified manner.
Equipment shall not travel over loose rock fragments, or other hard material, lying on
sections or pavement which are not to be removed. Removal, replacement and
restoration of areas of pavement shall be as indicated on drawings.
F. Connection to Existing Mains
The Contractor shall make no connection (open new valve) to another Contractor's work or
the Owner's existing mains unless the work has been substantially completed, accepted, and
paid for by the Owner, or expressed written permission to connect to the work has been given
by the other Contractor and said written permission has been forwarded to the Engineer.
END OF SECTION
02534 - 9
02534- Sanitary Sewer Force Mains
1.
2.
3.
SECTION 02535
TESTING FORCE MAINS
SCOPE
A. This Section describes the procedural, material, and acceptance requirements for
cleaning and testing of the mainlines with regard to quality, alignment, tightness, and
overall integrity of the installed system.
GENERAL
A. The Contractor shall furnish all labor, materials, transportation, pumps, gauges, and
equipment necessary to flush and test the installed pipe system as required by these
Specifications.
B. The Contractor shall provide and install all temporary connections, corporation stops,
blowoffs, and the like required for flushing and testing, and upon completion of
satisfactory tests, shall remove same and install appropriate plugging/capping devices
or permanent connections as required.
Co The Contractor shall notify the Owner and Engineer at least 48 hours in advance of
all acceptance testing to be performed. No testing for acceptance of the work shall
begin until the Owner and Engineer or his authorized representative are present.
D. No interconnection shall be made between the new work and an existing active pipe
system, except that necessary and approved by the Owner for testing, until the work
is approved for use by the Engineer and until all approvals and clearances required by
applicable construction permits for use of the work are issued by the permitting
agency.
E. At least 3 business days prior to conducting each item of work under this Section, the
Contractor shall submit to the Engineer for approval a description of the specific
equipment, materials, and procedures to be used, plus identification of proposed
water source(s), to be used for this particular work item.
FLUSHING
A. Upon completion of each run of pipe between main valves or between a main valve
and a terminal point, the pipe run shall be flushed with clean water at a minimum full
diameter velocity of 2.5 ft./sec. in order to remove sand, debris, and other foreign
materials prior to pressure testing.
B. The pipe run to be flushed shall be slowly filled with clean water with all valves open
to allow escape of air pockets. High points in the pipe shall be vented with air release
valves. When the system is full and prior to flushing, all valves shall be fully closed.
02535 = 7
02535 - Testing Force Mains
C. Flushing shall continue until a minimum water volume of two times the aggregate
pipe volume has passed through the pipe section being cleaned. The aggregate pipe
volume shall include all pipe carrying flushing water from the point of introduction
to the work to the point(s) of discharge from the run being cleaned.
D. For nominal pipe sizes of 6 inches and smaller, the pipe shall be flushed through a
discharge extension of at least the full pipe diameter. For nominal pipe sizes greater
than 6 inches, a 6 inch diameter discharge extension pipe, connected to the work with
reducer(s), may be used in lieu of a full diameter blowoff.
E. Flushing water shall be carried beyond the trench and shall be discharged in a manner
that will not cause erosion nor structural damage on or off-site, and will not cause
contravention of State water quality standards in receiving surface waters. The
Contractor shall provide adequate extension pipe, sedimentation basin(s), and/or
diffusion devices as necessary to prevent such damage.
4. HYDROSTATIC LEAKAGE AND PRESSURE TESTING
A. Hydrostatic pressure and leakage tests for ductile iron pipe shall conform with
Section 4 of AWWA C-600 Specification with the exception that the Contractor
shall furnish all gauges, meters, pressure pumps and other equipment needed to test
the line. P.V.C. pipe shall be tested in accordance with the applicable sections of
AWWA M23. Upon completion of flushing, the installed pipe system shall be
tested for tightness under a continuous hydrostatic gauge pressure of 25 psi and then
100 or 150 psi as applicable, ± 5 psi, determined at the lowest point in the system, for
a period of 2 hours. The allowable leakage rate shall not exceed that defined in and
specified by AWWA C600-82 or AWWA M23.
B. If the work is subject to acceptance by a municipal or private utility with its own
adopted test requirements more stringent than those stated herein with regard to
pressure, duration, and/or allowable leakage rate, such requirements shall supersede
these specifications.
C. Testing shall be performed separately on each valved -off section of the installed
system. Testing shall be against closed in-line valves with each valve in the system
subject to the full test pressure differential for full test time at least once during the
course of testing.
D. Allowable leakage shall be calculated based on the pipe diameter(s) and total laid
length of the run being tested, with no additional allowance for fittings, or joints. No
visible leakage shall be allowed.
If visible leakage is noted during the course of testing, or if allowable leakage is
exceeded, such leakage shall be repaired to the satisfaction of the Engineer and the
test repeated or extended for an additional period up to the full test time with suitable
adjustment for previous make-up water used, at the Engineer's discretion.
02535 = 2
02535 - Testing Force Mains
E. The pumping/pressurizing and make-up water measuring equipment shall be
provided by the Contractor and approved by the Engineer prior to testing. The
pressurizing equipment shall be designed and operated in a manner that will
minimize pressure surging and pulsing within the pipe.
F. The Contractor shall provide and install a temporary valved tap with a 1/4" FPT
connection to receive the pressure gauge in each pipe run to be tested. Upon
satisfactory completion of testing, the Contractor shall remove and plug the pipe.
G. In preparation for testing, the pipe shall be slowly filled with clean water from an
approved source, taking care to purge all air pockets. Water remaining in the pipe
system after flushing may be used and supplemented as necessary with prior approval
by the Engineer, and clean test water may be reused for sequential testing of pipe
segments.
H. In conducting the test, water shall be pumped into the full pipe until test pressure is
attained, and make-up water shall be added as soon as the pressure drops to 5 psi
below test pressure. All make-up water shall be accurately measured, and the total
test leakage shall be defined as the volume of make-up water added.
I. Should the tested section fail to meet these requirements, the Contractor shall, at his
own expense, locate and repair the defects and retest the section until it is acceptable.
J. Immediately upon completion of a passing pressure test, all valves shall be operated
to insure their full opening and closing.
02535 — Testing Force Mains
02535 - 3
r
SECTION 02536
PAVEMENT MARKINGS
PART 1 - GENERAL
1.1 SCOPE
A. This Section discusses painting thermoplastic traffic stripes and pavement
markings.
1.2 TEMPORARY TRAFFIC STRIPING AND MARKING
A. If required for traffic safety or if required by the ENGINEER or other agencies having
jurisdiction, install temporary traffic striping and marking as soon as practical after
the asphalt has been laid. If the temporary traffic stripes or marks become faded
out before the permanent stripes and marks are applied, repaint them at no
additional expense to the OWNER.
B. Maintain safety along the road improvements using warning signs, traffic cones,
emergency lights, and other necessary equipment until the temporary traffic striping
and marking is applied.
1.3 TRAFFIC STRIPES AND MARKINGS WITHIN D.O.T. RIGHT-OF-WAY
A. Use thermoplastic traffic stripes and markings for all work within FDOT right -of --ways
and apply per Section 711 of the D.O.T. "Specifications for Road and Bridge
Construction" and any other applicable D.O.T. specification or regulation articles
711-9 and 711-10 do not apply
B. At least 30 days must pass after the asphalt has been laid before any thermoplastic
stripes or markings may be applied.
1.4 THERMOPLASTIC
STRIPES
AND
MARKINGS WITHIN COUNTY
RIGHT-OF-WAY
AND
ON SITE
PAVING
A. All thermoplastic stripes and markings to be applied within County right-of-ways or
where shown on the DRAWINGS for the project site paving, shall be applied per
paragraph 1.3 above and the Manual on Uniform Traffic control Devices.
1.5 INTERIOR ROADWAY AND PARKING LOT STRIPING
A. The work under this heading consists of constructing centerline roadway stripes,
stripes on the edge of the roadway, and parking spaces, stop bars, pavement
markings etc, where shown on the DRAWINGS as either paint or thermoplastic.
02536-1 02536 — Pavement Markings
B. COLORS - All road centerline stripes shall be yellow. All road edge stripes, stop
bars, parking spaces stripes, markings, etc, shall be white. Handicap areas shall be
painted per the details on the Drawings and all stripes and markings per the Manual
on Uniform Traffic Control Devices (MUTCD).
C. PAINT
1) The paint shall be traffic paint formulated and manufactured from first grade
materials. It shall be free from imperfections and defects that may adversely
affect the finished product.
2) The paint shall conform to the FDOT Standard Specification for Road and
Bridge Construction Section 710. Submit shop drawings containing the
manufacturer's technical literature on the paint in accordance with Section
01340.
3) GLASS BEADS - The road centerline stripe, edge of road stripes, stop bars,
and all other painting within the road shall have durable reflective glass
spheres. The glass spheres shall be applied at a rate of 6 pounds per gallon
of paint while the paint is still tacky enough for them to adhere. Glass
spheres are not required for parking lot space stripes. .
D. APPLICATION OF THE PAINT
1) Wait a minimum of 3 weeks after laying the asphalt before applying paint to
it. Equipment and application shall comply with FDOT Standard
Specification for Road and Bridge Construction Section 710-3, 7104, and
710-5.
2) Paint stripes shall be as per the MUTCD. Before applying any striping, mark
the locations with chalk, tacks, or other suitable means.
3) The paint application equipment shall be in good working condition and shall
apply the paint uniformly at the required thickness with well-defined edges.
The pavement surface must be dry when the paint is applied.
4) All paint spills, application defects, alignment errors, discolored paint, etc.,
shall be removed in a manner that will remove the paint without harming the
pavement.
+ + END OF SECTION + +
02536-2 02536 — Pavement Markings
SECTION 02537
TRAFFIC SIGNS
PART 1
- GENERAL
1.1 SCOPE
A. Furnish and install street signs and traffic control signs as specified.
1.2 GENERAL
A. All signs shall meet the requirements of the "Federal Highway Administration
Manual of Uniform Traffic Control Devices latest edition. Sign locations shall be
subject to the approval of the Indian River County Public Works Department, Traffic
Engineering Division.
Be The Contractor shall replace all signs damaged during its work, at its expense. The
ENGINEER shall determine if damages are such that a new sign will be required.
+ + END OF SECTION + +
02537-1 02537 — Traffic Signs
PART 1- GENERAL
1.01
1.02
1.03
SECTION 02539
SUBMERSIBLE PUMPING STATION
RELATED WORK SPECIFIED ELSEWHERE
A. Site Work Division 02000 Sections
B. Concrete Work Division 03000 Sections
C. Coating Systems Division 09000 Sections
D. Electrical - General Division 16000 Sections
SCOPE OF SERVICES
A. The pumping station shall consist of a wet well structure, two (2) submersible sewage pumps,
an electrical control panel, liquid level controls, valve vault, valves, pump -out connection,
electric meter, electric and water service and all appurtenant piping and equipment as shown
on the Drawings and/or as specified.
B. The Contractor shall furnish all labor, materials, equipment and incidentals required and
install, place in operation, and field test a submersible wastewater pumping station. The
station shall be complete with pumps, motors, piping, valves, buried electric service,
electrical work (including motor controls and RTU), structures, connections and
appurtenances, tested and ready for service.
C. These specifications are intended to give a general description of what is required, but do not
cover all details which will vary in accordance with the requirements of the equipment as
offered. It is, however, intended to cover the furnishing, the shop testing, the delivery and
complete installation and field testing, of all materials, equipment and appurtenances for the
complete pumping units as herein specified and as shown on the Drawings, whether
specifically mentioned in these specifications or not.
D. For all units there shall be furnished and installed all necessary an desirable accessory
equipment and auxiliaries whether specifically mentioned in these specifications or not, and
as required for an installation incorporating the highest standard for the type of service
including field testing of the entire installation and instructing the regular operating personnel
in the care, operation and maintenance of all equipment.
PUMP SYSTEM REQUIREMENTS
A. Qualifications:
1. To assure unity of responsibility, the motors and control system shall be furnished
and coordinated by the pump manufacturer. The Contractor and manufacturer shall
assume responsibility for the satisfactory installation and operation of the entire
pumping system, including pumps, motors, and controls as specified.
2. The pumps covered by these specifications are intended to be standard pumping
equipment of proven ability as manufactured by a reputable manufacturer having
long experience in the production ofsuch pumps. The pumps furnished shall be
designed, constructed and installed in accordance with the best practice and methods,
02539 - Submersible Pump Station (Rev.)
02539-1
and shall operate satisfactorily when installed. Pumps shall be manufactured in
accordance with the Hydraulic Institute Standards.
3. The control system shall be manufactured by a company with an established record
of successful performance for similar products.
4. All equipment furnished under this specification shall be new and shall be the
standard product of manufacturers having a successful record of manufacturing and
servicing the equipment and systems specified herein for a minimum of five (5)
years.
5. The pumps shall be furnished complete with controls, and accessories required and
shall be as manufactured by Flygt or ABS.
1.04 SUBMITTALS
A. Shop Drawings - The Contractor shall furnish the Engineer a minimum five (5) copies of
shop drawings of the items listed below, prior to their delivery. This shall be done in
accordance with the provisions of the General Conditions.
1, Pumps
2, Pump Accessories
3. Access Covers
4, Control Panel and RTU
5, Electrical Devices
6. Precast Structures
7. Poured In Place Concrete Design Mix
B. Manufacturer's Data - The Contractor shall furnish the Engineer a minimum five (5) copies of
manufacturer's data of the items listed below, prior to their delivery.
1. Pipe
2, Fittings
3. Joints and Restrainers
4, Plug Valve
5, Check Valve
6, Quick Disconnect
C. Operation and Maintenance Data - The Contractor shall furnish the Engineer three (3) sets
of each of the following for each mechanical unit installed.
1. Instructions
2, Maintenance Manual
3, Parts Lists
4, Wiring Diagrams
5. Pump Performance Curves
D. Operating Instructions and Service
1. Three sets of operating and maintenance manuals shall be furnished. The manuals
shall be prepared specifically for this installation and shall include all required cuts,
drawings, equipment list, descriptions, etc. that are required to instruct operating and
02539 — Submersible Pump Station (Rev.)
02539-2
maintenance personnel unfamiliar with such equipment. The number and special
requirements shall be as specified by the County,
2. A factory representative of all major component manufacturers, who has complete
knowledge of proper operation and maintenance, shall be provided for one (1) day to
instruct representatives of the Owner and the Engineer on proper operation and
maintenance. If there are difficulties in operation of the equipment due to the
manufacturer's design or Contractor's installation, additional service shall be
provided by the Contractor at no cost to the Owner.
1.05 TOOLS AND SPARE PARTS
A. One (1) set of all special tools required for normal operation and maintenance shall be
provided. All such tools shall be furnished in a suitable steel tool chest complete with lock
and duplicate keys.
The manufacturer shall furnish a complete set of recommended spare parts necessary for the
first five (5) years operation of the pumping system, which shall include at least the
following:
1. 1 - set of upper bearings for each pump supplied
2. 1 - set of lower bearings for each pump supplied
3, 1 - set of upper and lower shaft seals for each pump supplied
4. 2 — replacement fuses for each installed fuse
5. 1 — relay and phase monitor for each type supplied with the pump control panel
6. 1 — spare impeller
B. Spare parts shall be properly bound and labeled for easy identification without opening the
packaging and suitably protected for long term storage.
1.06 WARRANTY
A. All equipment supplied under this section shall be warranted for a period of one (1) year by
the Contractor and the equipment manufacturers. Warranty period shall commence on final
date when project is accepted by the. Owner.
B. The equipment shall be warranted to be free from defects in workmanship, design and
materials. If any part of the equipment should fail during the warranty period, it shall be
replaced and the machine(s) and/or the unit(s) restored to service at no expense to the Owner.
C. The manufacturer's warranty period shall run concurrently with the Contractor's warranty
period. No exception to this provision shall be allowed.
PART 2 - EQUIPMENT AND MATERIALS
2.01 PUMP FOUNDATION PLATES
A. Each pump shall be furnished with a foundation base plate which shall be rigidly and
accurately anchored into position. The pump manufacturer shall furnish all necessary
foundation bolts, plates, nuts, and washers for installation by the Contractor. Each foundation
plate shall be '/2" thick, Type 316 stainless steel. Foundation bolts, nuts, washers, and spare
parts shall be Type 316 stainless steel.
2.02 SEWAGE PUMPS
02539 — Submersible Pump Station (Rev.)
02539-3
r�
■ A. The pumps shall be totally submersible, non -clog, centrifugal pumps with close -coupled
motors designed to pump sewage. The pumps shall be capable of passing a minimum 3- inch
diameter spherical solid. The motor shall be an integral part of the pumping unit. The design
shall be such that the pumping units shall be automatically connected to the discharge piping
when lowered into place on the discharge connection. The pumps shall be easily removable
for inspection or service, requiring no bolts, nuts or other fastenings to be removed for this
purpose, or need for personnel to enter the wet well.
B. At the rated m eacn um 111X uim onaiivav� �+.� • •" ••-_ _ ____-
FLOW - mm Total —H —ea—d (ft.)
0 36
80 32
190 26
The pumps shall be as manufactured by "ABS", model AFP 1040, with 177 mm impeller, or
approved equal.
Co Pump Construction - The pump shall be of the centrifugal type with a solids handling, single
vane, dynamically balanced, shearing type impeller. The common pump and motor shaft shall
be series 400 stainless steel. The shaft and rotor assembly shall be supported by two ball
act ball
bearings; the lower ball bearing shall be a heavy duty, double row, angular
bearings. Each pump shall be provided with a tandem double mechanical seal running in an
oil reservoir, composed of two separate lapped face seals, each consisting of one stationary
and one rotating tungsten -carbide or silicon carbide ring with each pair held in contact by a
separate spring, so that the outside pressure assists spring compression in preventing the seal
faces from opening. The compression spring shall be protected against exposure to the
pumped liquid. The pumped liquid shall be sealed from the oil reservoir by one face seal and
sealed from the oil reservoir from the motor chamber by the other. The seals shall require
neither maintenance nor adjustment, and shall be easily replaced. Conventional double
mechanical seals with a single spring between the rotating faces, requiring constant
differential pressure to effect sealing and subject to opening and penetration by pumping
forces, shall not be considered equal to tandem seal specified and required.The impeller shall
be constructed of nodular iron SP. All other parts shall be of close grain gray iron
construction, with all parts coming into contact with sewage protected by a coat of rubber -
asphalt paint. All external bolts and nuts shall be of stainless steel.
D. Pump Identification - Stainless steel nameplates giving the name of the manufacturer, head,
speed, and all other pertinent data shall be attached to each pump and motor.
2.03 PUMP MOTORS AND CABLES
A. Pump motors shall be of the submersible type, housed in an air-filled, watertight casing.
Motors shall be a NEMA Design B. Insulation shall be moisture -resistant NEMA Class F
with a maximum temperature rise of 90 degrees Celsius above ambient temperature (40
degrees Celsius). The motor shall be rated for a maximum of 3.0 Hp at 1780 RPM, connected
for operation at 230 volt, 60 hertz, 3-phase service. The motor shall be non -overloading along
the entire operation of the published pump curve. The full load current shall not exceed 10.0
amps at 230 volts, 3 phase, electric service. Pump motors shall have cooling characteristics
suitable to permit continuous operation, in a totally, partially or nonsubmerged condition.
Each motor shall incorporate an ambient temperature compensated overheat sensing device
and a moisture sending device wired in series. The protective devices shall be wired into the
02539 — Submersible Pump Station (Rev.)
02539-4
pump controls in such a way that if either device operates, the pump will shut down. The
devices shall be self -resetting. The cable shall be fixed to the pump using a watertight
trumpet assembly. The pump shall be capable of running continuously in a totally dry
condition under full load, without damage, for extended periods. Before final acceptance, a
field running test demonstrating this ability, with four (4) hours of continuous operation
(water supplied by the contractor) under the above conditions, shall be performed for all
pumps being supplied, if required by the IRCDUS. Pump motor cables shall be suitable for
submersible pump applications and shall be properly sealed.
B. Power cables shall be sized according to NEC standards and shall be of sufficient length to
reach the control panel without splicing. The cable shall be oil resistant and capable of
continuous submerged operation in raw sewage. The pump cable entry shall provide strain
relief for the cable. The cable and entry into the pump shall be "Factory Mutual" approved
for use in NEC Class 1, Division 1, Groups C and D hazardous locations.
C. Lifting cables shall be provided for each pump. Each pump shall be fitted with a braided, 316
stainless steel lifting cable of adequate strength, and shall be five (5) feet longer than wet well
depth to control panel to permit raising the pump for inspection and removal.
2.04 PUMP GUIDE RAILS & BRACKETS
A. A guide rail base for sliding pump mount shall be an integral part of the pumping unit, and
the pump casing shall have a machined connecting flange to connect with the cast iron guide
rail base. The base shall be bolted to a stainless steel base plate affixed to the wet well bottom
with stainless steel anchor bolts and so designed as to receive the pump connection without
the need of any bolts or nuts. Sealing of the pumping units to the guide rail base shall be
accomplished by a simple linear downward motion of the pump with the entire weight of the
pumping unit guided by stainless steel guide tubes or T -bars which will press it tightly
against the discharge connection or a single stainless steel guide with a locking guide rail
base as approved by the Engineer. No portion of the pump shall bear directly on the floor of
the sump and no rotary motion of the pump shall be required for sealing. The guide rail base
shall have a 4 -inch discharge elbow which shall be totally supported by the pump mount.
2.05 PUMP CONTROL SYSTEM
A. General
1. A pump controller shall be provided for the wastewater pumping station. The
controller shall respond to the liquid level switches to automatically start and stop
pumps in response to liquid level in the wet well.
2. The pump controller shall be the standard system of the manufacturer as modified for
this application. The wet well levels to be used in operation are as shown on the
Drawings.
3. All components within the pump control system shall be designed and sized to handle
their maximum potential full load amperage and ground fault capacities.
4. All electrical installations shall be conducted in accordance with the National Electric
Code and all applicable local codes.
51 Prior to ordering electrical components the Contractor shall contact Florida, Power
and Light to confirm the electric service and ground fault currents. This information
02539 - Submersible Pump Station (Rev.)
02539=5
shall be transmitted to the panel manufacturer. Any discrepancy between the
information shown on the plans and that provided by the electric company shall be
brought to the attention of the Engineer.
B, Components
The control panel shall include power distribution components for a duplex motor control
center including but not limited to the following components:
1. Main Circuit Breaker
2, Generator Circuit Breaker w/Mechanical Interlock
3, Surge Arrestor
4, Motor Circuit Breaker
5, Motor Starters
6, 120 V. Duplex Receptacle with 15 Amp. Breaker
7. Control Power Circuit Breaker
g. Generator Receptacle
The control panel shall include control components including but not limited to the
following:
1, Control Relays
2, Automatic Alternator
3, Hand -Off -Auto Switches
4, Run Lights
5, Elapsed Time Meters
6, Exterior Alarm Horn
T Exterior Flashing Alarm Lamp
g. Phase monitor and shutoffs for each pump
9, Seal failure detector with indicator lamp and reset for each pump
10. RTU data acquisition and control system
C. . Component Requirements
1. All motor branch circuit breakers, motor starters and control relays shall be of highest
industrial quality, securely fastened to the removable back panels with screws and
lock washers. Back panels shall be tapped to accept all mounting screws. Self -
tapping screws shall not be used to mount any component.
2, A thermal -magnetic circuit breaker, appropriately sized for the service and ground
fault interrupting capacity, as manufactured by Square D Company, or approved
equal, shall be furnished for the main breaker. All circuit breakers shall be sealed by
the manufacturer after calibration to prevent tampering. A motor circuit breaker
shall be provided for each motor starter. Each motor circuit breaker shall be
adequately sized to meet the pump motor and station operating conditions.
3. A mechanical disconnect mechanism shall be installed on each circuit breaker to
provide a means of disconnecting power to the pump motors. Operator handles for
the disconnect mechanisms shall be located on the exterior of the control
compartment door.
4, An open frame, across -the -line, NEMA rated, magnetic motor starter, Bulletin 709
as manufactured by Allen-Bradley Company, or approved equal, shall be furnished
02539 — Submersible Pump Station (Rev.)
025394
D.
E.
for each pump motor. All motor starters shall be equipped to provide under -voltage
release and overload protection on all three phases. Motor starter contacts shall be
easily replaceable without removing the motor starter from its mounted position.
Overload reset push -buttons shall be located on the exterior of the control
compartment door.
5. Time delay relays shall be of the electronic type.
6. An emergency power receptacle shall be installed in the side of the control panel and
connected to the line side of the generator breaker. The receptacle shall be 100A,
4P, 3W, Crouse -Hinds No. AR1042-S22 with AR610 panel adapter.
7. A ground fault interrupting duplex utility receptacle providing 120 volts, 60 hertz,
single phase current shall be mounted on the dead front of the enclosure.
8. Pump mode selector switches shall be Hand -Off -Auto type to permit over -ride of
automatic level control and manual actuation of shutdown of either pump motor.
Operation of pumps in Hand mode shall bypass all safety shutdown circuits except
pump motor overload shutdown and duplex lockout. Switches shall be oil -tight, as
manufactured by Allen-Bradley, or approved equal, providing three (3) switch
positions, each of which shall be clearly labeled according to function. Separate
indicator lamps, which shall operate at 115 volts input, shall be provided, mounted
above the H.O.A. selector switches. Lamps shall be easily replaceable from the front
of control compartment door without removing switch modules from their mounted
positions.
9. Indicator lamps shall be mounted in oil -tight modules, as manufactured by Allen-
Bradley, or approved equal. Lamp modules shall be equipped to operate at 115V.
Lamps shall be easily replaceable from the front of the control compartment door
without removing lamp module from its mounted position.
10. A six (6) digit, non reset elapsed time meter shall be connected to each motor starter
to indicate the total running time of each pump in "hours" and "tenth of hours". The
elapsed time meters shall be Bulletin 705, HK Series as manufactured by Eagle
Signal, or approved equal.
Enclosure
The electrical control equipment shall be mounted within a NEMA Type 4X, stainless steel,
dead front enclosure. The enclosure shall be equipped with an outer door, a dead front panel
on which control components shall be mounted, and a removable back panel on which the
power components shall be mounted. Back panel shall be secured to enclosure -with collar
studs.. All conduits entering the enclosure from the wet well shall be sealed at the panel.
The seal shall prevent sewage gases from entering the enclosure. Three Crouse -Hinds Type
"CGB" cable connectors shall be provided to terminate the motor cables and float switch
cables in the control panel bottom. The connectors shall be suitable for a 2" conduit with a
neoprene bushing suitable for the motor cables supplied.
All operating, controls and instruments shall be securely mounted on the control compartment
door. All controls and instruments shall be clearly labeled to indicate function.
Remote Telemetry Unit (RTU)
02539-7
02539 — Submersible Pump Station (Rev.)
A radio communication, Remote Telemetry Unit (RTU), complete with antenna and all data
acquisition and control components, shall be supplied with the pump control system. The
RTU shall be capable of acquiring analog and discrete data for transmission to the Central
Telemetry Unit (CTU); The RTU shall also be capable of receiving instructions from the
CTU for the operation of the pumps.
2.10 ACCESS COVERS
A, The wet well shall be furnished with a single leaf, and valve vault with a double leaf, hinged,
aluminum access cover, with recessed key wrench lock and stainless steel accessories. The
wet well cover frame shall be placed and securely mounted above the pumps with stainless
steel guide bar brackets accurately aligned. The frame shall be equipped with safety handles
to maintain the door in an open position. The covers shall be fabricated from checkered plate
aluminum sheet and shall be designed to withstand 300 psf loading. The valve pit access
cover shall be identical in construction to the wet well access cover, except that it shall be a
double leaf cover of larger opening size. Access covers shall be Bilco JD, or approved equal.
Minimum size of the wet well opening shall be 4 -foot by 346ot, adequate to accommodate
the two (2) pumps as shown on the Drawings. The stainless steel upper guide rail holder and
a stainless steel level sensor cable holder shall be mounted to the frame of the wet well access
cover.
2.10 MISCELLANEOUS CONCRETE
A. All miscellaneous concrete pours shall have a design mix with a 28 -day compressive strength
of 3,500 pounds per square inch, and shall comply in all respects with the requirements of
Division 03 of these specifications.
B, Concrete used for tremie pours shall have the same design mix as miscellaneous concrete,
except that the following admixtures shall be included in the mix:
1. High -Range Water Reducing Admixture shall be incorporated into the design.mix to
provide enhanced: water reduction; high slump retention; high flowability; and self
compacting properties. The admixture shall be based on polycarboxylate chemistry
and shall be as manufactured by "Master Builders Technologies", Glenium 3030 NS,
or approved equal.
2. Anti -Washout Admixture shall eThe admixture shallbe based o
e mthe
n liqu1d celluloix to se
washout and segregation resistant
chemistry and shall be as manufactured by `BASF", Rheomac UW450, or approved
equal.
C, Admixtures shall be incotrete supplierted w with any othence with radmixtures
recommendations. Co shall confirm ompatability
to be used in the design mix.
2.11 REINFORCING STEEL
A. All reinforcing steel shall be grade 60, and shall comply in all respects with the requirements
of Division 03 of these specifications.
2.12 PRECAST CONCRETE WET WELL SECTIONS
02539 — Submersible pump Station (Rev.)
02539-8
2.13
2.14
2.15
A. Precast manhole sections used for the wet well shall conform to the wet well details shown on
the Plans and shall -consist of a precast base cast poured monolithically with a minimum three
foot length of barrel section. Additional barrel sections shall also be a minimum three feet
in length. All concrete used in the construction of precast sections shall utilize Type II
cement and have a 28 day compressive strength of 4,000 pounds per square inch. The precast
sections shall conform with all applicable requirements of Division 03 of these specifications.
PRECAST CONCRETE VAULTS
B. Precast concrete vaults shall conform to the vault details shown on the Drawings and
shall consist of a precast monolithic base section and top slab. All concrete used in
the construction of precast sections shall utilize Type II cement and have a 28 day
compressive strength of 4,000 pounds per square inch. The precast sections shall
conform with all applicable requirements of Division 03 of these specifications..
MISCELLANEOUS HARDWARE
A. All hardware, bolts, anchors, accessories in the wet well and valve vault shall be stainless
steel.
B. Safety Netting — The wet well opening shall be provided with a rail mounted safety net
system designed to be installed to the access hatch. The safety net shall easily slide on the
guide rails to facilitate entry and then repositioned to prevent fall through. The net system
shall be manufactured to fit the 300# access hatch specified in paragraph 2.10 above. The net
system shall be manufactured of durable synthetic netting with all mounting and rail
components constructed of stainless steel. The net system shall be as manufactured by "U.S.
Netting", Hatch net 121 System, or approved equal.
PIPE AND FITTINGS
1. Ductile iron pipe shall conform to AWWA C151 (ANSI A21.51) and shall be
minimum pressure class 350 unless specified otherwise or shown otherwise on the
Drawings. Pipe shall be furnished in standard 18 or 20 foot lengths unless shown
otherwise on the Drawings. External surfaces of DI pipe shall be coated with a
minimum 10 mil thickness of "Kop-Coat" Bitumastic 300M or Protech EP214 Epoxy
Mastic or approved equivalent. Internal surfaces shall be coated to a minimum
thickness of 40 mil with McWane's Protecto 401 ceramic lining or approved equal.
2. Polyethylene pipe shall be new, unused, sections of polyethylene pipe having a
nominal density of 0.955. The polyethylene resin used to manufacture the pipe shall.
have a "Plastic Pipe Institute" material designation of PE 3408, with an ASTM
D3350 cell classification of 34544C. The pipe shall be black in color, containing
approximately 2 percent U.V. stabilizer. Pipe shall be extruded to the wall thickness
described in AWWA C906 for DRI 1. Pipe outside dimensions shall meet that of
ductile iron pipe size (D.I.P.S.). Pipe shall be provided in nominal 40 foot long
sections or pre-cut for the project.
During the extrusion process, the HDPE pipe shall be continuously marked with
durable printing including the following information:
02539-9
02539 — Submersible Pump Station (Rev.)
a. Nominal Size (O.D. Base)
_ b, . Dimension Ratio (for wall thickness)
C, Manufacturer Name and Product Series
d. Cell Class
e. ASTM Basis
f. Pipe Test Category
g, Plant Identification
h, Production Date
i, Operator Number (Shift Letter optional)
j, Resin Supplier Code
B, Fittings.
1. All underground fittings shall be ductile iron with mechanical or manufacturer's
mechanically restrained joints. Fittings shall be compact ductile iron conforming to
AWWA C 153. The fittings shall lie lined and coated in accordance with the ductile
iron pipe specification. Fittings shall have a minimum pressure rating is 350 psi.
All fittings and the appropriate number of downstream and upstream joints must be
restrained.
2, Unless otherwise indicated on the Drawings, all above ground fittings or fittings in
boxes shall be ductile iron flanged fittings, conforming to AWWA-C110 Standards.
The fittings shall be lined and coated in accordance with the ductile iron pipe
specification.
3. Where indicated on the Drawings, HDPE fittings shall be in accordance with ASTM
D 3261 and shall be manufactured by injection molding, a combination of extrusion
and machining, or fabricated from HDPE pipe conforming to this specification. The
fittings shall be designed for a working pressure of 160 psi. The fittings shall be
manufactured from the same resin type and cell classification as the pipe itself. The
fittings shall be homogeneous throughout and free from cracks, holes, foreign
inclusions, voids, or other injurious defects. All fittings shall be constructed to have
a minimum D.R. 11 sidewall thickness.
C. Joints:
1, Standard joints for ductile iron pipe shall be bell and spigot, rubber gasket,
compression, push -on type as specified in AWWA C111 (ANSI A21.11).
2, Flanged joints shall utilize NST threaded flanges and pipe barrels conforming to
AWWA specification C115. Flanged joints through 12 -inches shall be rated for a
working pressure of 350 psi. Bolt pattern and hole sizes shall comply with ANSI
B16.1, Class 125. Each flange joint shall have a 1/8 -inch thick, full-faced, rubber
gasket. Size, length and number of bolts shall conform to AWWA C115. -Bolts and
nuts shall be stainless steel, series 304 or 316.
3, Mechanical joints shall be used on all underground fittings for changes in horizontal
or vertical alignment on all runs of pipe. All mechanical joints shall be restrained in
accordance with AWWA C111.
4, Restrained Joints - Fittings used for changes in alignment of pipe shall be
mechanically restrained. As indicated on the drawings, pipe lengths located
i upstream and downstream of restrained fittings shall also be restrained. Method of
joint restraint shall be as follows:
02539 —Submersible Pump Station (Rev.)
02539-10
2.16
2.17
2.18
a. Push -on ductile iron pipe joints shall be restrained with "EBBA IRON" series
4500 restrainers, pipe manufacturer's restrained joints, such as U.S. Pipe
"TR -FLEX GRIPPER RING", American Pipe "LOK-RING" or "LOK-
FAST" joints, or approved equal.
b. Mechanical joint ductile iron pipe and fittings shall be restrained with
"EBBA IRON", Megalug Series 1100 restrainers, or approved equal.
C, Set screw type Adapter or Retainer glands shall not approved.
5. Sections of polyethylene pipe and fittings shall be joined in the field by the butt
fusion process into one continuous length at the job site. The joining method shall be
the heat fusion method and shall be performed in strict accordance with the pipe
manufacturer's recommendations. The heat fusion equipment used in the joining
procedures shall be capable of meeting all conditions recommended by the pipe
manufacturer.
D. Gaskets - All gaskets shall be manufactured of an elastomeric material. The gasket shall
provide a positive, tight seal under all combinations of joint and gasket tolerances.
Installation and lubrication of gaskets shall be as directed by the manufacturer.
VALVES
A. Plug Valves
Plug valves shall be of the non -lubricated, eccentric type with neoprene faces and have
flanged joint ends as shown on the Plans and shall be for hand operated service. Ports on
valves to 20 -inches shall beat least 80% of full area. Valve bodies shall be semi -steel. Seats
shall have a welded -in overlay of not less than 90% pure nickel on all surfaces contacting the
plug face. Valves shall have stainless steel permanently lubricated upper and lower plug stem
bushings. Valves shall be designed so they can be repacked without removing the bonnet
from the valve body or the actuator, and the packing shall be adjustable. Actuators shall
clearly indicate the valve position and an adjustable stop shall be provided to set closing
torque. Plug valves shall be DeZurik Series 100 or approved equal, suitable for a working
pressure of 150 psi. Plug valves shall be provided with concrete supports to prevent the
transmittal of shear forces to the P.V.C. pipe.
B. Check Valves
Check valves shall be of the horizontal, single -disk, non -slam, swing type, having a 150 psi
pressure rating. The valves shall be equipped with an externally mounted lever with
adjustable weight for control of closing speed. Access Covers and Guide of valve shall be
designed for non -buried service. Valves shall have semi -steel bodies with 125 lb. flanged
ends. The discs shall be semi -steel with elastomeric seat rings designed for use with raw
sewage.
WATER SUPPLY
A. A metered water supply shall be supplied to the pump station by the Contractor as indicated
on the Drawings. Contractor shall provide and install the service, backflow preventer, and
hose bib as shown on the Drawings.
ELECTRICAL SUPPLY
02539-11
02539 — Submersible Pump Station (Rev.)
A. The Contractor shall coordinate with the provider of electric power and install an unspliced,
underground power supply from the pump station to the power pole or transformer
designated by Florida, Power and Light. The Contractor shall install properly sized
conductors in conduit to provide a 230 volt, 3 phase, four (4) wire electric service with no
more than a 5% voltage drop when two pump are operating. Pull or Terminal boxes (if
needed) shall be polymer concrete and fiberglass, with the words "ELECTRIC" embossed on
the top. Boxes shall be "CDR Systems Corp.", model PA12-1730-26, or approved equal.
All conductors shall be installed in conduit (schedule 40 underground) with long radius
sweeps at all bends. All electrical components and accessories shall be provided and
installed in accordance with the NEC and local ordinances. All costs for coordinating and
installation of the electric service shall be the responsibility of the Contractor.
2.19 COATINGS
A. All coatings shall be industrial grade, designed to achieve maximum protection of all
structures and mechanical equipment. All coating components and accessories shall be
provided and installed in accordance with the Drawings and the requirements of Division 09
of these specifications
PART 3 - EXECUTION OF WORK
3.01 SITE PREPARATION
A. Clearing
The Contractor shall perform all clearing necessary, where applicable, for the proper
installation of the Pumping Station and its appurtenances as shown on the Plans.
B. Excavation
Excavation shall be to the depth shown on the Plans. The materials of excavation shall
include all materials encountered and no additional compensation shall be allowed for
difficulty in their removal. The Contractor shall be responsible for the disposal of the excess
material as directed by the Engineer.
1. Sheeting and Bracing - The Contractor shall be responsible for properly supporting
the sides of all trenches and excavations with timbers or other supports wherever
necessary or required to properly safeguard the trenches, adjacent properties and
structures. The cost of all necessary timber, sheeting and bracing whatsoever (left in
place or removed), shall be included in the prices bid.
Timber sheeting and bracing shall be left in place if so ordered by the Engineer
and/or where shown on the Plans to avoid undermining or otherwise endangering the
work or adjacent structures.
All sheeting left in place shall be cut off or driven at least 18 -inches below finished
grade, unless otherwise ordered by the Engineer.
2. Dewatering - The Contractor shall furnish sufficient pumping or other dewatering
equipment and shall provide satisfactory drainage during the construction to properly
complete the work. Except for the wet well which is to be installed by the caisson
method, all work shall be installed in the dry. Unless otherwise permitted by the
Engineer, the water table shall be lowered by the use of a well point system. The
02539 — Submersible Pump Station (Rev.)
02539-12
3.02
3.03
Engineer shall make the final decision as to the acceptability of the well point system
or any part thereof. _
The Contractor shall provide for the proper disposal of water removed from the
excavation in a manner that will not cause injury to public health, private or public
property, any portion of the work completed or in progress, the surface of the streets,
or cause any impediments to the reasonable use of the site by other Contractors. The
Contractor shall be responsible for complying with all the local regulations,
St. Johns River Water Management District and the Department of Environmental
Regulation regarding pollution of the surface waters. The Contractor shall take
special precautions to eliminate any odor problems resulting from the discharge of
sulfide water, such as submerged discharge outlets and overflow basins.
C. Utility Relocation
The existing utilities and irrigation system noted on the Plans to be relocated shall removed
and relocated at the Contractor's expense. The contractor shall coordinate with the affected
utility Owner to have the utilities adjusted as needed. The existing irrigation system shall be
be removed (including existing wells) and a new system of equal capacity and components
shall be installed in
INSTALLATION
A. The station including wet well, valves and meter pits, valves, pumps, motor controls, electric
system, and all accessories shall be installed at the locations as shown on the Drawings in
accordance with the applicable Sections of these specifications.
B. Backfilling - No backfill shall be placed until setting of the wet well and valve pits have
been inspected and approved by the Engineer. Backfill shall be brought to within 3 inches of
the surrounding finished grade surface. Backfill material shall be free of roots, logs, limbs,
large rocks or any material or debris determined to be unsuitable by the Engineer. The
backfill shall be placed in 12 -inch layers and compacted to a minimum density of 95% as
determined by AASHTO T-180.
C. Restoration - All ground surfaces damaged or disturbed by pump station installation either
within or adjacent to the limits of lump sum pay item shall be restored to the condition which
existed prior to pump station construction.
D. Coating Preparation and Application - The surfaces requiring coating shall be prepared and
surface coated by the Contractor in accordance with Division 09. All other components shall
remain as prepared and coated by their Manufacturer. The Contractor shall be responsible for
touch-up or restoration of any finish coatings provided by the Manufacturer which may be
damaged or scratched during shipping or installation.
TESTING
A. Field Quality Control
All systems and equipment shall be tested, under the observation of the Engineer and a
representative of the Owner, to assure operation in accordance with the plans and
specifications. All water, electricity, or other materials or services required for these tests
shall be furnished by the Contractor at no cost to the Owner. Contractor shall furnish all labor,
piping, equipment and materials necessary for conducting the tests.
02539-13
02539 — Submersible Pump Station (Rev.)
L
B. Manufacturer's Certificatiorr
Contractor shall coordinate with the Manufacturer's of major control components and pump
equipment to provide all pre start-up work and inspections as necessary to prepare the pump
station for final start-up. At start-up, the Manufacturer's representatives shall be present for a
minimum of one 8 -hour day to provide the following services:
1. Check final installation of equipment
2, Provide start-up of equipment
3. Run specified tests
4. Train personnel in operation and maintenance of equipment
5. Certify as to acceptability of final installed and tested product
C. The pump test shall demonstrate their ability to:
1, Operate without vibration or overheating at the specified conditions.
2. Perform as specified.
3. Load test, check amperage, phase to voltage test and insulation test.
4. Flow test based on timed draw down of the wet well and force main pressure reading.
D. All defects revealed by or noted during the tests shall be corrected or equipment replaced
promptly at no additional expense to the Owner.
E. Should the Contractor be unable to demonstrate to the satisfaction of the Engineer that the
units will satisfactorily perform the service required, the units may be rejected. Contractor
shall remove and replace the equipment at his own expense.
F. Prior to final acceptance by the Owner, all required: as -built record drawings; pump curves;
operation and maintenance manuals; special tools necessary to disassemble, service, repair
and adjust the equipment and all spare parts shall be delivered to the Owner.
END OF SECTION
02539-14
02539 — Submersible Pump Station (Rev.)
SECTION 02714
STABILIZED SUBGRADE
PART 1 - GENERAL
1.01 SCOPE
Under this item, the Contractor shall furnish all equipment, labor, materials, and transportation
necessary to construct a stabilized subgrade course upon the compacted in-place material for the
pump station driveway.
1.02 REFERENCES
Standards applicable in this Specification shall be:
A. Florida Department of Transportation - Standard Specifications. for Road and Bridge
Construction (latest edition)
B. American Association of State Highway and Transportation Officials (AASHTO)
1. AASHTO T-180 -Test for Moisture -Density Relations of Soils using a 10 lb. Rammer
and an 18 -inch Drop.
C. ASTM International (ASTM)
1. ASTM D 1557 - Test Method for Laboratory Compaction Characteristics of Soil
Using Modified Effort
2. ASTM D 2167 - Density and unit weight of soil in place by the rubber balloon method
3. ASTM D 2922 (2001) - Standard Test Methods for Density of Soil and Soil -
Aggregate in Place by Nuclear Methods (Shallow Depth)
1.03 DESCRIPTION
The subgrade will be constructed such that after being compacted it will conform to the lines and
grades as shown on the Drawings. The subgrade shall be Type -B (LBR), stabilized and constructed
in accordance with the 2002 edition of the Florida D.O.T. Specifications, Section 160.
PART 2 - MATERIALS
2.01 The subgrade shall have a minimum Florida Bearing Value of 50 as determined by the Florida Soil
Bearing Test. In an area where the bearing value is less than 50, stabilizing material approved by the
Engineer shall be furnished by the Contractor, spread and mixed in accordance with Section 160-5.3
"Mixing" of the 2006 Edition of the Florida D.O.T. Specifications,
PART 3 - EXECUTION OF WORK
3.01 The subgrade shall be shaped, graded, and rolled to conform to the lines and grades as shown on the
Drawings. Fine grading of the subgrade to its final profile shall be accomplished after the existing
ground has been excavated as close as possible to the design elevations.
02714 — Stabilized Subgrade
02714,1
SECTION 02714
STABILIZED SUBGRADE
PART 1 - GENERAL
1.01 SCOPE
Under this item, the Contractor shall furnish all equipment, labor, materials, and transportation
necessary to construct a stabilized subgrade course upon the compacted in-place material for the
pump station driveway.
1.02 REFERENCES
Standards applicable in this Specification shall be:
A. Florida Department of Transportation - Standard Specifications for Road and Bridge
Construction (latest edition)
B. American Association of State Highway and Transportation Officials (AASHTO)
1. AASHTO T-180 -Test for Moisture -Density Relations of Soils using a 10 lb. Rammer
and an 18 -inch Drop.
C. ASTM International (ASTM)
1. ASTM D 1557 - Test Method for Laboratory Compaction Characteristics of Soil
Using Modified Effort
2, ASTM D 2167 - Density and unit weight of soil in place by the rubber balloon method
3. ASTM D 2922 (2001) - Standard Test Methods for Density of Soil and Soil -
Aggregate in Place by Nuclear Methods (Shallow Depth)
1.03 DESCRIPTION
The subgrade will be constructed such that after being compacted it will conform to the lines and
grades as shown on the Drawings. The subgrade shall be Type -B (LBR), stabilized and constructed
in accordance with the 2002 edition of the Florida D.O.T. Specifications, Section 160.
PART 2 - MATERIALS
2.01 The subgrade shall have a minimum Florida Bearing Value of 50 as determined by the Florida Soil
Bearing Test. In an area where the bearing value is less than 50, stabilizing material approved by the
Engineer shall be furnished by the Contractor, spread and mixed in accordance with Section 160-5.3
"Mixing" of the 2006 Edition of the Florida D.O.T. Specifications.
PART 3 - EXECUTION OF WORK
3.01 The subgrade shall be shaped, graded, and rolled to conform to the lines and grades as shown on the
Drawings. Fine grading of the subgrade to its final profile shall be accomplished after the existing
ground has been excavated as close as possible to the design elevations.
02714 - Stabilized Subgrade
02714-1
3.02 Record Drawing elevations shall be confirmed to meet design drawing grades prior to placement of
base material.
3.03 The top of the subgrade in both cuts and fills shall be compacted to a minimum of 98 percent of the
maximum dry density to the depth specified on the Plans. The required density shall be maintained
until the surface course has been constructed. The subgrade shall be compacted with an approved
self-propelled steel drum or pneumatic tired roller weighing not less than 8 tons. All hollows and
depressions which develop under rolling shall be filled in with suitable material. The process of
grading and rolling shall be repeated until no depressions develop. After compaction, the top surface
of the fine grade shall be true to line and grade at all locations. If the fine grade becomes rutted or
displaced due to any cause whatsoever, the Contractor shall regrade it and recompact it. Ditches,
drains, and swales shall be maintained along the completed subgrade section after their construction.
3.04 In no case shall the Contractor proceed to construct further courses on the subgrade until the
subgrade has been tested for Florida Bearing Values, compaction, checked for line and grade, and
approval given by the Engineer.
3.05 Material and Compaction Testing
A. Florida Bearing Value tests on the subgrade shall be taken at a minimum of four (4) test
locations per 10,000 sf of area to be paved, where designated by the Engineer. Smaller
projects shall have a minimum of two (2) test locations.
B. The maximum density and optimum moisture shall be determined in accordance with the
Modified Proctor Test procedures of AASHTO T180 (Method D as modified by the
F.D.O.T.). The percentage compaction and in place density shall be determined according
to procedures of ASTM D2167 "Test for Density of Soil In Place by the Rubber Balloon
Method" or the nuclear method ASTM D2922,
C. Each material which is inherently different in composition from other subgrade material
and which is used over a widespread area of the project, will necessitate an additional
Modified Proctor Test,
END OF SECTION
02714- 2 02714 — Stabilized Subgrade
SECTION 02722
CEMENTED COQUINA SHELL BASE COURSE
PART 1 - GENERAL
1.01 SCOPE
Under this item, the Contractor shall furnish all equipment, labor, materials, and transportation
necessary to construct a Coquina shell base course upon the "off-site" completed stabilized subgrade
restoration.
1.02 REFERENCES
Standards applicable in this Specification shall be:
A. Florida Department of Transportation
Bridge Construction (2002)
1. Section 250 — Shell
- Standard Specifications for Road and
2. Section 915 - Cemented Coquina Shell Material
3, Section 300 — Prime and Tack Coats for Base Courses
4, Section 916 — Bituminous Materials
B. American Association of State Highway and Transportation Officials (AASHTO)
1. AASHTO T-180 - Test for Moisture -Density Relations of Soils using a 10 lb.
Rammer and an 18 -inch Drop.
C. ASTM International (ASTM)
1. ASTM D 1557 - Test Method for Laboratory Compaction Characteristics of Soil
Using Modified Effort
2, ASTM D 2167 - Density and unit weight of soil in place by the rubber balloon
method
3. ASTM D 2922 (2001) - Standard Test Methods for Density of Soil and Soil -
Aggregate in Place by Nuclear Methods (Shallow Depth)
PART 2 - MATERIALS
2.01 Coquina shell shall conform to the requirements of Florida D.O.T. Standard Specifications, 2002
Edition, Section 915, and shall be from a source acceptable to Florida D.O.T. The material shall have
a minimum LBR value of 100. Prior to placement, the material shall be crushed or broken to such a
size that no less than 97 percent by weight will pass a 3 1/2 inch sieve and no more than 20 percent
dry weight shall wash through a No. 200 sieve. No visible clay or organic matter will be permitted.
02722 - Cemented Coquina Shell Base
02722.1
PART 3 - EXECUTION OF WORK
3.01 PLACEMENT OF MATERIAL
The base course shall be constructed in accordance with the lines, grades, and typical section as
shown on the Drawings. Unless otherwise noted construction shall conform to the provisions of
Florida D.O.T. Standard Specifications for Road and Bridge Construction, Section 250, 2002
Edition.
After the subgrade is completed and approved, the Contractor shall furnish and spread the coquina
shell in a uniform distribution. Spread thickness shall be a minimum of 9 inches. Segregated areas of
fine or course rock will not be permitted. Such areas shall be removed and replaced with properly
graded rock.
After the spreading is completed, the entire surface shall be compacted, scarified and shaped so as to
produce the required grade and cross section after compaction.
3.02 COMPACTION
The required compaction of the coquina shell base course shall be a minimum of 98 percent of the
maximum dry density.
No less than 8-10 ton steel drum or pneumatic tired roller shall be used to compact the base course.
All depressions shall be filled and the process of rolling and filling shall continue until a thoroughly
compacted uniform surface is produced. During final compaction operations, if blading of any area
is necessary to obtain the true grade and cross section, the compaction operations for such areas shall
be completed prior to making the field density -compaction test on the finished base.
Should the subgrade material become mixed with the base course material at any time, the
Contractor shall remove the mixture, reshape and recompact the subgrade, replace the materials
removed with additional coquina shell and reshape and recompact the coquina shell base at no cost
to the Owner.
If cracks or checks appear in the base which would impair the structural integrity of the base in the
opinion of the Engineer, the Contractor shall remove the cracks or checks by rescarifying, reshaping,
refilling with coquina shell where necessary, and recompacting at no cost to the Owner.
The finished coquina shell base shall be checked for thickness at intervals of not more than 300 feet
on center. Finished thickness shall be as shown on the Drawings. Any areas which are less than 1/2
inch of the specified thickness shall be corrected by scarifying and adding rock. The scarifying shall
extend for 50 feet either side of the deficient area. Areas which are less than 1/2 inch deficient in
thickness shall be corrected if the Engineer determines that the area is extensive or may adversely
affect the quality of the finished work.
3.03 PRIME COAT
The prime coat shall be a rapid curing liquid cut back asphalt equal or equivalent to RC -70 or RC -
250 at the Contractor's option, and conforming to Sections 300 and 916-2 of the 2002 Edition of the
Florida D.O.T. Standard Specifications for Road and Bridge Construction.
02722 - 2 02722 — Cemented Coquina Shell Base
The surface of the base material shall be cleaned after final compaction and the moisture content of
the base shall not exceed 90 percent of the optimum moisture before the prime coat is applied. The
prime coat shall be applied uniformly with a pressure distributor. The entire length of the spray bar
shall be set at the height above the surface recommended by the Manufacturer for even distribution.
The prime coat shall be applied to the finished base course at the rate of 0.15 gallons per square yard
at a temperature between 100°F to 150°F. The prime coat shall be applied such that a period of no
longer than two (2) hours lapse prior to application of the asphaltic concrete wearing course, unless
the prime coat is covered with sand or screenings as outlined in Section 300-6.5 of the 2002 Edition
of the Florida D.O.T. Specifications.
3.04 TESTING
The maximum density and optimum moisture shall be determined in accordance with the Modified
Proctor Test procedures of ASTM -D1557 or AASHTO-T180 (Method D). At a minimum, one (1)
Modified Proctor Test shall be performed for each 10,000 square feet of base material on
representative samples from location(s) designated by the Engineer. The percentage compaction and
in-place density shall be determined according to procedures of ASTM -132167 "Test for Density of
Soil In -Place by the Rubber Balloon Method" or the nuclear method ASTM- D2922. In-place
density testing shall be performed at a minimum rate of four (4) Modified Proctor tests per 10,000
square feet of area to be paved unless quality control measures allow the Engineer to dictate fewer
tests. Smaller projects shall require a minimum of two (2) test locations.
END OF SECTION
02722 — Cemented Coquina Shell Base
02722 - 3
J
SECTION 02741
ASPHALT CONCRETE SURFACE COURSE
PART 1 - GENERAL
1.01 SCOPE
The work to be performed under this item shall include the selling, delivering and installing of
asphalt concrete surface courses on "off-site" restored bases, as further specified herein. Final
asphalt concrete surface course shall be completed within 30 days after placement of any
temporary asphalt surface course.
1.02 REFERENCES
Standards applicable in this Specification shall be:
A. Florida Department of Transportation - Standard Specifications for Road and Bridge
Construction (2006)
I. Section 300 -Prime and Tack Coats for Base Courses.
2. Section 320 -Hot Bituminous Mixtures -Plant, Methods and Equipment.
3. Section 330 - Hot Bituminous Mixtures - General Construction Requirements.
4. Section 334 — Superpave Asphalt Concrete.
1.03 SUBMITTALS
A. Manufacturer's Data - Prior to fabrication or installation of the final asphalt concrete
surface course, the Contractor shall furnish to the Engineer, for review and approval the
following:
1. Certification from the asphalt supplier that their plant meets or exceeds the
requirements of Section 320 above.
2. Asphalt mix design with supporting test data indicating compliance with all mix
design criteria.
PART 2 - MATERIALS
2.01 PRIME AND TACK COAT
A. Prime Coat shall be applied on all prepared bases. Prime coat material shall be Cut-back
Asphalt Grade RC -70 or RC -250, conforming to the Florida D.O.T. Standard
Specifications for Road and Bridge Construction, 2006 Edition, Section 916-3,
B. Prime Coat Cover Material shall consist of sand or screenings, conforming to the Florida
D.O.T. Standard Specifications for Road and Bridge Construction, 2006 Edition, Section
902.
02741 -1 02741 — Asphaltic Concrete Surface Course
C. Tack Coat shall be applied on all prepared bases and existing pavement immediately prior
to surfacing. Tack coat material shall be Asphalt Grade RA -500 or Emulsified Asphalt
Grades Rs -1 or RS -2, conforming to the Florida D.O.T. Standard Specifications for Road
and Bridge Construction, 2006 Edition, Section 916-2.
2.02 SUPERPAVE ASPHALT CONCRETE
A. Asphalt used for structural, leveling or patching courses shall be Type SP -12.5,
conforming to the Florida D.O.T. Standard Specifications for Road and Bridge
Construction, 2006 Edition, Section 334. Asphalt gradation shall be fine or course
depending on planned thickness.
B. Asphalt used for final surface course shall be Type SP -9.5, conforming to the Florida
D.O.T. Standard Specifications for Road and Bridge Construction, 2006 Edition, Section
334. Asphalt gradation shall be fine or course depending on planned thickness.
PART 3 - EXECUTION OF WORK
3.01 CLEANING SURFACES
Prior to the laying of any surface courses, the surface of the pavement or base to be covered shall
be cleaned of all loose and deleterious material by the use of power brooming or hand brooming
where necessary. All such material shall be collected and disposed of by the Contractor.
3.02 APPLICATION OF PRIME AND TACK COATS
A. Prime Coat material shall be heated to a suitable temperature and applied to the base in a
thin, uniform layer at a rate of between 0.1 and 0.15 gallons per square yard, as determined
by the Engineer. The prime coat shall be applied using a pressure distributor. Uniformly
cover the primed surface with a light application of cover material. Roll the covered prime
coat with a traffic roller to provide a dense mat.
B. Where primed base courses have become dirty or lost their bonding effect and on all
underlying asphalt courses, a tack coat shall be required. Tack coat material shall be heated
to a suitable temperature and applied in a thin, uniform layer at a rate of between 0.02 and
0.08 gallons per square yard. The tack coat shall be applied sufficiently in advance of the
surface course installation to permit drying but not so far in advance as to lose its
adhesiveness as a result of being covered with dust. The tack coat shall be kept free from
traffic until the surface course has been laid.
3.03 PREPARATION OF ASPHALT CONCRETE
The batching of aggregates, fillers and asphalt binder as well as the mixing and heating of the
mixture shall conform to the Florida D.O.T. Standard Specifications for Road and Bridge
Construction, 2006 Edition, Section 330. The "Master Temperature Range" for all mix designs
shall be the accepted mix design temperature t 30 degrees Fahrenheit ff). Any load or portion
of a load measured by the Engineer's Representative which is outside the "Master Temperature
Range" shall be rejected prior to installation.
3.04 TRANSPORTATION OF ASPHALT CONCRETE
02741 - Asphaltic Concrete Surface Course
027414
The surface course shall be transported in tight sealing vehicles previously cleaned of all foreign
material. The inside surface of the truck bodies shall be thinly coated with soapy water or an
acceptable asphalt release agent prior to receiving asphalt concrete.. Diesel, kerosene, gasoline
or any other hazardous or environmentally detrimental material shall not be used to lubricate the
truck bed. Cover each load during cool and cloudy weather when there is a possibility of rain.
3.05 PATCHING AND LEVELING COURSES
Where asphalt concrete is to be installed on an existing paved surface or old base which is
irregular, or where indicated on the Plans, the existing surface shall be brought to proper grade
and cross section by the application of patching or leveling courses.
3.06 PLACING ASPHALT CONCRETE
The placement of asphalt concrete for patching, leveling and subsequent courses shall conform
to the Florida D.O.T. Standard Specifications for Road and Bridge Construction, 2006 Edition,
Section 330-9,
3.07 COMPACTING ASPHALT CONCRETE
The Contractor shall provide a separate set of rollers, with their operators, for each paving or
leveling train crew working at the job. All coverage requirements for rolling shall be conducted
before the surface temperature of the asphalt concrete drops to the extent that effective
compaction can not be achieved or the rollers begin to damage the pavement course. Compaction
and joints for as freshly laid asphalt concrete courses shall be installed in compliance with the
Florida D.O.T. Standard Specifications for Road and Bridge Construction, 2006 Edition, Section
330-10 and 330-11.
3.08 FIELD QUALITY CONTROL
A. The longitudinal installation of all asphalt concrete courses shall be required to be checked
by a rolling straightedge. The straightedge shall have a minimum effective length of 15
feet. The finished surface of base or structural surface courses shall not vary more than 3/8
inch from the straightedge applied parallel to the centerline of the pavement. The finished
surface of final surface courses shall not vary more than 3/16 inch from the straightedge
applied parallel to the centerline of the pavement. Any pavement section exceeding the
above tolerances may be rejected by the Engineer.
B. The transverse cross slope shall be checked at up to 10 locations for each days work.
When the difference between the measured cross slope and the design cross slope varies
by more than t 0.2% for travel lanes or f 0.5% for shoulders, the paving operation shall be
stopped and corrected. Should the average measurement for the 10 locations be above the
specified tolerance, the measured pavement section may be rejected by the Engineer.
3.07 CORRECTING UNACCEPTABLE ASPHALT CONCRETE
The Contractor shall be required to correct rejected pavement sections by; removing and replacing;
overlaying; or other method in compliance with the Florida D.O.T. Standard Specifications for Road
and Bridge Construction, 2006 Edition, Section 330-12.4.
END OF SECTION
02741 a3 02741 - Asphaltic Concrete Surface Course
J