HomeMy WebLinkAbout2003-226 SECTION 00942 = Change Order Form #2 . doc
No . 2
DATE OF ISSUANCE : 8/25/03 EFFECTIVE DATE : 8/25/03
OWNER : Indian River County
CONTRACTOR WCG , Inc.
Contract : WCG Work Authoriztion #6
Project : Odor Scrubbing System Design Building Construction
OWNER's Contract No , ENGINEER's Contract No .
ENGINEER
You are directed to make the following changes in the Contract Documents :
Description :
Reason for Change Order:
Engineering of maintneance hood support racks and building extension design .
Attachments : ( List documents supporting change )
CHANGE IN CONTRACT PRICE : CHANGE IN CONTRACT TIMES
Description Amount Description Time
Original Contract Price $271 . 875 . 00 Original Contract Time : (days or dates )
Substantial Completion :
Final Completion :
Net Increase ( Decrease) from previous $4 . 110 . 00 Net change from previous Change
Change Orders No . 1 to 1 : Orders No . to (days )
Substantial Completion :
Final Completion :
Contract Price prior to this Change $275 . 985 . 00 Contract Time prior to this Change
Order: Order: (days or dates )
Substantial Completion :
Final Completion :
Net increase (decrease ) of this Change $8 ,423 . 75 Net increase (decrease ) this
Order : Change Order : (days or dates )
Substantial Completion :
Final Completion :
Contract Price with all approved $284 .408 . 75 Contract Time with all approved
Change Orders : Change Orders : (days or dates)
Substantial Completion :
Final Completion :
ACCEPTE • RECOMMENDED : APPRO
Terry Sout Kenn hR c
By : By:
ONTRACTOR (Signature) ENGINEE Signat re ) ER (Signature )
Date : 251ssl03 Date : �° Z � Date : 09 - 02 - 03
00942 - Change Order Form #2.doc
00942 - 1
FAUtilities\UTILITY - ENGINEERING\Projects - O&M Projects\Central WWTF WCG Improvements - UCP#2217\00942 - Change Order Form #2.doc Rev. 05/01