HomeMy WebLinkAbout2007-376 aoo 7 - 376 WORK AUTHORIZATION DIRECTIVE No. 2007-012 HRC — Pelican Elementary School Fire Hydrant DATE OF ISSUANCE: November 2007 EFFECTIVE DATE: November 2007 OWNER: Indian River County CONTRACTOR: Underaound Utilities, Inc. CONTRACT: WATER, SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT, BID NO. 2007026, AWARDED Feb. 6, 2007 PROJECT: Construct about 500 LF of 6" PVC Water Main and a Fire Hydrant at Pelican Island Elementary School COUNTY UTILITY PROJECT NO.: UCP #3008 CONTRACTOR' S PROJECT NO. : N/A COUNTY W.I.P. No. 472- 169000-07530 You are directed to proceed promptly with the following work: Description: Construct about 500 feet of 6" PVC Water Main and a Fire Hydrant with necessary appurtenances and restoration to the school property. Purpose of Work Authorization Directive: The construction of 6" PVC water main with fire hydrant will satisfy fire protection requirements for a proposed classroom building. Attachments: (List documents supporting work) Method of determining Contract Price: ❑x Unit Prices: Bid Items as established pursuant to Bid No. 2007026, and awarded by the Board of County Commissioners on February 6, 2007 to Underground Utilities Inc. ❑ Lump Sum ❑ Cost of the Work The Cost of Labor, Contingency and Contract Time is summarized below: Estimated Labor Cost = $ 13,859.56 Estimated Contract Time: 14 days Total Estimated Labor Costs= $ 13 ,859.56 ACCEPTED: RECO MENDED: APPRQVED: , A . r " By: JI�!? , - By: �GyL sy: r r1 ( � J Underground Utilities, Inc. Gordon E. SWks, P.E. ary, C Wheeler '.` Labor Contractor Environmental Engineer '' COUNTY; CHAIRMAN Date: /p- ,a - d7 Date: /0 - 30 - 01 Date: Attachment 4 C:\Documents and Settings\George French\Lucal SettingsUernporary Internet Fi1es\Content.IE5\02SCBMT3\A - Work Authorization No. 2005-012 Attachment 4AoO - - ' —I? ELI-C_AN _ ISLAND - - - LACE Proposed 6I � I - _ - " water Main r _ with Fire Hydrant Paz \ 6e, TELIC "N ISLAND ELEMENTARY Lum i14 k it rll i / \ / �. ° / iid . Y ` iz` 14io . \ - - BARBER — STREET ` GRAPHIC SCALE 150 0 75 150 300 600 Location Map 1 in IN FEET , nch 150 ft. Attachment 1 Please get our copy as soon as you receive one Page 1 of 1 Gordon Sparks From : Pat Walther [PatW@carterassoc.com] Sent: Wednesday, October 24 , 2007 10 : 21 AM To: Gordon Sparks Cc : susan .olson@indian-river. k12 .fl . us Subject: RE : Treasure Coast Elementary Easement Gordon, The easement got approved at last night' s School Board meeting. Judy Stang will have the documentation signed by the Sup' t. and Mrs. Johnson, so they should have it in a few days. Can you get started on the water line and hydrant? Thanks, Patrick S . Walther, P . E. Project Manager Carter Associates , Inc. 1708 21st Street Vero Beach, Florida 32960 Office: 772-562-4191 Fax: 772-562-7180 Mobile : 772-473-9445 From : Gordon Sparks [mailto : gsparks@ircgov.com] Sent: Monday, October 22, 2007 12 :45 PM To: Pat Walther Subject: RE : Treasure Coast Elementary Easement Please get our signed copy as soon as you receive one. It will have to be recorded in County Records. Gordon From : Pat Walther [ma i Ito : PatW@carterassoc.com] Sent: Monday, October 22, 2007 11 : 34 AM To: Gordon Sparks Subject: Treasure Coast Elementary Easement Gordon , The easement is on the Board agenda for approval at tomorrow's meeting (Board Meeting @ 6 p. m 10/23/07). Patrick S . Walther, P. E. Project Manager Carter Associates, Inc. 1708 21 st Street Vero Beach , Florida 32960 Office 772-562-4191 Fax: 772-562-7180 Mobile: 772-473-9445 Attachment 2 10/24/2007 Indian River County Department of Utilities COST ESTIMATE Project: IRC -Pelican Elementary Fire Hydrant Installation Cost Estimate for Work Authorization No. 2007-012 to Underground Utilities, Inc. UCP 43008, W IP 8402-169000.07530 24Ort-o7 Bid Item Estimrted Unit of Unit Total Labor Unit Total Labor materia unit m242 1 Item No Deaeri tion uamit Meexure Price A^ Price A• Price B•' Price B^^ Price price 63 Mobilization, Demnbilimtiou, Mo 1 1 0.04 48460 n.m 867, 13 Ole Install 6" PVC Water Main 500 LF 8.00 4,000.00 7.00 1,500.00 $3.68 1,84000 03a Insall Driveway Bares for 6" PVC WM 60 LF 25.00 1 ,500.00 57.00 3,42000 $3,68 220.80 07 Install 6" MJ Restraind Pittings 0.50 TON 4,000.00 2.000.00 1,665.00 832.50 $2,500.00 1 ,250.00 13a Install Dl wa Te w/ GV&B 6' X6" and Tap Main 1 .00 EA 4000 400.00 Lownfl 1 ,000.00 $ 1 ,050.95 1 ,05095 F/c Install 6' Gate Valve & Box 1 EA 400.00 400.00 435.00 435.00 $51362 513.62 19b Install Fire Hydrant Assert ly w/6" Gine Valve & Tee I EA 415.00 415.00 2,UOO.00 2,000,00 $2,064.02 2,064.02 29a lmw 11 Sample Points per County Detail 2.00 EA 200.00 400.00 100.00 200,00 $ 184.69 369.38 59a Lawn/ROW Restoration (Topsoil & Bahia Sod) 500 SY 6.00 3,000.00 200 1 ,000.00 $2.50 1 ,250.00 Subtotal Labor Cost $ 12. 115MO 12.38750 Subtotal Labor Cost with Item 03 $ 12,599.60 13,254.63 Total Materials _ 8'55&77 IRCDUS Farce Account 1 0. 10 $ 1,259.96 1 ,325,461 real Labor Cost I $13,859.56 14,580.09 TOTAL ESTIMATED COST $22,418.33 $33,138.86 TOTAL ESTIMATED LABOR COS I $13,859.56 $14,580.09 ' Underground UciLities , Tne . " Derrlco Consonction Corp. Attachment 3