HomeMy WebLinkAbout2005-077 WORK AUTHORIZATION DIRECTIVE
No . 2001 -202 IRC — Breezy Village Sanitary Sewer Relocation l ( J
DATE OF ISSUANCE : February, 2005 EFFECTIVE DATE : February, 2005
OWNER : Indian River County
CONTRACTOR: Underground Utilities , Inc . (George E . French)
CONTRACT : WATER, SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS
AND MISCELLANEOUS LABOR CONTRACT, UCP #909 , BID NO , 3032
PROJECT : IRC — 9890 61St Terrace , Lot 52 , Breezy Village Sanitary Sewer Relocation
COUNTY UTILITY PROJECT NO . : UCP #2576 CONTRACTOR ' S PROJECT NO . : N/A
COUNTY WIP No . 471 -26836-044699 Sewer Maintenance Fund
You are directed to proceed promptly with the following work:
Description:
Please relocate a sanitary sewer under the mobile home at 9890 61 " Terrace to the side easement between Lots 52
and 53 by constructing two doghouse manholes and about 65 LF of 6" PVC sewer line .
Purpose of Work Change Directive :
To remove sanitary sewer from underneath existing mobile home .
Method of determining Contract Price :
❑x Unit Prices : Bid Items as established pursuant to Bid No . 3032, and awarded by the Board
of County
Commissioners on January 7 , 2001 to George E . French, Renewed April, 2004 as Underground Utilities, Inc .
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below:
Estimated Labor Cost = $3 , 342 . 60 Estimated Contract Time : 30 days ,
V Y
Total Estimated Labor Costs = $ 35342 . 60 �' - '•. .;,
ACCEPTED : RECOM ENDED : ;API O ED :
4Geor . French Gordon E . Sparks, ��;�C'kainnae. Ord of County
Underground Utilities, Inc . Environmental Engineer Nf sslloneis
i
Date// Date : J � -�;g/ L>j '
Date : 02 - 22 - 2005