Loading...
HomeMy WebLinkAbout2006-326 v WORK AUTHORIZATION DIRECTIVE No. 2005-030 SEP 2 0 2006 020 /' - 3a6 UTILITIES IRC — Bella Vista Isles 6" Force Main on 26th Street East of 66" Avenue DATE OF ISSUANCE: September 19, 2006 EFFECTIVE DATE: September 19, 2006 OWNER: Indian River County CONTRACTOR: The Danella Companies Inc CONTRACT: WATER SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT, BID NO . 7033 , AWARDED March 15 . 2005 PROJECT Construct 6" PVC Force Main on North Side of 26`h Street per Construction Plans Prepared by Kimley-Hom & Assoc for Indian River County COUNTY UTILITY PROJECT NO. : UCP #2605 CONTRACTOR' S PROJECT NO . : N/A COUNTY W.I.P . No. 472- 169000-06530 You are directed to proceed promptly with the following work: Description: Construct about 600 feet of 6" PVC Force Main and necessary restoration to the ROW Purpose of Work Authorization Directive: The constntction of 6' PVC force main will allow future customers to connect from the east on 26" Street Attachments : (List documents supporting work) Method of determining Contract Price: ❑O Unit Prices: Bid Items as established pursuant to Bid No . 7033, and awarded by the Board of County Commissioners on March 15, 2005 to The Danella Companies, Inc. ❑ Lump Sum ❑ Cost of the Work The Cost of Labor, Contingency and Contract Time is summarized below: Estimated Labor Cost = $ 103576. 15 Estimated Contract Time: 30 days Total Estimated Labor Costs= $ 107576 . 15 . 1 ACCEPTED : RECO' ECO END APPROVED : BY By . The lldneames Gordon E. Spa s, P.E. Arthur R . euberg Labor Contractor Environmental Engineer COUNTY , CHAIF.MAN Date: "/ D (o Dater Iv-' 0(0 Date : 09 - 19 - 2006 Attachment 3 CAD0CUME-1 \NFIDUC-1 \L0CALS- 1 \Temp\nmes6030C8'A - Work Authorization No. 2005-030 Attachment 3 .doc9 Indian River County Department of Utilities COST ESTIMATE and CONTRACTOR'S BID ITEM LIST Project: IBC — Bella Vista Isles 6" Force Main on 26th Street east of 66th Avenue Description : UCP #2605, WIP # 471 -169000-06530 Misc. Sewer Fund Date: August 31 , 2006 LABOR COSTS MATERIAL COSTS Bid Bid Item Estimated Unit of Labor Unit Total Labor Material Unit Total Material Item No. Description Quantity Measure Price Price Price Price 63 Mobilization 1 4% 399. 10 $399. 10 Demobilization 1 I % 99.78 $99'78 65 Maintenance of Traffic 1 1 % 99'78 $99'78 3le Install 6" PVC Force Main 535 I,F $6.00 $3,210.00 $5.37 $2,872.95 09 Make Connection/Disconnection to Existing Mains I Eq $795.00 8795.00 $291 00 $291 .00 17c Install 6" GVBCB 2 EA $395.00 $790.00 $376.00 $752.00 06 Install MJRDI Fittings 0,5 TONS $1,665.00 $832.50 $3,500.00 $ 1 ,750.00 23 Potholes 5 FA $200.00 $1 ,000.00 53 ROW grading 2,000 Sy .$ IAO $2000.00 73a Sod and topsoil 500 Sy $2.70 $1 ,350.00 $ 1 .49 $745.00 Subtotal Subtotal Sewer System Labor $9,977.50 Subtotal Subtotal Sewer System Labor, Mob., Demob.. MOT $10,576. 15 SubTotal Labor Cost 10,576.15 Subtotal Material Costs $6,410.95 TOTAL PROJECT COST $ 16,987.10 Attachment 2 + COMMUJN1 EMS August 10, 2006 VIA FACSIMILE (772-7705143) and OVERNIGHT MAIL Mr. Michael C . Hotchkiss Indian River County Department of Utility Services 1840 25" Street Vero Beach , Florida 32960 Re : Bella Vista Isles Force Main Extension Requirements Dear Mr. Hotchkiss, CJM Construction of South Florida Inc. ("CJM") would like to take this opportunity to thank you for your assistance in resolving the "force main extension" requirements for the development project known as Bella Vista Isles. We truly appreciate your diligent effort in resolving this issue . We have reviewed the contents of your letter dated August 9, 2006 , and understand that this is a one time accommodation . It is our understanding that the Indian River County Utilities Department ("IRC") intends to undertake the construction of the "force main extension". Accordingly, in lieu of constructing the "force main extension" and inclusive of all extensions fees CJM will deliver a check in the sum of $ 16, 000 . 00 to IRC, as and for full payment and settlement of this issue. Additionally, you requested that our engineering consultant, Kimley-Horn & Associates Inc. (" KH") , provide construction observation services to IRC for construction of the "force main extension" and certification upon completion , at no cost to the municipality. Accordingly, we have communicated with KH and have provided them with a copy of your correspondence for review and consideration . CJM will facilitate delivery, to your office, of five (5) signed and sealed copies of the engineering plans for the "force main extension". Additionally, CJM has contracted with KH to provide construction observation services for the "force main extension" to be constructed by IRC . KH has agreed to provide the requested services provided your contractor gives adequate prior notice to KH of commencement, utility installation , and back-fill activities and such other prior notice and documentation as may be required by KH for certification of improvements. CJM will absorb the fees generated by KH for the construction observation services, inclusive of certification, provided IRC ' s contractor completes construction of the "force main extension" , in accordance with the plans provided , prior to completion of utility and infrastructure improvements at the Bella Vista Isles project. Again , we would like to thank you for you cooperation and assistance. e my Y David Ofstein Director of PI nning and Lan evelopment Cc: Eric Olson Melibe Tardaewether Attachment 1 9825 SW 18 ` STREET , SUITE 100 , BOCA BATON . FL 33428 PH . 561 -488-9509 FAx 561 -488 -2539 VV C/ W. CJMCOnNUN1T .Fs . COn