HomeMy WebLinkAbout2006-178 WORK AUTHORIZATION DIRECTIVE
No. 2005-027
WIP No. 472- 169000-06537
8-INCH MASTER PLAN FORCE MAIN
DATE OF ISSUANCE : JUNE 6, 2006 EFFECTIVE DATE : JUNE 6, 2006
OWNER: Indian River County
CONTRACTOR: The Danella Companies
CONTRACT : WATER, SEWER AND RECLAIM WATER LINE REPLACEMENT /
EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT BID NO 7033 February 15
2005
PROJECT: Construct about 2000 feet of 8" PVC and 300 feet of HDPE water main on lit Street SW
from 43rd Avenue to 27"' Avenue
COUNTY UTILITY PROJECT NO. : UCP #2823 CONTRACTOR' S PROJECT NO. : N/A
COUNTY W.I.P. No . N/A
You are directed to proceed promptly with the following work:
Description :
Construct about 2000 feet of 8" PVC AND 300 feet of HDPE water main on lsr Street SW from 43`d
Avenue to 27"' Avenue.
Method of determining Contract Price :
❑X Unit Prices : Bid Items as established pursuant to Bid No. 7033, and awarded by the Board of County
Commissioners on February 15 , 2005 to The Danella Companies
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below:
Estimated Labor Cost = $34,460 .60 Estimated Contract Time: 30 days
Total Estimated Labor Costs = $34,460 . 60
ACCEPTED /� RECO ENDE /J APPROVED :
By: � �//��/ By:
Danella Companies, Inc. ENGINEERChairman, B_ C - -
Date: Date :
S ✓ / �,� 0� Date: _ May -23',- 2006
�' ' � J - -
Arthur R . Neuberger
Attachment 3
F:AUti l itiesVUTILITY - ENO INEERINGAProjccts - UhIity Construction PermitsVIRC - 8-inch Master Planned Force Main on 1st Street SWAA -
Work Authorizalior No. 2005-027. Attachment 3.doe 9
WORK AUTHORIZATION DIRECTIVE
No. 2005-027
WIP No. 472-169000-06537
8-INCH MASTER PLAN FORCE MAIN
DATE OF ISSUANCE : JUNE 6, 2006 EFFECTIVE DATE : JUNE 65 2006
OWNER: Indian River County
CONTRACTOR: The Danella Companies
CONTRACT : WAFER, SEWER AND RECLAIM WATER LINE REPLACEMENT /
EXTENSIONS AND MISCELLANEOUS LABOR CONTRACTBID NO 7033 February 15
2005
PROJECT: Construct about 2000 feet of 8" PVC and 300 feet of HDPE water main on I ` Street SW
from 43`d Avenue to 2711i Avenue
COUNTY UTILITY PROJECT NO . : UCP #2823 CONTRACTOR ' S PROJECT NO. : N/A
COUNTY W.I . P. No . N/A
You are directed to proceed promptly with the following work:
Description :
Construct about 2000 feet of 8" PVC AND 300 feet of HDPE water main on 1 ST Street SW from 43'd
Avenue to 271' Avenue.
Method of determining Contract Price :
O Unit Prices: Bid Items as established pursuant to Bid No. 7033 , and awarded by the Board of County
Commissioners on February 15, 2005 to The Danella Companies
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below :
Estimated Labor Cost = $345460 . 60 Estimated Contract Time: 30 days
Total Estimated Labor Costs = $ 34,460 .60ij
r� 0 ?
ACCEPTCIV RECOt ENDS APl?20VED :
4 .
4
Danella Companies, Inc. ENGINEER 6hair` ian , B , C
�6 ` py Date : .` Mi,yi�23 , 2006
Date : S Date : / � � � •
Arthur C. Neuberger
Attachment 3
1':A [ti litiesAUI'ILITY - GNGIN 81i.R I NGAProjects - Utility Construction PcrmksV1RC - 9-inch Masicr Planned Poree Main on I st sit eel S W\t1 -
Work Anth01'19ation No. 2005-027, Attachment 3 . doc9
f
Indian River County Department of Utilities
COST ESTIMATE and CONTRACTOR'S BID ITEM LIST
Project: IRC - Proposed 8" Master Planned Force Main on 1st Street SW from 43rd Avenue to 27th Avenue
)escription: WIP #472-169000- UCP #2823
12-May-06 I LABOR COSTS MATERIAL COSTS
Bid Bid Item Estimated Unit of Labor Unit Total Labor Material Unit Total Material
Item No. Descri rtion uantits D7easure Price Price Price Price
77 Mobilization 1 1 4% 1 ,300.40
78 Demobilization I 1 % 325 . 10
79 Maintenance of Traffic 1 1 1 % 1 1 325 . 10
04c Install 8" HDPE Horiz. Directional Drill 300 LF 1 $2200 6,600.00 $14.99 4,497.00
06 Install MRJD1 Fittings 2 Tons $ 1 ,665.00 3 ,330.00 $3,500 7,000.00
31f Install 8" PVC Force Main 2,000 LF $6.50 13,000.00 10.44 20,880.00
13d Tap 10" Main for Installation of Assembly I EA $700.00 700.00
nb Install Wet Tap Assembly 10" X 8" 1 EA $900.00 900.00 1 ,788.30 1 ,788 .30
17d Install 8" GV&B 2 EA. $420.00 840.00 716. 10 1 ,432.20
23 Potholes 6 EA. $200.00 11200.00
73a Topsoil & Sod 2.200 SY $2.70 5,940.00 2. 17 4,774.00
Subtotal Subtotal Sewer System Labor 32,510.00
Subtotal Sewer System Labor, Mob.,
Subtotal 34
Demob. ,460.60
SubTotal Labor Cost 1 $34,460.601 SubTotal Mater. Cost 1 $40,371 .50
TOTAL. PROJECT COST $74,832. 10
Attachment 2
f
Indian River County Department of Utilities
COST ESTIMATE and CONTRACTOR'S BID ITEM LIST
Project: IRC - Proposed 8" Master Planned Force Main on 1st Street SW from 43rd Avenue to 27th Avenue
)escription: WIP #472-169000- UCP #2823
12-May-06 I LABOR COSTS MATERIAL COSTS
Bid Bid Item Estimated Unit of Labor Unit Total Labor Material Unit Total Material
Item No. Descri rtion uantits D7easure Price Price Price Price
77 Mobilization 1 1 4% 1 ,300.40
78 Demobilization I 1 % 325 . 10
79 Maintenance of Traffic 1 1 1 % 1 1 325 . 10
04c Install 8" HDPE Horiz. Directional Drill 300 LF 1 $2200 6,600.00 $14.99 4,497.00
06 Install MRJD1 Fittings 2 Tons $ 1 ,665.00 3 ,330.00 $3,500 7,000.00
31f Install 8" PVC Force Main 2,000 LF $6.50 13,000.00 10.44 20,880.00
13d Tap 10" Main for Installation of Assembly I EA $700.00 700.00
nb Install Wet Tap Assembly 10" X 8" 1 EA $900.00 900.00 1 ,788.30 1 ,788 .30
17d Install 8" GV&B 2 EA. $420.00 840.00 716. 10 1 ,432.20
23 Potholes 6 EA. $200.00 11200.00
73a Topsoil & Sod 2.200 SY $2.70 5,940.00 2. 17 4,774.00
Subtotal Subtotal Sewer System Labor 32,510.00
Subtotal Sewer System Labor, Mob.,
Subtotal 34
Demob. ,460.60
SubTotal Labor Cost 1 $34,460.601 SubTotal Mater. Cost 1 $40,371 .50
TOTAL. PROJECT COST $74,832. 10
Attachment 2
PI
PROPOSED 4'
FORCE MAIN
(BY OTHERS)
Do INR
135 r
F CC MA
Est STREET W
EXIT TING 8' 127
F ra CTE' MG
0 CE MAIN EX STING 4'
MA
ED CE IN
ATTs4CF111AE1mT 1 �
J
PI
PROPOSED 4'
FORCE MAIN
(BY OTHERS)
Do INR
135 r
F CC MA
Est STREET W
EXIT TING 8' 127
F ra CTE' MG
0 CE MAIN EX STING 4'
MA
ED CE IN
ATTs4CF111AE1mT 1 �
J
WORK AUTHORIZATION DIRECTIVE
No. 2005-027
WIP No. 472-169000-06537
8-INCH MASTER PLAN FORCE MAIN
DATE OF ISSUANCE : JUNE 6, 2006 EFFECTIVE DATE : JUNE 65 2006
OWNER: Indian River County
CONTRACTOR: The Danella Companies
CONTRACT : WAFER, SEWER AND RECLAIM WATER LINE REPLACEMENT /
EXTENSIONS AND MISCELLANEOUS LABOR CONTRACTBID NO 7033 February 15
2005
PROJECT: Construct about 2000 feet of 8" PVC and 300 feet of HDPE water main on I ` Street SW
from 43`d Avenue to 2711i Avenue
COUNTY UTILITY PROJECT NO . : UCP #2823 CONTRACTOR ' S PROJECT NO. : N/A
COUNTY W.I . P. No . N/A
You are directed to proceed promptly with the following work:
Description :
Construct about 2000 feet of 8" PVC AND 300 feet of HDPE water main on 1 ST Street SW from 43'd
Avenue to 271' Avenue.
Method of determining Contract Price :
O Unit Prices: Bid Items as established pursuant to Bid No. 7033 , and awarded by the Board of County
Commissioners on February 15, 2005 to The Danella Companies
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below :
Estimated Labor Cost = $345460 . 60 Estimated Contract Time: 30 days
Total Estimated Labor Costs = $ 34,460 .60ij
r� 0 ?
ACCEPTCIV RECOt ENDS APl?20VED :
4 .
4
Danella Companies, Inc. ENGINEER 6hair` ian , B , C
�6 ` py Date : .` Mi,yi�23 , 2006
Date : S Date : / � � � •
Arthur C. Neuberger
Attachment 3
1':A [ti litiesAUI'ILITY - GNGIN 81i.R I NGAProjects - Utility Construction PcrmksV1RC - 9-inch Masicr Planned Poree Main on I st sit eel S W\t1 -
Work Anth01'19ation No. 2005-027, Attachment 3 . doc9