HomeMy WebLinkAbout2007-167 WORK AUTHORIZATION DIRECTIVE
No. 2007-003 tt
Dasie Hope Center/Douglas School Private Pump Station and Force Main ? H t
DATE OF ISSUANCE : June 2007 EFFECTIVE DATE : June 2007
OWNER: Indian River County
CONTRACTOR: Underground Utilities , Inc .
CONTRACT: WATER, SEWER AND RECLAIM WATER LINE REPLACEMENT /
EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT BID NO 2007026 February
612007
PROJECT : Construct about 400 feet of 4" PVC force main, about 165 feet of 4" HDPE force main about
270 feet of sewer service electrical service and a duplex grinder pump station
COUNTY UTILITY PROJECT NO. : UCP #2940 CONTRACTOR' S PROJECT NO. : N/A
COUNTY W.I.P. No. 472- 169000-07514
You are directed to proceed promptly with the following work:
Description:
Construct 4" PVC force main in 64" Avenue, 4" directional drill force main in 64°i Avenue, sewer
service, electrical service and a private duplex grinder pump station
Method of determining Contract Price:
x❑ Unit Prices: Bid Items as established pursuant to Bid No . 2007026, and awarded by the Board of
County Commissioners on February 6, 2007 to Underground Utilities, Inc .
❑ Lump Sum
❑ Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below:
Estimated Labor Cost = $51 ,964. 64 Estimated Contract 60 days
Time:
Total Estimated Labor Costs = 551 ,964. 64 ;c
ACCEPTED: RECO MENDED: AF4`ROVED :�
By: By: /f/ By < C
Underground Utilities, Inc . Gordon E. S arks, P . Gai : .: • C; 'Wheeler
Labor Contractor Engineer Chairman, BCC
Date: <s--10 '7 Date: 07 Date: May 22 2007
Attachment 2
F-AUtilitiesVUTILITY - ENGINEERINGAProjects - Utility Construction Pcrmits\IRC - Dasie Hope Center Pump Station & FM UCP #2940
(Douglas School)\A - Work AuthUrilatlon No. 2007-003 .doc9
t 7
Indian River County Department oft It l hies
COST ESTIMATE and CONTRACTOR'S BID ITEM LIST
Project: IRC - Proposed 8" Master Planned Force Mein on Ist Street SW from 43rd Avenue to 27th Avenue
)escription: WIP #472- 169000-06537 UCP #2823
10-Ma --07 LABOR COSTS MATERIAL COSTS
Bid Bid Itofl Unit of Labor Unit Total Labor 3laterial Cnit Total 0later!at
Item Vo. Descri tion at
uantity Measure Price Price Price Price
63 Mobilization, Demobilization & MOT 1 % $0.04 S1 ,998.64
28b Duplex Grinder Station (TX 12') 1 EA $3,000.00 53 ,000.00 $ 11 ,000 $ 11 ,000.00
29d Install 4" PVC Force Main 386 LF $ 10.00 S3 .860.00 $2.39 $922.54
05a Install 4" HDPE Dir. Drill Force Main 163 LF $30.00 S489000 53 .44 $560.72
l4b Install 12"X 4" SS Wet Tap Assembly and Tap Main 1 EA $ 1 ,200.00 51 ,200.00 $ 1 ,200 511200.00
7 Install MJRDI Fittings 0.25 TONS $7,000.00 S1 ,750.00 3 ,500.00 $875.00
17b Install 4" MJGV&B 4 EA $300.00 51 ,200.00 450.00 $ 1 ,800.00
40d Install Double Sewer Service (>7' ) 270 LF $ 12.00 53,240.00 2.46 $664.20
45b Install 2" Sewer Air Release valve .Assembly & Manhole Structure I EA S800.00 $800.00 2362.00 $2,362.00
0 AbandonTill Septic Tanks per Dept of Health 3 EA 5500.00 $ 1 .500.00 1 ,000.00 $3,000.00
22 Potholes 10 EA S150.00 $1 ,500.00
59b Sod and topsoil 1 ,000 LF $6.00 $6,000.00 2.50 $2,500.00
16 Waterservice - Single long w/ 1 " meter and box I> 50' ) 1 EA 51 , 100.00 $ 1 , 100.00 161 .67 $ 161 .67
26a Assemble & install 3/4"-2" Backflow Assembly 2 EA 5150.00 $300.00 215 .46 $430.92
29b Install 2" Force Main 191 LF $6.00 $ 1 , 146.00 1 .501 5286.50
05a Install T' HUFF Dir Drill Force Main 70 LF 530.00 $2, 100.00 1 .501 S105 .00
99 Install 2" Electrical Conduit 200 LF $6.00 $ 1 ,200.00 0.67 5134.00
05a Install 2" HDPE Dir Dill Electrical Conduit 70 LF 530.00 $2, 100.00 1 .50 5105.00
99 Install Electrical Panel (lift station) I EA $2,000.00 $2,000.00 11400.00 $ 1 .400.00
99 Install SS Disconnect (lift station) t EA $500.00 $500.001 475.00 5475.00
61a Well Point, Each Tier, (0' - 15') (lift station) 1 LS $2.500.00 $2,500.00
'1615 Additional Well Points (below 5' for service line on grade) 33 LS S50.00 $ 1 ,650.00
99 Install Inline Sewer Clean Out Assembly 7 EA $60.00 $420.00 160.33 $ 1 , 122.31
58 Load and Haul Debris to Landfill l TONS $35.00 $35.00
55 Sidewalk repair 9 SF $5.00 $45.00 15 .00 $ 135 .00
99 Remove Electrical Sewer Pumps & Panel for Septic Tanks 3 EA $300.00 $900.00
60 Density Test and Proctor 10 EA $ 150.00 $ 1 ,500.00
99 Onsite Utility Locates I LS $ 150.00 $ 150.00
99 Support Light Poles 1 EA $500.00 5500. 00
99 Remove and Replace Chain Link Fence _ 1 LS $400.00 5400.00
56 Tree & Stump Removal & Disposal. Per Inch Diameter 24 EA $20.00 -S48000 -
62
4800062 Record Drawhip I LS 52,000.00 S2.000.00
Subtotal Subtotal Sewer System Labor 49,966.00
Subtotal Subtotal Sewer System Labor, Mob., Demob. 51 ,964.64
SubTotal Labor Cost 1 $51 ,964.64 SubTotal Mater. Cost F $29,239.86
TOTAL PROJECT COST $81 ,204.50
Attachment 1