HomeMy WebLinkAbout2006-207 (y7p
D
WORK ORDER NUMBER V1 7
a v Co — a07
ALTERNATE DESIGN TO THE EXISTING VORTEX TREATMENT SYSTEM DESIGN
FOR THE NORTH , MAIN , AND SOUTH RELIEF CANALS
This Work Order Number V1 is entered into as of this 13th day of June
2006 , pursuant to that certain Continuing Contract Agreement for Professional Services
entered into as of March 15 , 2005 ("Agreement') , by and between Indian River County, a
political subdivision of the State of Florida ("COUNTY") and Malcolm Pirnie , Inc .
("CONSULTANT") .
The COUNTY has selected the CONSULTANT to perform the professional services
set forth on Attachment 1 , attached to this Work Order and made part hereof by this
reference . The professional services will be performed by the CONSULTANT for the fee
schedule set forth in Attachment 2 , attached to this Work Order and made a part hereof by
this reference . The CONSULTANT will perform the professional services within the
timeframe more particularly set forth in Attachment 3 , attached to this Work Order and
made a part hereof by this reference , all in accordance with the terms and provisions set
forth in the Agreement. Pursuant to paragraph 1 . 4 of the Agreement , nothing contained in
any Work Order shall conflict with the terms of the Agreement and the terms of the
Agreement shall be deemed to be incorporated in each individual Work Order as if fully set
forth herein .
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of
the date first written above .
CONSULTANT BOARD OF COUNTY COMMISSIONERS
MALCOL PIRNIE , INC . OF INDIAN RIVER COUNTY
By : Bye
� , 4Gar . Wheeler ,. Vice Chairman
Title :` r.�.[c�2 1i�FhlL� y � aa�'S3�aspvs�a`;`
Attest : J . K . Barton„ C�,lerr1Q,of"Court
By �J ! #rr
Deputy Clerk
Approved
J seph . Baird ; County Administrator
pp ed to foLm-,andJagal suffici cy:
ria Fell , Assista t County ttorney
ATTACHMENT 1 to WORK ORDER NO, 111
ALTERNATE DESIGN TO THE EXISTING VORTEX TREATMENT SYSTEM
DESIGN FOR THE NORTH , MAIN , AND SOUTH RELIEF CANALS
1 , SCOPE OF WORK
The CONSULTANT shall provide certain engineering and AutoCAD drafting services as
necessary for COUNTY staff to prepare an alternate design to the existing vortex
treatment system design for the North , Main , and South Relief Canals . (CONSULTANT is
already familiar with said vortex treatment system design , having assisted the COUNTY
with its review of the vortex treatment system construction drawings and technical
specifications . )
1 . 1 Activities
A . Provide professional structural and electrical engineering design services , including
technical specifications , bid quantities , and opinion of probable construction cost for
the electrical and structural systems . Said Work will be competitively bid as an
alternate design to the original vortex treatment system design . ( Both designs may
be included the same bid package . )
B . Provide AutoCAD drafting services (AutoCAD release 2005 or later) . The COUNTY
will prepare certain redlined construction drawings for the alternate design and it will
send these to the CONSULTANT who will transfer the COUNTY design to AutoCAD
drawings .
C . Provide quality control review services for all of the construction drawings and
technical specifications prepared for the alternate design . Said reviews shall occur
at 60 percent and 90 percent completion . Comments shall be written on the plans
and technical specifications and discussions shall be via conference telephone
calls .
2 . DELIVERABLES
2 . 1 60 Percent Design
A . The CONSULTANT will submit one set of drawings to the COUNTY for review at
the 60 percent completion level . If required by the COUNTY , the CONSULTANT
will meet with the COUNTY to discuss the submittals and subsequently revise the
drawings per the COUNTY' s comments .
B . The 60 percent level of completion submittal will include a complete set of structural
and electrical drawings indicating all pertinent features of the alternate design
together with applicable construction details .
C . The CONSULTANT will submit one set of technical specifications at the 60 percent
completion levels . The 60 percent submittal will include a table of contents and a
preliminary draft of all the required technical specification sections .
2. 2 90 Percent Design
The 90 percent level of completion is defined as the incorporation of all COUNTY
comments received and verified after the 60 percent review with the COUNTY . The
drawings will be at a level of completion that will allow the project to be bid . The
CONSULTANT will submit one set of technical specifications and drawings at the 90
percent completion level . If requested by the COUNTY , the CONSULTANT will meet with
the COUNTY to discuss the submittal and subsequently revise the drawings per the
COUNTY' s comments .
2. 3 100 Percent Design
At the 100 percent submittal , two sets of the drawings will be submitted together with an
electronic copy using AutoCADTm Release 2005 or later format . The 100 percent submittal
will also include bid schedule , table of contents , and technical specifications in electronic
Microsoft WordTM format . The CONSULTANT will prepare and submit an Engineer's
Opinion of Probable Construction Cost for the project at the 100 percent design level .
2 .4 Conformed Sets
Conformed sets - After the project is bid but before the COUNTY awards the construction
contract , provide five signed and sealed copies of the conformed structural and electrical
contract drawings and five signed and sealed sets of the conformed technical
specifications .
3. 0 BIDDING ASSISTANCE AND CONSTRUCTION SERVICES
The CONSULTANT will provide bidding assistance (including pre- bid conference) and
construction services at an hourly rate as requested in writing by the COUNTY .
" END OF ATTACHMENT 1 "
ATTACHMENT 2 to WORK ORDER NO, V1
ALTERNATE DESIGN TO THE EXISTING VORTEX TREATMENT SYSTEM
DESIGN FOR THE NORTH , MAIN , AND SOUTH RELIEF CANALS
1 . COMPENSATION
The COUNTY agrees to pay and the CONSULTANT agrees to accept , a not-to-exceed fee
of $83 ,955 for services rendered according to Attachment 1 of this WORK ORDER .
Hourly rates for AutoCAD services shall be as set forth in the Agreement .
2 , PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the CONSULTANT for all
authorized work pertaining directly to this project performed during the previous calendar
month . The CONSULTANT shall submit invoices monthly for services performed and
expenses incurred pursuant to this Agreement during the prior month .
The CONSULTANT shall submit duly certified invoices in duplicate to the Director of
the Public Works Department . For lump sum line items , the amount submitted shall be the
prorated amount due for all work performed to date under this phase , determined by
applying the percentage of the work completed as certified by the CONSULTANT , to the
total due for this phase of the work. For time and material line items , the amount
submitted shall be based on the actual hours worked and expenses incurred for the billing
period .
The amount of the partial payment due the CONSULTANT for the work performed
to date under these phases shall be an amount calculated in accordance with the previous
paragraph , less ten percent ( 10%) of the invoice amount thus determined , which shall be
withheld by the COUNTY as retainage , and less previous payments . Per F . S . 218 . 74 (2 ) ,
the COUNTY will pay approved invoices on or before the forty-fifth day after the COUNTY
receives the CONSULTANT's invoice .
Per F . S . 218 . 74(2 ) , the ten percent ( 10%) retainage withheld shall be paid in full to
the CONSULTANT by the COUNTY , on or before the forty-fifth day after the date of final
acceptance of the Work by the Public Works Director.
** END OF ATTACHMENT 2**
ATTACHMENT 3 to WORK ORDER NO. V1
ALTERNATE DESIGN TO THE EXISTING VORTEX TREATMENT SYSTEM
DESIGN FOR THE NORTH , MAIN , AND SOUTH RELIEF CANALS
1 . TIME FOR COMPLETION
The CONSULTANT will complete the 100 percent design within 75 days of
receiving the Notice -to- Proceed from the COUNTY , excluding COUNTY review time .
" END OF ATTACHMENT 3"
EXHIBIT A
Indian River County
Vortex Project
Engineering Fee Estimate
Task PRO Total Exp. Cost/
No. Task Description OFF MGR PE ENG ELEC CADD Admin bra Task
1 .0 Coordination Services
1 . 1A Coordinate Subs 8 8 16 $100 $2,404
1 . 1 S AutoCAD Services 2 8 80 4 94 $100 $7,892
IAC 60% & 90% OC Review 16 16 4 36 $100 $4,988
Total Task 1 .0 - Coordination Services 0 26 32 0 0 80 8 146 $300 $15,284
2.0 Final Design Services
2. 1A 60% Design Review Meeting 8 2 10 $188 $1 ,704
2. 1B 60% Design Review 2 12 8 8 30 $238 $4,274
2. 1C 60% Design Specifications 12 8 20 $750 $3,742
2.2 90% Design Review Meeting 8 2 10 $688 $2,204
2.3 100% Design Review 8 4 8 20 $43,450 $45,914
2.4 Conformed Sets (5 Sets) 1 1 4 41 41 13 $750 $1 ,978
Total Task 2.0 - Final Design Phase 2 49 24 0 0 20 8 103 $46,063 $59,815
3.0 113iddinq Assistance & Construction Services
3. 1 1 Bid & CA Services 1 241 301 1 1 1 8 62 $6881 $8,856
Total Task 3.0 - Bidding & Construction
Assistance Phase 0 24 30 0 0 0 8 62 $688 $8,856
Total Hours 2 99 86 0 0 100 24 311
Hourly Rate $210.00 $172.00 $116.00 $85.00 $116.00 $78.00 $70.00
Total Malcolm Pirnie Salary Cost $420 $17,028 $9,976 $0 $0 $7,800 $1 ,680 $36,904 $47,051 $83,955
Times 1 .0 Multiplier $420 $17,028 $9,976 $0 $0 $7,800 $1 ,680
Malcolm Pirnie Labor Totals $36,904
Total Project Lump Sum Fee (includes labor and expenses) $83,955
P:\2240015 Rockridge Surge\Copy of Feeestimale-Vortex 5.26.06.xls
EXHIBIT B
' Indian River County
Vortex Project
Estimated Expenses
Task Mileage Total
No. Task Description Miles Cost Specifications Drawings Other Expenses
1 .0 Coordination Services
1 . 1A Coordinate Subs $100 $100
1 . 16 AutoCAD Services $ 100 $100
1 . 1C 60% & 90% QC Review $100 $100
Total Task 1 .0 - Coordination 0 $0 $0 $0 $300 $300 Ali
2.0 Final Design Services
2. 1A 60% Design Review Meeting 240 $88 $100 sisal
2A 60% Desi gn Review 240 $88 $150 $238
2. 1C 60% Design Specifications $250 $350 $150 $750
2.2 90% Design Review Meeting 240 $88 $100 $100 $400 $668
2.3 100% Design Review $43,450 $43,450
2.4 Conformed Sets (5 Sets) $250 $350 $150 $750
Total Task 2.0 - Final Design Phase 720 $263 $600 $800 $44,400 $46,063
3.0 IBiddinq Assistance & Construction Services
3. 1 1 Bid and CA Services 1200 $438 $50 $50 $150 $688
Total Task 3.0 - Bidding & Construction
Assistance Phase 1200 $438 $50 $50 $150 $688
TOTAL LUMP SUM (Tasks 1 .0 to 3.0) $1 ,920 $701 $650 $850 $44,850 $47,051
Total Project Lump Sum Expenses 547,051
Subconsultants: Barth $19,500
Electrical $20,000
Subtotal $39,500
x0. 10 $3,950
Total $43,450
P:\2240015 Rockridge Surge\Copy of Feeestimate-Vortex 5.26.06.xls