HomeMy WebLinkAbout2006-249 WORK ORDER NUMBER 4 �' y a q
This Work Order Number 4 is entered into as of this 111 day of July 200 6
("Effective Date") pursuant to that certain Continuing Contract Agreement for Professional Services
entered into as of April 6, 2004 ("Agreement"), by and between Indian River County, a political
subdivision of the State of Florida ("COUNTY") and Masteller and Moler, Inc. ("CONSULTANT") .
The COUNTY has selected the CONSULTANT to perform the professional services set forth
in Attachment 1 (Scope of Work), attached to this Work Order and made a part hereof by this
reference. The professional services will be performed by the CONSULTANT for the fee schedule set
forth in Attachment 2 (Fee Schedule), attached to this Work Order and made a part hereof by this
reference. The CONSULTANT will perform the professional services within the timeframe more
particularly set forth in Attachment 3 (Time Schedule), attached to this Work Order and made a part
hereof by this reference all in accordance with the terms and provisions set forth in the Agreement.
Pursuant to paragraph 1 .4 of the Agreement, nothing contained in any Work Order shall conflict with
the terms of the Agreement and the terms of the Agreement shall be deemed to be incorporated in
each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date
first written above.
CONSULTANT: BOARD OF COUNTY COMMISSIONERS
Masteller and Moler, Inc. OF INDIAN RIVER `COUNTY
By: oaf By: A ,, ?
Arthur R. Neuberg , Chairman
Title:
BCC Approved: July 11 , 2006
Date: (Date)
Attest: J. K. Barton, Clerk of Court
ry
By. Deputy Clerk oto ' t ?t;
se
p � . d
Approved :
Y
By: _ C'J Ulc
oseph Baird, County Administrator a 1
APYManan
form and legal sufficiency:
E. Fe ssis ant oun Attorney
Our File #0627LA
June 16, 2006
NON-EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
ATTACHMENT 1
• Project Description
Work Authorization #4 provides for professional engineering services for preparation of a plan of
action and tasks to convert an 8" wastewater force main into a reuse main.
Masteller & Moler, Inc. will utilize its expertise on wastewater force main conversion into reuse
mains relative to the 8" pipeline between the North and Central WWTP along Lateral G Canal. We
will conduct site visit(s); prepare plans, specifications and bid documents to transform the force
main into a reuse main including: cleaning, disinfecting, leak detection, valve checking and
hydrostatic testing. Included in our services will be detail plans showing the piping connection to
the 12 " reuse line at the North County WWTP site and the 16" reuse line at the Central County
WWTP site. We will also prepare the FDEP permit application as well as bidding and services
during construction.
The Estimated Cost of the Project is $275,000. 00
A brief description of the scope of services and deliverables for Work Authorization 94 is provided
below:
• Scope of Services
Task A — Contract Plans/Specifications
Masteller & Moler, Inc. will meet with County staff, conduct site visits along the existing 8" force
main route; prepare construction plans; project specifications; prepare a plan of action; and prepare
bid documents to convert the existing 8" force main into a reuse main. Contract plans will show the
method of connection to the existing reuse system piping on the North Regional and Central
Regional Wastewater Treatment Plant ends of the pipeline. Our services will include preparation of
permit applications.
(H \Projects\0627\ADMIMContracts\0627_Attachment I_rev.061606.doc)
Attachment 1
6/5/2006
Page 2
Task B — Construction Services
Masteller & Moler, Inc. will provide assistance during bidding and periodic inspection of the
pipeline conversion project on an as needed basis to observe that construction is in reasonable
compliance with contract plans and specifications. Observations of pipe cleaning, disinfection, leak
detection, valve checking and hydrostatic testing will be conducted by our staff to assure the County
Utilities is getting a good job.
Our File 40627
June 16, 2006
NON-EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
ATTACHMENT 2
Method and Amount of Compensation
Masteller & Moler, Inc . proposes to provide the above Scope of Services based on the following
lump sum fees:
Tasks A Engineering design; preparation of Construction Plans;
preparation and submittal of Permitting Applications; and
preparation of Specifications and Bid Documents utilizing
Standard IRC Bid Documents. Forms, Documents and
Drawings will be in electronic Format MS Word $ 15 ,320 . 00
Task B. Assistance during Bidding, Bid Evaluation, Contract
Award and Construction Administration and Periodic
Administration and Periodic Construction /Field
Inspection $ 11 ,310 . 00
ATTACHMENT #2
INDIAN RIVER COUNTY LUMP SUM FEE TABULATION 6/16/2006
CONVERSION OF 8" FM ALONG LATERAL "G" BETWEEN CRW WiP & HOBART ROAD TO 8', REUSE MAIN
ENGINEERING DESIGN/PREPARATION OF CONSTRUCTION PLANS & PERMITTING APPLICATIONS/
PREPARTION OF SPECIFICATIONS AND BID DOCUMENTS
Professional Engineer Project Engineer Desi ner CAD Administration
S15500 $ 125.00 $ 80.00 $ 45.00 Total Comments
Hours Amount Hours Amount Hours Amount Hours Amount Costs
Engineering Design 30 $ 4,650.00 0 $ - 10 $ 800.00 4 $ 180.00 $ 5,630.00
Preparation of 4 $ 620.00 0 $ - 16 $ 1 ,280.00 4 $ 180.00 $ 2,080.00
Construction Plans
Preparation & Acquisition 4 $ 620.00 8 $ 1 ,000.00 8 $ 640.00 10 $ 450.00 $ 2,710.00
of Permits
Prepare Specifications 20 $ 3, 100.00 0 $ - 0 $ - 40 $ 1 ,800.00 $ 4,900.00
and Bid Documents
Total (hrs/cost) 58 $ 81990.00 8 $ 1 ,000.00 34 $ 2,720.00 58 $ 2,610.00 $ 15,320.00
File 0627LA
Schetl_manhours.zls
(Design_Sewices)
ATTACHMENT #2
LUMP SUM FEE TABULATION 6/16/2006
INDIAN RIVER COUNTY
CONVERSION OF 8" FM ALONG LATERAL "G" BETWEEN CRW WTP & HOBART ROAD TO 8" REUSE MAIN
ASSISTANCE DURING BIDDING AND CONTRACT AWARD
CONTRACT ADMINISTRATION/PERIODIC CONSTRUCTION OBSERVATION
Professional Engineer Project Inspector Administration
$ 155.00 $ 70.00 $ 45.00 Total Comments
Hours Amount Hours Amount Hours Amount Costs
Assistance during 4 $ 620.00 4 $ 280.00 20 $ 900.00 $ 1 ,800.00
Bidding & Contract
Award
Contract Administration 6 $ 930.00 12 $ 840.00 14 $ 630.00 $ 2,400.00 Includes review of
Shop Drawings
Periodic Construction 12 $ 1 ,860.00 75 $ 5,250.00 $ - $ 7, 110.00
Observation
Total (hrs/cost) 22 $ 3,410.00 91 $ 6,370.00 34 $ 1 ,530.00 $ 11 ,310.00
File 0627LA
Sched_manhours.zls
(Construction-Services)
Our File #0627
June 16, 2006
NON-EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
ATTACHMENT #3
• Time of Performance
The estimated time frame for completion of services from the approval of this Work Authorization* is as
follows :
MILESTONE *COMPLETION DATE
Engineering Design &
Preparation of Construction Plans
Submittal of Permit Applications July 17, 2006
Project Construction Services Completed October 20, 2006
*Dates are based on assumption that County Commission will approve on June 12 , 2006 .