WORK ORDER NO. 5 (Engineering)
FOR
PROFESSIONAL BRIDGE DESIGN SERVICES AGREEMENT
FOR ANNUAL BRIDGE DESIGN SERVICES CONTRACT
WITH
Bridge Design Associates, Inc.
Indian River County Project No. 0107-B
This Work Order No. 5 is in accordance with the existing AGREEMENT dated October 3 ,
2006 between Bridge Design Associates, Inc. (ENGINEER) and Indian River County
(COUNTY).
This Work Order No. 5 amends the agreement as follows:
SECTION I - PROJECT LIMITS
53'd Street Bridge over I.R.F.W.C .D. Lateral H Canal
SECTION H - SCOPE OF SERVICES
This Work Order No. 5 is for providing Construction Phase Service (Construction Engineering
and Inspection) for the above mentioned project.
SECTION III - TIME FOR COMPLETION
During Bidding and Construction Phases.
SECTION IV - COMPENSATION
The COUNTY agrees to pay, and the ENGINEER agrees to accept, a fee for services
rendered according to the "Scope of Services" identified in Section II and III of this Work
Order No. 5, Hourly Not To Exceed $30,883 .00.
C:\DOCUME-1 \Kimberly\LOCALS-1\Temp\Temporary Directory 2 for BCCBridgeDesignWorkOrder1W07-30-
07.zip\BCCBridgeDesign WorkOrder#507-30-07.doc
PAGE TWO
Work Order No. 5 Bridge Design Associates, Inc.
July 30, 2007
The AGREEMENT is hereby amended as specifically set forth herein. All remaining sections
of the AGREEMENT shall remain in full force and effect, and are incorporated herein.
IN WITNESS WHEREOF the parties hereto have executed these presents this
2 day of u sT 2007.
BRIDGE DESIGN ASSOCIATES, INC . INDIAN RIVER COUNTY, FLORIDA
BOARD OF COUNTY COMMISSIONERS
BY : �� BY: l�
Title: PRES ! DEIs'7-
GARY C. WHEYLER, CHAIRPERSON
(
Approved by the BCC : q l4 I0 -7
Witnessed By: � "� ATTEST: 4 . K. BARTON
Jeffrey K. Barton
� Clerk of Circuit Court
BY: Yet u o �ir kyr
D UE UTY CLERK OF CO RT
SEPH B IRD
C UNTY AD IS
WILLIAM G . COLLINS, II
COUNTY ATTORNEY
Approved as to Form and Legal Sufficiency
C:\DOCUME-1 \Kimberly\LOCALS-I\Temp\Temporary Directory 2 for BCCBridgeDesignWorkOrder#407-30-
07.zip\BCCBridgeDesign WorkOrder#507-30-07.doc
BRIDGE DESIGN ASSOCIATES , INC .
CONSULTING ENGINEERS
BRIAN C. RHEAULT, P.E.
President
July 23, 2007
Indian River County
1840 25'" Street
Vero Beach, Florida 32960
ATTENTION: Chris Kafer, P. E .
REGARDING: 53`' Street Bridge over Lateral "H" Canal
Construction Phase Services
PROJECT NO. : 05-623
Dear Chris:
Pursuant to your request, Bridge Design Associates, Inc. can provide the necessary
construction phase services at the above referenced project site. We propose to provide
these services on an hourly, not to exceed basis_
The attached Exhibit "A" is a manhour breakdown of tasks with commensurate fees .
If you have any questions, please give me a call.
Respectfully,
BRID E DESIGN ASSOCIATES, INC.
Brian C. Rheault, P. E.
President
BCR:kedS:V005-Jobs105.623 53rd Street at Lateral HICorrespondencelpro cps 07-23-07.wpd
, ft&v �
<5 D
JUS
ENG/H FR CCQ�TIo' Y
N
2035 Vista Parkway, Suite 200 • West Palm Beach, Florida 33411
(561) 686-3660 • Fax: (561) 686-3664
BRIDGE DESIGN ASSOCIATES, INC.
53RD STREET OVER LATERAL "H" CANAL
July 25, 2007
HOURLY BREAKDOWN OF SERVICES
EXHIBIT "A"
PROJECT PROJECT CADD FIELD TOTAL LABOR
MANAGER ENGINEER TECH REP/ HOURS COST
ACTIVITY E.I. BY BY
ACTIVITY ACTIVITY
$130.50 $110.20 $89.90 $62.35
Pre-Construction Meeting 2.0 2.0 4.0 $385.70
Shop Drawing Reviewes / concrete
mbc test pile, re-cast components 2.0 16.0 8.0 26.0 $2,523.00
Pile Casting / Sheet Pile 112.0 192.0 $6,983.20
Pile Driving 56.0 56.0 $3,491 .60
Pile Caps 16.0 16.0 $997.60
Prestressed Beams *48.048.0 $2,992.80
CIP Slab 8.0 $2,378.00
Median $498.80
Sidewalks $997.60
Banters $997.60
A roach Slab $997.60
Approach Slab sidewalks $997.60
Approach Slab barriers 16.0 16.0 $997.60
Slope Protection 16.0 16.0 $997.60
Final Ins ectton 2.0 2.0 4.0 $385. 70
Final Report & Certification 2.0 2.0 $261 . 00
TOTAL MANHOURS 8.0 24.0 0.0 372.0 404.0
DIRECT LABOR COST $1 ,044.00 $2,644.80 $0.00 $23, 194.20
=$26,883.00
ENGINEERING FEES $26,883.00
PDA Test $4,000.00
05-623 pro cps TOTAL FEES $30,883.00