HomeMy WebLinkAbout2006-355 s-
WORK ORDER NUMBER 8
This Work Order Number 8 is entered into as of this 10 day of October 2006
("Effective Date") pursuant to that certain Continuing Contract Agreement for Professional Services
entered into as of April 6, 2004 ("Agreement"), by and between Indian River County, a political
subdivision of the State of Florida ("COUNTY") and Masteller and Moler, Inc. ("CONSULTANT").
The COUNTY has selected the CONSULTANT to perform the professional services set forth
in Attachment 1 (Scope of Work), attached to this Work Order and made a part hereof by this
reference. The professional services will be performed by the CONSULTANT for the fee schedule set
forth in Attachment 2 (Fee Schedule), attached to this Work Order and made a part hereof by this
reference. The CONSULTANT will perform the professional services within the timeframe more
particularly set forth in Attachment 3 (Tissue Schedule), attached to this Work Order and made a part
hereof by this reference all in accordance with the terms and provisions set forth in the Agreement.
Pursuant to paragraph 1 .4 of the Agreement, nothing contained in any Work Order shall conflict with
the terms of the Agreement and the terms of the Agreement shall be deemed to be incorporated in
each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date
first written above.
CONSULTANT: BOARD OF COUNTY COMMISSIONERS
Masteller and Moler, Inc. OF INDIAN RIVER CO TY
By: � Q B
Arthur It. Neuber r, hairim
Title:
f�F BCC Approved: October _ 10 , 2006
Date:
91h 1 /&4 (Data)
Attest: J. K. Barton, Clerk of Court
By: Nk _— _ � pv\\ tel?
Deputy Clerk
Approved:
By: CTJ
seph A. Baird, County Admin strator
Appro d as to form and legal sufficiency:
B
lanAanE. F ssistan County Attorney
Our File #0649
August 31 , 2006
NON-EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
ATTACHMENT
• Project Description
Work Order No . 8 provides for professional engineering services for the surveying, design, permitting,
bidding and services during construction of a 12" force main for conveyance of wastewater in CR 510
between the east end of the Wabasso Bridge to A- 1 -A .
Work Order No . 8 is being implemented at this time to provide professional engineering services by
Masteller & Moler, Inc. associated with the project described above. The work to be performed as part
of this Work Order will generally include providing a route survey and base plans; preparation of project
design for the proposed 12" pipeline, preparation of contract plans; preparation of specifications and bid
documents ; preparation and submittal of permit applications, assistance during bidding and contract
administration/periodic inspection for the pipeline project.
The estimated project construction cost is $435 ,000 . 00
A brief description of the scope of services for Work Order No . 8 is provided below:
• Scope of Services
Task A — Route Survey and Base Plans
Masteller, Moler, Reed & Taylor, Inc. will perform a Route Survey for property located in Indian River
County and lying in Section 23 , Township 31 South, Range 39 East and identified as County Route 510,
from the east side of the Wabasso Bridge to State Road A- 1 -A (including intersection) . The total length
of the Route Survey is approximately 4600 linear feet.
Route Survey includes :
1 . Establish survey baseline as directed by the Engineer;
2 . Locate all monumentation for establishment of existing rights-of-way;
3 . Locate and identify all visible topographic features along the route (ie : power poles, mailboxes,
pavement, culverts, etc.) ;
4. Obtain elevations along the route sufficient for engineering design purposes;
5 . Elevations will be based on NGVD 1929 unless otherwise directed;
6. Produce map of survey drawing for basis of engineering design;
7. Provide five paper copies and one digital file of route survey upon completion of field work
Attachment 1
8/31 /2006
Page 2
Task B — Construction Plans
Masteller & Moler, Inc . will utilize the route survey and base plans prepared by Masteller, Moler, Reed
& Taylor, Inc. We shall use these base plans for design and preparation of construction plans for a 12"
diameter force main. This project will begin at the east end of the Wabasso Bridge approach and
proceed east to the existing pump station wet well at the southeast corner of CR 510 and Jungle Trail . A
separate section of the 12" force main will connect to the pump station wet well and proceed east to SR
A- 1 -A for connection to the existing force main system. The total estimated length of the proposed 12 "
force main is t 4,600 feet. Our plans will show the necessary gate valves, air release valves, directional
boring, and construction details.
Task C - Permitting
Masteller & Moler, Inc. services include permitting from the Florida Department of Environmental
Protection (FDEP). In addition, an Indian River County Utility and Right-of-way permit and the ACOE
Nationwide 14 Permit will be needed Masteller & Moler, Inc. will prepare the permit applications and
supporting data and submit on behalf of the County. Permit application fees are not included in this
Proposal .
Task D - Construction Services
Masteller & Moler, Inc. will provide assistance during bidding and periodic inspection of the pipeline
system project on an as-needed basis to observe that construction is in reasonable compliance with the
Contract Plans and Permits. We will also attend meetings, review shop drawings and monthly pay
estimates from the contractor.
Our File #0649
August 31 , 2006
NON-EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
ATTACHMENT
Method and Amount of Compensation
Masteller & Moler, Inc. proposes to provide the above Scope of Services based on the following
lump sum fees:
Tasks A. B, & C :
Provide for Surveying Services including Route Survey andBase Plan
Preparation, Engineering Design; Preparation & Submittal of Permit
Applications; Preparation of Specifications & Bid Documents Utilizing
Standard IRC Bid Documents. Forms, Documents & Drawings will be in
electronic Format MS Word
Fee for Tasks A, B & C $34 ,700 . 00
Task D :
Assistance during Bidding, Bid Evaluation, Contract Award &
Construction Administration; Periodic Administration and Periodic
Construction/Field Inspection
Fee for Task D $ 8 ,580.00
ATTACHMENT #2
LUMP SUM FEE TABULATION 6/312006
INDIAN RIVER COUNTY
12" FORCE MAIN PIPELINE ON CR 510 FROM EAST END OF WABASSO BRIDGE TO SR A-1 -A
PROVIDE FOR ENGINEERING DESIGN / PREPARATION OF CONSTRUCTION PLANS AND
PERMITTING APPLICATIONS / PERPARATION OF SPECIFICATIONS AND BID DOCUMENTS
Professional Engineer Pro ed Engineer Designer CAD Administration
$ 155.00 $ 125.00 $ 80.00 $ 45 .00 Total Comments
Hours Amount Hours Amount Hours Amount Hours Amount Costs
Engineering Design 6 $ 930.00 6 $ 750.00 15 $ 1 ,200.00 6 $ 270.00 $ 3, 150.00
Preparation of 18 $ 2,790.00 6 $ 750.00 75 $ 6,000.00 9 $ 405.00 $ 9,945.00
Construction Plans
Preparation & Acquisition 12 $ 1 ,860.00 9 $ 11125.00 25 $ 2,000.00 25 $ 1 , 125.00 $ 6, 110.00 Permits needed from ,
IRC ,
of Permits FDEP and ACOE
Prepare Specifications 10 $ 1 ,550.00 12 $ 1 ,500.00 6 $ 480.00 37 $ 1 ,665.00 $ 5 , 195.00 Includes final engineees
estimate
and Bid Documents of construction cost.
Total (hrs/cost) 46 $ 7,130.00 33 $ 4,125.00 121 $ 9,680.00 77 $ 3,465.00 $ 24,400.00
File 0649LA Engineering Design/Permitting $ 24,400.00
Sched_manhours.xls
(Design_Services) Surveying Services $ 10,300.00
Total $ 34,700.00
ATTACHMENT #2
LUMP SUM FEE TABULATION 8/312006
INDIAN RIVER COUNTY
12" FORCE MAIN PIPELINE ON CR 510 FROM EAST END OF WABASSO BRIDGE TO SR A-1 -A
ASSISTANCE DURING BIDDING AND CONTRACT AWARD
CONTRACT ADMINISTRATIOWPERIODIC CONSTRUCTION OBSERVATION
Professional Engineer Protect Inspector Administration
$ 155.00 $ 70.00 $ 45.00 Total Comments
Hours Amount Hours Amount Hours Amount Costs
Assistance during 6 $ 930.00 $ - 15 $ 675.00 $ 1 ,605.00
Bidding & Contract
Award
Contract Administration 10 $ 1 ,550.00 10 $ 700.00 10 $ 450.00 $ 2,700.00 Includes reviewof
Shop Drawings
Periodic Construction 5 $ 775.00 50 $ 3,500.00 $ - $ 4,275.00
Observation
Total (hrs/cost) 21 $ 3,255.00 60 $ 4,200.00 25 $ 10125.00 $ 8,580.00
File 0649LA
Sched_manhours.zls
(Construction—Services)
Our File #0649
August 31 , 2006
NON-EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
ATTACHMENT #3
• Time of Performance
The estimated time frame for completion of services from the approval of this Work Order* is as
follows :
MILESTONE *COMPLETION DATE
Route Survey & Base Plans Preparation October 3 , 2006
Engineering Design &
Preparation of Construction Plans November 7, 2006
Submittal of Permit Applications
And Receipt of Permits November 17, 2006
Project Construction Services January 31 , 2007
*Dates are based on assumption that County Commission will approve on September 12, 2006.
ATTACHMENT 4
INDIAN RIVER COUNTY UTILITIES DEPARTMENT 8/31 /2006
Schedule of Bid Items - Estimate for Proposal
12" Force Main East End of Bridge to A-1 -A on CR 510
ITEM # DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL PRICE
1 Mobilization 1 LS $ 391000.00 $ 39,000.00
2 Performance Bond/Payment Bond 1 LS $ 5,600. 00 $ 5,600.00
3 Testing Concrete, Soils, Etc. 1 LS $ 31000. 00 $ 31000.00
4 MOT 1 LS $ 5,000. 00 $ 52000. 00
5 Survey & As-builts 4600 LF $ 2 . 00 $ 91200. 00
12" PVC C-905 DR 18, CL 235 4070 LF $ 40. 00 $ 1621800.00
Force Main
7 12" Directional Bore 530 LF $ 160 . 00 $ 841800. 00
8 Air Release Valve Assembly 0 EA $ -
9 12" Gate Valves 8 EA $ 2 ,250. 00 $ 18, 000. 00
10 MJ Fittings w/restraints expoxy 2. 8 Tans $ 91500. 00 $ 26,600. 00
coated
11 Connection to Existing FM 1 LS $ 51000.00 $ 5,000.00
on A-1 -A
12 CAP Proposed 12" PVC FM 1 LS $ 500. 00 $ 500.00
13 Connection to Existing Wet Well 2 LS $ 7 ,500.00 $ 15,000.00
14 Restoration - Seed & Mulch 3600 SY $ 1 .00 $ 37600.00
15 Restoration - Dirt Driveways 50 SY $ 5.00 $ 250. 00
$ 378,350. 00
16 Contingency @ 15% 1 LS $ 56, 752. 50
$ 4351102.50
USE $ 4352000.00
file 0649A
(schedule of bid items.)ds)
c\mydocumentskproject0649 Bid Items