HomeMy WebLinkAbout2006-203 WORK ORDER NUMBER CT- 1 a c) c) 6 - a o 3
WABASSO BEACH PARK RESTORATION
This Work Order Number CT- 1 is entered into as of this 1 .1th day of
June , 200 pursuant to that certain Continuing Contract Agreement for
Professional Services entered into as of December 13 , 2005 ( "Agreement' ) , by and
between Indian River County, a political subdivision of the State of Florida ( "COUNTY" )
and Coastal Technology Corporation ( "CONSULTANT' ) .
The COUNTY has selected the Consultant to perform the professional services set
forth on Attachment 1 , attached to this Work Order and made part hereof by this reference .
The professional services will be performed by the Consultant for the fee schedule set
forth in Attachment 2 , attached to this Work Order and made a part hereof by this
reference . The Consultant will perform the professional services within the timeframe
more particularly set forth in Attachment 3 , attached to this Work Order and made a part
hereof by this reference all in accordance with the terms and provisions set forth in the
Agreement . Pursuant to paragraph 1 . 4 of the Agreement, nothing contained in any Work
Order shall conflict with the terms of the Agreement and the terms of the Agreement shall
be deemed to be incorporated in each individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Work Order as of
the date first written above .
CONSULTANT BOARD OF COUNTY COMMISSIONERS
Coastal Technology Corporation OF INDIAN RIVER COUNTY,
By:/A )0 ac� B
4ryWheePer , Vice Chairman ;
Title : President
7, [
Attest: J . K. Barton ` lerkmf Cb'S
i
By f
Deputy Clerk
Approved :
tJeph A. Baird , County Administrator
AaO6(n
ved as to form and legal sufficiency:
. Fell , Assi Cou y Attorney
Attachment 1 TO WORK ORDER CT- 1 — Professional Services
WABASSO BEACH PARK RESTORATION
1 . INTRODUCTION
In September 2004, Hurricanes Frances and Jeanne severely damaged Wabasso Beach Park
( Park); the storms destroyed the boardwalk , restroom , pavilions and portions of the parking area and
roadway within the Park. This Scope of Work entails design and permitting services to provide for
restoration of the Park (Project) . The Project entails restoration of the Park outside Florida
Department of Transportation ( FDOT) right-of-way and makes use of existing stormwater
management facilities without exceeding St. Johns River Water Management District (SJRWMD)
thresholds for permit exemption ; this Scope of Work is based upon the expectation that no SJRWMD
permits are required and that an FDOT utility permit will be required only for new water and sewer
utilities located within SR At right-of-way.
Services are proposed under the Continuing Contract Agreement for Professional Services between
COUNTY and CONSULTANT, dated December 13 , 2005. CONSULTANT shall sub-contract water
and sewer related services to Carter Associates , Inc. ( CAI ) . The following describes the work .
2. SCOPE
A. Task 1 - Design : CONSULTANT has previously completed a draft preliminary site plan "pro
bond". CONSULTANT shall provide customary preliminary and final design services for the site plan ,
and design of the boardwalk, boardwalk showers , sidewalks, paving , grading , water connection ,
sewer ( including lift station and force main ) and drainage . Scope of design for water and sewer is
based upon service to the park restroom facility with (a ) all proposed water and sewer located on
park property except for sewer force main connection to existing service line west of SR A1A, ( b )
the sewer lift station to be located landward of the VE flood zone and CCCL , and ( c) the bottom of
the lift station to be set so as to allow for potential gravity flow connections by others to adjacent
properties . For each phase of the design , CONSULTANT shall furnish three (3 ) copies of the
Design Documents to COUNTY and CONSULTANT will meet with the COUNTY to review the
Design Documents and the opinion of probable construction costs . The design will be prepared
consistent with COUNTY standards for roadways , the Florida Building Code , and the U . S . Army
Corps of Engineers Coastal Engineering Manual. The COUNTY shall provide standard details and
Technical Specifications for pavement, curbs , sidewalks , and boardwalks . The design shall be
based upon the survey by Morgan & Eklund Inc. ( M& E) dated April 25 , 2005 and titled " Boundary
and Topographic Survey of Wabasso Beach Park For Indian River County" or as may be updated
by the COUNTY or M&E .
Another COUNTY consultant shall provide for design of the restroom , pavilions , landscaping , site
lighting , and electricity. CONSULTANT shall incorporate standard building , structure , or other
component design documents prepared by COUNTY or other COUNTY consultants into the
Design Documents . CONSULTANT's responsibility with respect to such components shall be
horizontal and vertical placement and orientation on the Site and integration with components
designed by CONSULTANT. CONSULTANT shall coordinate the incorporation of such
components with COUNTY and the COUNTY's Architect. In addition , COUNTY shall provide up to
three ( 3) 30-foot soil borings and up to three ( 3) 15-foot soil borings , and one ( 1 ) geotechnical
laboratory report from a Geotechnical firm currently under continuing contract with the COUNTY.
The preliminary design drawings are to be the basis of formal permit applications by the COUNTY
under Task 2 and the CONSULTANT under Task 3. CONSULTANT shall prepare a written
description of the Project design criteria and any material changes from the draft Preliminary Site
Plan . The preliminary design shall address the site-specific design conditions and shall include
calculations , which form the basis of the Project design . As part of the preliminary design , the
CONSULTANT shall identify expected beach-dune profiles and associated wave loads for the 50
and 100 year return interval storm events for design of the boardwalk ( by CONSULTANT) and
restroom ( by others) respectively. These drawings shall illustrate the proposed site plan and
include representative cross sections with dune plantings .
The final design drawings shall be consistent with the State of Florida Department of
Environmental Protection ( FDEP) permit and the Indian River County Minor Site Plan Approval,
these drawings shall be prepared after permit issuance or otherwise upon request by the
COUNTY. Final design includes proposed Technical Specifications — suitable for bidding and
construction.
B . Task 2 - Minor Site Plan Approval : The Project is a " nonresidential' project comprised of less
than five thousand ( 5 , 000) square feet of new impervious surface area and qualifies for Minor Site
Plan approval by the Indian River County. Based upon the Preliminary Design Documents
prepared under Task 1 , the COUNTY shall prepare , submit and process Minor Site Plan Approval
as follows :
2 . 1 Pre-application Conference : COUNTY will request and hold a pre-application meeting with
Indian River County Community Development Department staff. COUNTY will prepare a
written summary of staff comments .
2 . 2 Application : COUNTY will prepare and submit a formal application for Minor Site Plan
Approval .
2 . 3 Staff Reviews : COUNTY will confer with Department staff to address staff questions ,
address staff requests for additional information , and provide for completion of the
application .
2 . 4 Technical Review Committee (TRC ): COUNTY will meet with the TRC to review the
application and address TRC comments . If required , COUNTY will formally address TRC
comments in writing and re-submit application with written response to TRC so as to obtain
TRC approval of the Site Plan . CONSULTANT will attend up to two (2) TRC meetings and
concurrently advise COUNTY as to means to address TRC comments .
C . Task 3 - FDEP Permit Application : In general , CONSULTANT shall assist the COUNTY with
preparation and processing of a formal permit application for the Project to FDEP as follows :
3 . 1 Pre-Application Conference : Following Task 2 . 1 , CONSULTANT submit the draft
Preliminary Site Plan to FDEP staff, formally request and chair a pre-application telephone
conference with representatives of the COUNTY and FDEP staff. The purpose of the pre-
application telephone conference is to ( a ) verify applicable rule provisions for FDEP
permitting of the Project, ( b ) seek FDEP staff comments regarding the proposed Project.
CONSULTANT will prepare a written summary of the results of the pre-application
telephone conference .
3 . 2 Permit Application : CONSULTANT shall prepare a formal FDEP permit application for the
Project to FDEP for submission by the COUNTY to FDEP. COUNTY will provide (a ) permit
application fees, ( b ) evidence that the Project does not contravene local building codes ,
setbacks, or Comprehensive Plan , and (c) evidence of title or ownership .
3 . 3 Permit Processing : CONSULTANT will informally confer with FDEP staff to address staff
issues and concerns and to expedite processing of the FDEP permit application . It is
expected that FDEP staff will issue two Requests for Additional Information ( RAI ) .
D . Task 4 — IRC Utility Application : In general , CONSULTANT shall assist the COUNTY with
preparation and processing of a formal permit application for the Project to Indian River County
Utilities as follows :
4 . 1 Permit Application : CONSULTANT shall prepare a formal IRC Utility permit application for
the Project to IRC Utilities for submission by the COUNTY to IRC Utilities . COUNTY will
provide (a ) permit application fees , ( b) evidence that the Project does not contravene local
building codes , setbacks , or Comprehensive Plan , and ( c) evidence of title or ownership .
4. 2 Permit Processing : CONSULTANT will informally confer with IRC Utilities staff to address
staff issues and concerns and to expedite processing of the IRC Utility permit application . It
is expected that ( a ) IRC Utilities staff will issue two Requests for Additional Information
( RAI ) and ( b ) it will be necessary to meet with IRC Utilities staff in to resolve issues
surrounding the proposed Project.
E . Task 5 — Bidding & Construction Phase Services : COASTAL TECH will address questions
from the COUNTY and Bidders and prepare Addenda , if necessary. COASTAL TECH will attend
bid opening and make recommendation to COUNTY for contract award .
6 . 1 In general , COUNTY will provide construction administration , construction phase
engineering services , and day-to-day site inspections . For sewer, as required by FDEP ,
COUNTY will retain a " professional engineer registered in Florida , to conduct on-site
observation of construction , to prepare a certification of completion of construction , and to
review record drawings for adequacy. "
3. DELIVERABLES
A. Preliminary design (shall be considered 60 percent design review submittal ) — provide
one copy each of structural and civil construction drawings together with one copy of the
technical specifications . Also provide quality control comments on the 60 percent review
submittal .
B . Final design (shall be 100 percent review submittal) — provide one copy each of all
drawings and technical specifications compatible with EJCDC 1996 General Conditions and
provide digital AutoCAD drawing files 2005 edition or later and digital word document files
of the technical specifications . Also provide one copy of the itemized opinion of probable
construction cost.
C . Conformed sets — After the project is bid but before the COUNTY awards the construction
contract, provide five signed and sealed copies of the conformed contract drawings and five
signed and sealed sets of the confirmed technical specifications . Further any revisions to
the above digital drawing and document files shall be provided .
END ATTACHMENT
ATTACHMENT 2 to WORK ORDER NO . CT- 1
WABASSO BEACH PARK RESTORATION
1 . COMPENSATION
The COUNTY agrees to pay and the CONSULTANT agrees to accept , a not-to-exceed fee
of $47 , 797 for services rendered according to Attachment 1 and the attached FEE
SCHEDULE of this WORK ORDER .
2. PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the CONSULTANT for all
authorized work completed per the FEE SCHEDULE and pertaining directly to this project
performed during the previous calendar month . The CONSULTANT shall submit invoices
monthly for services performed and expenses incurred pursuant to this Agreement during
the prior month .
The CONSULTANT shall submit duly certified invoices in duplicate to the Director of
the Public Works Department . For lump sum line items , the amount submitted shall be the
prorated amount due for all work performed to date under this phase , determined by
applying the percentage of the work completed as certified by the CONSULTANT , to the
total due for this phase of the work . The amount of the partial payment due the
CONSULTANT for the work performed to date under these phases shall be an amount
calculated in accordance with the previous paragraph , less ten percent ( 10 % ) of the
invoice amount thus determined , which shall be withheld by the COUNTY as retainage ,
and less previous payments . Per F . S . 218 . 74( 2 ) , the COUNTY will pay approved invoices
on or before the forty-fifth day after the COUNTY receives the CONSULTANT' s invoice .
Per F . S . 218 . 74( 2 ) , the ten percent ( 10 % ) retainage withheld shall be paid in full to
the CONSULTANT by the COUNTY, on or before the forty-fifth day after the date of final
acceptance of the Work by the Public Works Director.
Attachment 2 - Fee Schedule
Wabasso Beach Park Restoration
$47, 797 Mow CT Cris Jeff B Pati Jeff Lee Brooke
- Summary of Estimated Fees Principal Senior Staff Project Permit Engineer Major
May 27, 2006 - Engineer Engineer Engineer Engineer Specialist Tech Clerical Total Direct Costs Subtask Task
Task Description $ 195 $ 141 $91 $112 $96 $89 $48 Fee Amount Description Total Fee
Task 1 -,;Desi n -
$31 , 334
Arrange for Soil Borings by COUNTY 0.5 2 $322 $322
Prelimina Design - Boardwalk B Dune Vegetation 2 0. 5 34 $3, 487 $3, 487
PreliminaryDesign - Water & Sewer Services Conn. 1 3 $379 $3, 500 CAI $3, 879
PreliminaryDesign - Pavin & radio 1 0. 5 6 20 $2, 718 $2, 718
Prelimina Design - Storm Profiles & Wave Loads 2 0. 5 24 6 $3, 317 $3, 317
Prelimina Design - meeting with COUNTY 1 . 5 4 1 $789 $789
Final Design - Site Plan 1 8 2 12 $2, 351 $25 phone $2, 376
Final Design - Coordination with Architect 1 6 3 $1 , 134 $1 , 134
Final Design - Boardwalk & Dune Vegetation 2 0. 5 21 $2 , 330 $2, 330
Final Design - Water & Sewer Services Conn. 1 0. 5 1 2 $556 $2, 500 CAI $3, 056
Final Design - Pavin & grading 1 0. 5 8 16 $2, 586 $2 , 586
Final Design - Technical Secs 2 0. 5 12 $1 , 805 $1 , 805
Final Design - Oinion of Probable Costs 1 0. 5 12 12 $2, 678 $25 phone $2, 703
Final Design meet with COUNTY 1 .5 4 2 $837 $g37
Task :2 -Minor Site Plan .Approval
$1 ,804
TRC meetings - up tot meetings 4 4 6 $1 , 804 $1 , 804
Task. 3FDEP PermitApplication .
$8;603
0--Application Conference 1 2 4 2 $899 $20 phone $919
prepare 2ermitapplication 0. 5 2 20 4 $2 , 434 $ 100 reproduction $2, 534
Permit Processing - followupw / FDEPstaff 2 2 16 2 $2, 246 $50 phone $2, 296
Permit Processing - 2 RAIs 2 4 20 2 $2, 854 $2 , 854
Task 4" IRC Ltilit Application ' - -
$3; 134
FDEP/FDOTPermitApplication 1 1 $144 $ 144
FDEP/FDOTPermit Processing 2 1 $240 $2, 750 CAI $2, 990
�&
Task 5 'Biddin Construction Phase Services $2,923
Bidder's Questions and Addenda 4 6 2 _ $1 , 548 $25 phone $1 , 573
Bid Evaluation & Contact Aw and 2 6 2 2 $1 , 350 $ 1 , 350
Total Hours : 33 4 24 96 73 123 19 372
Total : - $s a3s ' $5sa $2, 184 $1o;iaz $a,00s . $1osa� .. $s1z .$38802 $8; 995 - - $47, 797 $47, 797
Attachment 3 — Timeframe
WABASSO BEACH PARK RESTORATION
Estimated Time
for Completion May 27 , 2006
( # of days from NTP) Task Description
Task 1 - .Desi n
42 1 . 1 Arrange for Soil Borings by COUNTY
1 . 1 Preliminary Design - Boardwalk & Dune Vegetation
1 . 1 Preliminary Design - Water & Sewer Services Conn .
1 . 1 Preliminary Design - Paving & grading
1 . 1 Prelimina Design - Storm Profiles & Wave Loads
1 . 1 Preliminary Design - meeting with COUNTY
210 1 . 2 Final Design - Site Plan
- 1 . 2 Final Design - Coordination with Architect
1 . 2 Final Design - Boardwalk & Dune Vegetation
1 . 2 Final Design - Water & Sewer Services Conn.
1 . 2 Final Desi in - Paving & grading
1 . 2 Final Design - Technical Specs
03. 11D,
esi n - 0 inion of Probable Costs
al Desi n - meet with COUNTY
te. Plan A " royal
as scheduled C meetin s - u to 2 meetin s
mitApplication - - -
14 A litiCfce
56 prepare permit application
3. 3 Permit Processing - follow up w / FDEPstaff
189 3. 3 Permit Processing - 2 RAIs
Task 41RC Utility Application
49 4. 1 FDEP/FDOTPermitApplication
139 4. 2 FDEP/FDOTPermit Processing
Task 5 Bidding & Construction Phase Services
231 5. 1 Bidder's Questions and Addenda
252 5. 2 Bid Evaluation & Contact Aw and