Board of County Commissioners /43
0
1801 27th Street
Vero Beach , Florida 32960C�/�'
Telephone : (772 ) 567- 8000 FAX : (772) - 778-9391
Surveying and Mapping Services
for
Old Dixie Highway Right-of-Way Mapping
From Oslo Road North to East Bound SR 60
AMENDMENT NO . 1 to WORK ORDER NO . 1 ( Engineering / Surveying )
FOR
FOR PROFESSIONAL SURVEYING AND MAPPING SERVICES AGREEMENT
FOR ANNUAL LAND SURVEYING AND MAPPING /GIS SERVICES
CONTRACT RFQ No . 2011009
WITH
CARTER ASSOCIATES , INC .
All services performed under this contract shall be supervised and certified by a licensed
Professional Surveyor and Mapper ( PSM ) registered with the State of Florida and staff
employed directly with your firm .
Scope of Services
All work shall be performed on a unit price basis in accordance with the attached
Scope of
Services ( Exhibit A) dated October 17 , 2011 and shall comply with Standards enumerated in the
ANNUAL LAND SURVEYING AND MAPPING/GIS SERVICES CONTRACT , RFQ 2011009
WITH CARTER ASSOCIATES , INC . Effective Date : October 5 , 2010 .
Minimum Specification Requirements as follows :
Right-of-Way Mapping
• Additional Field and Office tasks needed to accurately prepare Right- of-Way map for
that portion of Old Dixie Highway lying between Oslo Road North to East Bound SR 60 .
All work shall also comply with the current Florida Minimum Technical Standards .
COMPENSATION .
The COUNTY agrees to pay , and the Surveying and Mapping Professional agrees to accept ,
a fee for services rendered according to the " Scope of Services " identified in the attached
EXHIBIT "A" Fee Schedule and Man Hours .
A Lump Sum Amount of : $ 8 , 121 , 50 to be paid on a unit price basis for actual work performed in
accordance with the schedule of services and fees set forth in Exhibit A .
F :APublic Works\FNGINITRING DIVISION IT0.11 CTS\ 1101 -Old Dixie I hay ROW Map Oslo to SR 60\Admim\agenda items\BCC agenda
Carter Amendment No . I to WO No . 1 10-20- 1 I .doc
Amendment No . 1 to Work Order No . 1
Old Dixie highway - Oslo Road to SR 60
Surveying and Mapping
IRC Project No. 1101
TIME FOR COMPLETION
The Task will be completed within 30 days of acceptance of Amendment No . 1 to Work Order
No . 1 , IRC Project No . 1101 ,
IN WITNESS HEREOF the parties hereto have executed these presents this lst day
J�,�,t � U M N1IS•s 0
of November 2011 .
OWNER CARTER ASSOCIATES, INC .
to
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY , FLORIDA
9 •
C Mp. Y„ 4. tlOM �p
(Signature) ('Signtltiire) John H . Blum , Treasurer
Bob Solari , Chairman 17 emps
Approved by BCC 11 / 1 / 11 . . Witnessed by :
ATTEST :
Jeffrey K . Barton , Clerk of Circuit Court
r ! i
ll- aw-i
Deputy Clerk (Printed name)
Approv as to lForand Leg Suffi y :
Alan S. Polackwlch , Sr. , County Attorney
)o4seph A aird , C unty Administrat r
F :APublic Works\FNGINFERING DIVISION PR0JFCI1S\ I 101 -Old Dixie FkNv ROW Map oslo to SR 60\Admin\agenda items\ BCC aeenda
Carter Amendment No . I to WO No . 1 10-20- 1 I . doc
CARTER ASSOCIATES , INC .
CONSULTING ENGINEERS AND LAND SURVEYORS
1708 21 ,t SIREE I' • CERO IIFACII , FLORIDA 32960- 3472 • 772 - 562-4191 • 772 - 562 -7 ISO ( FAX )
FRANK S . CUCCI ; kESL, I' S . M .
JOHN 11 , BLUM , P . , PRINCIPAL CLINTON J . RAILIES , P . E.
L1 xY I I C IPIISTEVE D SN0136kC [ R P . L .
P41
}�? I CIP A AL BENJAMIN D. SPLFD 1 L.
MAR INE,IIN E . ( AII .: ]' . . M , irowh :uu to she Firm
DF. I .lif T L' . n .� , C,0 [1s0 ( :1111 lo the Firm
INDIAN RIVER C . T '(
ENGINEE(Nt P,eP4\ 9N
Memo
Reference : Old Dixie Highway Right- of-Way Mapping
Oslo Road to S . R . 60 Highway, Indian River County Project No . 1101 ,
W . O . No . l (Right-of- Way Map ), CAI Project No . 11 - 2045
Dear Mr . Kafer,
Thank you for your consideration and review of our request for additional monies for the
Old Dixie Highway Mapping project .
Please note below , a breakdown comparison of tasks with costs of the project items for
approved time estimated to additional cost overrun .
1 . Item no . II of the proposal and project referenced :
"Locate property corners, sectional corners, right-of--way control , centerline control ,
centerline intersections , side street property corners , edge of pavement, buildings
structures and major miscellaneous structures within 25 ' of the right-of-way . . . "
Approved contractual hours Additional time%xpense
and cost for Item 11 required for Item 11
Surveyor I Surveyor 1
4 hours @ $ 140 . 00/ hr . . . . . . . . . . . . $ 560 . 00 0 hours @ $ 140 . 00/ hr . . . . . . .
. . . . . . . . . . . $ 00 . 00
Surveyor 11 Surveyor 11
40 hours @ $ 125 . 00/hr . . . . . . . $ 51000 . 00 6 . 8 hours @ $ 125 . 00/hr . . . . . . . . . . . . .
. $ 850 . 00
Survey Crew ( 3 Men / 2 Units ) Survey Crew ( 3 Men / 2 Units )
240 hours @ $ 150 . 00/hr . . . . . $ 36 , 000 . 00 16 hours @ $ 150 . 00/hr . . . . . . . . . . . $ 2400 .
00
Geodetic processing Geodetic processing
30 hours @ $ 140/hr . . . . . . . . . . . $ 4 , 200 , 00 1 . 7 hours @ $ 140/hr . . . . . . . . .
. . . . . . . . $ 238 . 00
Total I I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 45 , 760 . 00 Total ll. . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $ 3y488, 00
Scrvu-1fi Honda
S : AP\ 11 -204S IRC O1dDixie\Docs\Notes\Letter of explanation add- scoperevised . doc AI Since f911
2 . Item no . III of the proposal and project referenced :
"Data reduction/drafting of right-of-way location maps in AutoCAD format"
Approved contractual hours Additional time%xpense
and cost for Item III required for Item 111
Surveyor I Surveyor I
2 hours @ $ 140 . 00/ hr . . . . . . . . $ 280 . 00 0 hours @ $ 140 . 00/ hr . . . . . . . . . . . .
. . . . . . $ 00 . 00
Surveyor II Surveyor II
16 hours @ $ 125 . 00/hr . . . . $ 2 , 000 . 00 9 . 4 hours @ $ 125 . 00/hr . . . . . . . . . . . $ 11175
. 00
CAD Technician I CAD Technician 1
160 hours @ $ 80 . 00/hr . . . . 12 , 800 . 00 16 . 2 hours @ $ 80 . 00/hr . . . . . . . . . . . . $ 1 , 296
. 00
Total III . . . . . . . . . . . . . . . . . . . . . . . $ 15 , 080 . 00 Total Ill . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . $ 2, 471 . 00
3 . Item no . IV of the proposal and project referenced :
" Locate property corners, sectional comers , right-of-way control , CL control , CL intersections,
side- street property corners , to re-establish/verify existing right-of--way of Old Dixie Highway
(Plat Book 13 , Page 45 ) to Oslo Road/9th Street right-of-way from the west line of Section 19
and 30 , Township 33 South , Range 40 East to the Florida East Coast Railway right-of--way"
Approved contractual hours Additional time%xpense
and cost for Item IV required for Item 111
Surveyor I Surveyor II
2 hours @ $ 140 . 00/ hr . . . . . . . . $ 280 . 00 9 . 7 hours @ $ 125 . 00/hr . . . . . . . . . . .
. $ 11212 . 50
Survey Crew ( 3 Men / 2 Units ) Survey Crew ( 3 Men / 2 Units )
24 hours @ $ 150 . 00/hr . . . . $ 3 , 600 . 00 5 . 4 hours @ $ 150 . 00/hr . I . . . . . . . . . . . . . .
$ 810 . 00
Geodetic processing Geodetic processing
3 hours @ $ 140/hr . . . . . . . . . . . $ 420 . 00 1 . 0 hours @ $ 140/hr . . . . . . . . . . .
. . . . . . . $ 140 . 00
Total IV . . . . . . . . . . . . . . . . . . . . . . . . . $ 4 , 300 . 00 Total IV. . . . 1 . . . I .
I . A . . . . . . . . . . . . . 0 . . 0 . 0 . I IS 2, 162 . 50
Total additional expense . . . . . . . . . . $8, 121 . 50
The above cost overrun for each item is a partial cost for the extra time and work involved to
complete the tasks .
Be assured that Carter Associates , Inc . will continue to complete this project to the
highest standards with full attention . Your assistance in this matter is greatly appreciated . If you
have any questions, please do not hesitate to call .
Respectfully,
Frank S . C ccurese , P . S . M .