No . 1
DATE OF ISSUANCE : 9- 17- 12 EFFECTIVE DATE :
OWNER : Indian River County
CONTRACTOR A . M . Construction Group Inc.
Contract : Bid No . : 2012042
Project : South Regional Wastewater Treatment Facility Headworks Rehabiliation
OWNER's Contract No . ENGINEER's Contract No .
ENGINEER
You are directed to make the following changes in the Contract Documents :
Description : Replace 5 (five) Pipe support Pedestals , Replace 2 (two) 16 inch Diameter Knife
Valves , Repair Headworks Odor Control Tower and Blower Base , and Extend Chlorine Fill
Lines
Reason for Change Order:
Facility Inspection revealed several components that were noted to be in dilapidated
condition and need repair
Attachments : ( List documents supporting change)
Attachment # 1 (A . M . Construction Group Proposal)
Attachment # 2 (Pictures of Pipe Pedestals , Knife Valves , and Headworks Odor Control
Tower and Blower Base
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES
Description Amount Description Time
Original Contract Price $89, 177 . 43 Original Contract Time: (days or dates)
Substantial Completion : 90
Final Completion : 105
Net Increase ( Decrease) from previous $0 Net change from previous Change
Change Orders No . 0 to 0 : Orders No. 0 to 0 : (days)
Substantial Completion : 90
Final Completion : 105
Contract Price prior to this Change $89 . 177 . 43 I Contract Time prior to this Change
Order: Order: (days or dates)
Substantial Completion : 90
Final Completion : 105
Net increase (decrease) of this Change $27. 200 . 00 Net increase (decrease) this
Order: Change Order: (days or dates)
Substantial Completwrr:� ' ��
Finalm ,ICtwhY ' �
Contract Price with all approved $ 116 . 377 .43 Contract Time with all JVehf �a
TM. a
Change Orders : Change Orders : �, � rlaya dgtes)
SubstaomQlon : s0
F m le , : ..%
il
ACCEPTED : RECOMMENDED : �QVE. •rm mikee <"
Abel Mendez Aaron Bowles �
0 k -
By : y: Bv : �.
CONTRACTOR (Signature) ENGINEER (Signature) OWNER: ateirti)
Gary C . c f eefer , Chairman
Date : 9- 17- 12 Date : 9- 17- 12 Date : r)riwpher 16 , 2.pj
Agenda - Change Order No 1 South WWTF Headworks Change Order with AM Construction Group Inc October 2012 Form
00942 - 1
CADocuments and Settings\acosner\Local Settings\Temporary Internet Files\OLI(71 Wgenda - Change Order No 1 South W WTF Headworks Change Order with AM
Construction Group Inc October 2012 Fono.doc Rev. 05/01
t
12689 — 164h Court North
Jupiter, FL 33478
Fax : (561 ) 748-9203
Office (561 ) 262-7874 S
Cell : 561 262-7833 �' lOri Group., Inc .
Email : amconstructiongbellsouth.net DATE : September 17, 2012
LICENSED & INSURED : REVISED
General & Plumbing Contractor
AM Construction Group, Inc .
CGC 1504453 QB21671 CFC 1425723
AME / ADDRESS ,
Terry Southard
Indian River County Utilities
Operations Complex
350 41St Street
Vero Beach, FL 32967
Vero Beach Headworks C.O. Proposal
SCOPE OF WORK.
1).Replacement of additional viae pedestals
1 . Demo 5 existing pipe supports .
2 . Supply & install 5 additional galvanized dipped pipe" supports that need replacing.
3 . All 316 S . S . hardware, grout & epoxy.
4 . Equipment, tools & labor.
5 . All insurances.
TOTAL PRICE .
Two thousand, five hundred dollars and no cents. 2$ ,500.00
2).Replacement of (2) - 16" Knife valves
1 . Demo 2 existing 16" knife valves & DIP couplings .
2 . Install 2 - 16" FNW S . S . lined knife gate valves & couplings .
3 . Materials & labor.
4 . All insurances .
TOTAL PRICE .
Fifteen thousand, nine hundred and fifty dollars and no cents. 15$ ,950.00
Deduct: To use Dezurik Knife valves (Additional 4 week lead time more
than quoted FNW- S . S. lined knife valves) . $ 1 ,400.00
1
- I
3).Headworks Odor control tower repairs :
1 . Clean & prep odor control tower.
2 . Cut out, re-fiberglass or re-wet damaged fiberglass matting with vinylester resin .
3 . Gel-coat odor control tower.
4 . Remove blower, motor and frame .
5 . Repair existing frame base with S . S . angle .
6 . Repair/patch existing concrete pump pad.
7 . Install blower with S . S . anchors .
8 . Materials & labor.
9 . All insurances .
TOTAL PRICE :
Nine thousand, seven hundred dollars and no cents $9.700.00
4).Extend chlorine fill lines.
1 . Extend 2 — 2" chlorine fill lines to corner of slab to accommodate fill truck.
2 . 40 ' of 2" sch. 80 PVC pipe, S . S . uni-strut, S . S . anchors, S. S . pipe support.
3 . All materials & labor.
4 . All insurances.
TOTAL PRICE .
Four hundred fifty dollars and no cents $450.00
EXCLUDED : Electrical & anything not in scope of work.
If this proposal is acceptable to you, please sign below and return to AM
Construction Group, Inc., and keep the attached copy for your records.
Customer Signature & Printed Name