HomeMy WebLinkAbout2010-130 v
i � - J • i
dvf � � 13o
TASK ORDER NO . 1
INDIAN RIVER COUNTY
AND
CAROLLO ENGINEERS , A Professional Corporation
This Task Order is issued by the OWNER and accepted by ENGINEER pursuant to the mutual
promises , covenants and conditions contained in the Agreement between the above named
parties dated the 1 st day of May 2007 , in connection with the Continuing Contract Agreement
for Professional Services .
PURPOSE
The purpose of this Task Order is to describe the Scope of Services for the Evaluation Related
to Scaling and Corrosion Considerations at the OWNER 7s Reverse Osmosis ( RO ) treatment
plant.
The overall goal of the study is to perform evaluations and develop suitable recommendations
for the treatment process/operations to address scaling and corrosion considerations . These
evaluations will be achieved through specific data analysis , chemistry modeling , and sampling .
ENGINEER ' S SERVICES
ENGINEER ' s services include the following two tasks to complete this assignment . These tasks
are discussed in detail below.
• Task 1 — Reviews and Evaluation
• Task 2 — Report
TASK 1 . REVIEWS AND EVALUATION
The data reviews and evaluation will focus on specific evaluations of water quality related to
scaling/corrosion , chemistry modeling using RTW model , and specific sampling and analysis for
water quality related to scaling/corrosion . In case a coupon study is one of the
recommendations based on the results from these evaluations , its scope will be separately and
subsequently developed in another task order.
An interim letter memorandum will be prepared and submitted at the end of Subtask 1 . 2 ,
summarizing the results of the chemistry modeling , and including initial recommendations on
changes to treatment process/operations . These initial results and recommendations will be
enhanced and finalized in the project report that will be developed in Task 2 , after completion of
the sampling and analysis in Task 1 . 3 . The associated subtasks are listed below .
Subtask 1 . 1 Water Quality Related to Scaling/Corrosion
a . Obtain/compile pertinent data (for last 1 -2 years ) on water quality related to
scaling /corrosion
b . Analyze water quality data related to scaling for last 1 -2 years
c . Analyze water quality data related to corrosion for last 1 -2 years
HAClienAIndian River County\ContracAIRC 2010-T01 _Fn1 .doc 1
. p
Subtask 1 . 2 Chemistry Modeling
a . Evaluate scaling/corrosion indices under current operation
b . Determine conditions for recommended operation
c . Draft letter memorandum summarizing modeling results
d . Final letter memorandum summarizing modeling results
Subtask 1 . 3 Sampling and Analysis
a . Sampling protocol
b . Sampling and coordination
c . Sample Analysis
d . Deposits/scale sampling and coordination
e . Deposits/scale analysis
Task 1 Deliverables : Draft Letter Memorandum ( electronic copy PDF format )
Final Letter Memorandum ( electronic copy PDF format )
TASK 2 . REPORT
Subtask 2 . 1 . Draft Report
At the completion of the data reviews and evaluation (Task 1 ) , ENGINEER will produce a Draft
Report summarizing and documenting the results of the evaluations and including suitable
recommendations , and distribute the draft report to the OWNER for review and approval .
Subtask 2 .2 . Meeting to discuss draft report ( Prep/Attend/ Distribute Minutes )
After the submission of the draft report, ENGINEER will meet with OWNER to discuss the
results and recommendations included in the draft report . OWNER' s comments will be received ,
and incorporated in the finalization of the report .
Subtask 2 . 3. Final Report
The ENGINEER will revise the Draft Report as appropriate based on the OWNER ' s comments
received , and submit a Final Report .
Task 2 Deliverables : Draft Report ( 4 copies )
Final Report ( 4 copies )
TIME OF PERFORMANCE
Completion of the services outlined above will be provided as needed during the project . The
overall schedule for the preparation of the Report is estimated to be fourteen ( 14) weeks after .
receipt of the Notice to Proceed ( NTP ) . The estimated timeline is described below .
• Task 1 . 1 and 1 . 2 of the study will delivered to the OWNER within seven weeks of
receipt of the NTP .
• Task 1 . 3 and Task 2 of the study will be delivered to the OWNER within fourteen weeks
of receipt of the NTP .
H :1Clientllndian River County\ContracAIRC 2010-T01 _Fn1 .doc 2
1
PAYMENT
OWNER shall pay ENGINEER for ENGINEER 's Services , as delineated above , rendered under
a lump sum fee of $ 39 , 545 , plus approved expenses .
Reimbursable Expenses . OWNER shall pay ENGINEER the actual costs of all approved
Reimbursable Expenses incurred in connection with all ENGINEER's Services , as delineated
above , including those of independent associates and consultants employed by ENGINEER.
EFFECTIVE DATE
This Task Order No . 1 is effective as of the "day of April , 2010 .
IN WITNESS WHEREOF , duly authorized representatives of the OWNER and of the
ENGINEER have executed this Task Order No . 1 evidencing its issuance by OWNER and
acceptance by ENGINEER .
CAROLLO ENGINEERS , BOARD OF COUNTY COMMISSIONERS OF
A Professional Corporation INDIAN RIVER COUNTY
Accepted this 18 day of May 2010
Rob S . Cushing , PhD , PE , DEE Peter D . O ' Bryan ,c• ° ° ° °�'.?*:�iFI
Partner Chairman 0 : •'
. • 5p
o e ,
8
e � a
By : �/�� Attest : J . K . Barton , Clerk of Court ':•:, c
Partner
.#too
Off'•
By : - R �OUNTY; ��•
Deputy rk
proved : May 18 , 2010
J ' ephA . B ird , County Administra
proved as to form and legal sufficiency:
r .-�
Alan S . Polackwic , County Attorney
HACIientUndian River County\Contract\ IRC 2010-T01 _Fnl .doc 3
4/28/2010 Indian River County Carollo Engineers , P .C .
Evaluation Related to Scaling and Corrosion Considerations Engineering Fee Estimate
TOTAL TOTAL SUB SUB/ TOTAL TOTAL
` LABOR LABOR MARKUP - DIRECT PECE : ODC'S COST
ITEM DESCRIPTION HOURS COSTS Extemal ON SUBS COSTS ON +
`Laboratory DL His PECE
(HRS) ($$$) ($$$) ($$$) ($$$) .
10 % $9 . 00
Task 1 - Reviews and Evaluations
1 . 1 Water Quality Related to Scaling/Corrosion
a. Obtain and compile pertinent data ( last 1 -2 years) 2 $310 $0 $0 $0 $ 18 $ 18 $328
b. Analyze water quality data related to scaling (last 1 -2 years) 20 $22750 $0 $0 $0 $ 180 $ 180
$2, 930
c. Analyze water quality data related to corrosion (last 1 -2 years) 8 $ 11100 $0 $0 $0 $ 72 $72 $ 1
, 172
1 .2 Chemistry Modeling
a. Evaluate scaling/corrosion indices under current operation 15 $29360 $0 $0 $0 $ 135 $ 135 $2,495
b. Determine conditions for recommended operation 15 $2 , 360 $0 $ 0 $0 $ 135 $ 135 $2,495
c. Draft letter memo summarizing modeling results 19 $ 2 , 680 $0 $0 $0 $ 171 $ 171 $2;851
d. Final letter memo summarizing modeling results 10 $ 12350 $0 $ 0 $0 $ 90 $90 - $.11440
1 .3 Sampling and Analysis
a. Sampling protocol 10 $ 1 ,460 $0 $0 $0 $ 90 $90 $ 1 ,550
b. Sampling and coordination* 4 $630 $ 1 , 200 $ 120 $ 150 $ 36 $ 1 , 506 $2, 136
c. Sample analysis 15 $2 , 250 $0 $0 $0 $ 135 $ 135 - $2, 385
d. Deposits/scale sampling and coordination* 6 $880 $ 1 , 000 $ 100 $ 150 $ 54 $ 1 , 304 $2, 184
e. Deposits/scale analysis 12 $ 12760 $0 $0 $0 $ 108 $ 108 $1 ,868
136 $ 199890 $2,200 $220 $300 $ 17224 $3,944 $231834
SUBTOTAL
Task 2 - Report
2. 1 Draft report 57 $7 , 580 $0 $ 0 $0 $ 513 $ 513 581093
2.2 Meeting to discuss draft report ( Prep/Attend/Distribute Minutes) 28 $ 5 , 240 $0 $0 $0 $252 $252
$5,492
2.3 Final report 14 $2 , 000 $0 $ 0 $0 $ 126 $ 126 $2„126
99 $ 14,820 $0 $0 $0 $891 $891 $ 15,711
SUBTOTAL
-
Total Engineering Services 235
$34,710 $21200 $220 $300 $2 , 115 $4,835 $397545
PECE = Project Equipment and Communication Expenses
* Overall sampling direction , oversight, and coordination by Carollo ; field sample collection to be performed by County operations staff