CHANGE ORDER NO. 001
to WORK ORDER NO. L4
0.ftL1o(It I
g. F.
Q011- 0!8
DATE OFISSUANCE: February 1, 2011EFFECTIVE DATE February 1., 2011
OWNER: Indian River County
CONSULTANT/CONTRACTOR: G.K. Environmental, Inc.
Project: EGRET MARSH STORMWATER PARK
OWNER's Project No. 0430
ENGINEER: Indian River County Stormwater Division
The following items are included in Change Order No. 1:
1. Obtain soil samples and analyze for pH and other pertinent soil parameters. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $275.00
2. Increase the diameter of the planting holes for all trees to 36" diameter. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $290.00
3. Purchase additional topsoil for backfilling the tree planting holes. See Attachment A
for additional information.
ADDITION TO THE CONTRACT PRICE = $654.00
4. Purchase polymer and provide additional labor to over -excavate the tree planting
holes, mix topsoil and polymer, and place the mix into the planting holes. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $2,490.00
5. Revise tree quantities as follows:
Tree Species
Revised
Contract
Quantity
Bald Cypress
12
Live Oak
115
Slash Pines
40
Maple
51
Water Oak
0
TOTAL
218
DEDUCTION FROM THE CONTRACT PRICE = ($3,821.00)
Change Order No. 001
Page 1
FAPublic Works\KeithM\Stormwater Projects\Egret Marsh Construction\Project Closeout\GK Environmental\Change Order #1.doc
CHANGE ORDER NO. 001
to WORK ORDER NO, L-1
DATE OF ISSUANCE: February 1, 2011EFFECTIVE DATE February 1, 2011
OWNER: Indian River County
CONSULTANT/CONTRACTOR: G.K. Environmental, Inc.
Project: EGRET MARSH STORMWATER PARK
OWNER's Project No. 0430
ENGINEER: Indian River County Stormwater Division
The following items are included in Change Order No. 1:
1. Obtain soil samples and analyze for pH and other pertinent soil parameters. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $275.00
2. Increase the diameter of the planting holes for all trees to 36" diameter. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $290.00
3. Purchase additional topsoil for backfilling the tree planting holes. See Attachment A
for additional information.
ADDITION TO THE CONTRACT PRICE = $654.00
4. Purchase polymer and provide additional labor to over -excavate the tree planting
holes, mix topsoil and polymer, and place the mix into the planting holes. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $2,490.00
5. Revise tree quantities as follows:
Tree Species
Revised
Contract
Quantity
Bald Cypress
12
Live Oak
115
Slash Pines
40
Maple
51
Water Oak
0
TOTAL
218
DEDUCTION FROM THE CONTRACT PRICE = ($3,821.00)
Change Order No. 001
Page 1
FAPublic Works\KeithM\Stormwater Projects\Egret Marsh Construction\Project Closeout\GK Environmental\Change Order #1.doc
CHANGE ORDER NO, 001
to WORK ORDER NO. L-1
CHANGE IN CONTRACT PRICE
Description
Amount
Original Contract Price
$2437508.20
Net change from previous Change Orders:
$0.00
Contract Price prior to this Change Order:
$243,508.20
Net decrease of this Change Order:
$112.00
Contract Price with all approved Change
Orders:
$243,396.20
C4�NSMLTANJ (Signku
G.K. Environmental, Inc.
George R. Kulczycki,
President
Date: /— /4.-20//
RECOMMEN
ENGINEER (Signature)
Keith McCully, P.E., Indian
River County Stormwater
Engineering Division
Date: I -14-2011
APPROVED:
By.,a,/
OWNER: Bob Solari, Chairman,
Board of County Commissioners
Date: 2/1/11
P
Change Order No. 001
Page 2
FAPublic Works\KeithM\Stormwater Projects\Egret Marsh Construction\Project Closeout\GK Environmental\Change Order #1.doc
CHANGE ORDER NO, 001
to WORK ORDER NO. L-1
CHANGE IN CONTRACT PRICE
Description
Amount
Original Contract Price
$2437508.20
Net change from previous Change Orders:
$0.00
Contract Price prior to this Change Order:
$243,508.20
Net decrease of this Change Order:
$112.00
Contract Price with all approved Change
Orders:
$243,396.20
C4�NSMLTANJ (Signku
G.K. Environmental, Inc.
George R. Kulczycki,
President
Date: /— /4.-20//
RECOMMEN
ENGINEER (Signature)
Keith McCully, P.E., Indian
River County Stormwater
Engineering Division
Date: I -14-2011
APPROVED:
By.,a,/
OWNER: Bob Solari, Chairman,
Board of County Commissioners
Date: 2/1/11
P
Change Order No. 001
Page 2
FAPublic Works\KeithM\Stormwater Projects\Egret Marsh Construction\Project Closeout\GK Environmental\Change Order #1.doc
G. K. ENVIRONMENTAL, INC.
Environmental Consulting
GEORGE R. KULCZYCKI, CFC. CFS
155 McKee Lane
Vero Beach. FL 32960
Office 772-567-9129
Cell 772-913-0294
Fax 772-567-6245
gke(c�me.com
ATTACHMENT A TO CHANGE ORDER NO. 1 to
WORK ORDER NO. L-1
January 11, 2011
Mr. Keith McCully
Stormwater Engineer
Indian River County
1801 27th Street (Building A)
Vero Beach, Florida 32960
RE: INVOICE — EGRET MARSH STORMWATER PARK
Work Order No. L-1
Soil Amendment Change Order
Invoice # 020
Dear Keith,
Per our discussion, due to the very poor soils for the above referenced site and
poor growth responses to previously installed trees by others, we chose to modify the
species of trees and tree counts based upon the existing high soil Ph and rock rubble soil
conditions left over from the historic pit operations.
This modification allowed us to dig much larger holes for the trees than were
previously dug by others, and add a mixture of top soil and a Polyacylamide polymer, in
order to maintain soil moisture and provide additional good soil for tree growth. This soil
amendment will provide a much better chance for tree survival and growth in these poor
soil conditions.
The cost breakdown to incorporate these soil amendments into the project are
outlined below:
a) Obtain 3 soils samples onsite and mail to the University of Florida for analysis.
Receive soils report from OF and review with OF staff.. I I ......... $ 275.00
G. K. ENVIRONMENTAL, INC.
Environmental Consulting
GEORGE R. KULCZYCKI, CFC. CFS
155 McKee Lane
Vero Beach. FL 32960
Office 772-567-9129
Cell 772-913-0294
Fax 772-567-6245
gke(c�me.com
ATTACHMENT A TO CHANGE ORDER NO. 1 to
WORK ORDER NO. L-1
January 11, 2011
Mr. Keith McCully
Stormwater Engineer
Indian River County
1801 27th Street (Building A)
Vero Beach, Florida 32960
RE: INVOICE — EGRET MARSH STORMWATER PARK
Work Order No. L-1
Soil Amendment Change Order
Invoice # 020
Dear Keith,
Per our discussion, due to the very poor soils for the above referenced site and
poor growth responses to previously installed trees by others, we chose to modify the
species of trees and tree counts based upon the existing high soil Ph and rock rubble soil
conditions left over from the historic pit operations.
This modification allowed us to dig much larger holes for the trees than were
previously dug by others, and add a mixture of top soil and a Polyacylamide polymer, in
order to maintain soil moisture and provide additional good soil for tree growth. This soil
amendment will provide a much better chance for tree survival and growth in these poor
soil conditions.
The cost breakdown to incorporate these soil amendments into the project are
outlined below:
a) Obtain 3 soils samples onsite and mail to the University of Florida for analysis.
Receive soils report from OF and review with OF staff.. I I ......... $ 275.00
b) Obtain a large 36 inch tree auger attachment to excavate the 218 larger holes...
.......................................................... 0 0 0 0 .... $ 290.00
C) Purchase 436 bags of top soil for each hole ........................ $ 654.00
d) Additional labor costs to over excavate holes, mix polymer and top soil, and
install soil amendments to enlarged holes for each tree planting......... $ 2,490.00
TOTAL Cost for Soil Amendment for 218 trees. .
($17.00 per tree)
If you have any questions, please do not hesitate to give me a call.
Sincerely,
(�wrgiel2. Kuicl3yckdv
$ 3,709.00
George R. Kulczycki, President
Principal Ecologist
b) Obtain a large 36 inch tree auger attachment to excavate the 218 larger holes...
.......................................................... 0 0 0 0 .... $ 290.00
C) Purchase 436 bags of top soil for each hole ........................ $ 654.00
d) Additional labor costs to over excavate holes, mix polymer and top soil, and
install soil amendments to enlarged holes for each tree planting......... $ 2,490.00
TOTAL Cost for Soil Amendment for 218 trees. .
($17.00 per tree)
If you have any questions, please do not hesitate to give me a call.
Sincerely,
(�wrgiel2. Kuicl3yckdv
$ 3,709.00
George R. Kulczycki, President
Principal Ecologist
p
CHANGE ORDER NO. 001
to WORK ORDER NO. L4
0.ftL1o(It I
g. F.
Q011- 0!8
DATE OFISSUANCE: February 1, 2011EFFECTIVE DATE February 1., 2011
OWNER: Indian River County
CONSULTANT/CONTRACTOR: G.K. Environmental, Inc.
Project: EGRET MARSH STORMWATER PARK
OWNER's Project No. 0430
ENGINEER: Indian River County Stormwater Division
The following items are included in Change Order No. 1:
1. Obtain soil samples and analyze for pH and other pertinent soil parameters. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $275.00
2. Increase the diameter of the planting holes for all trees to 36" diameter. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $290.00
3. Purchase additional topsoil for backfilling the tree planting holes. See Attachment A
for additional information.
ADDITION TO THE CONTRACT PRICE = $654.00
4. Purchase polymer and provide additional labor to over -excavate the tree planting
holes, mix topsoil and polymer, and place the mix into the planting holes. See
Attachment A for additional information.
ADDITION TO THE CONTRACT PRICE = $2,490.00
5. Revise tree quantities as follows:
Tree Species
Revised
Contract
Quantity
Bald Cypress
12
Live Oak
115
Slash Pines
40
Maple
51
Water Oak
0
TOTAL
218
DEDUCTION FROM THE CONTRACT PRICE = ($3,821.00)