FORMER GIFFORD ROAD LANDFILL
AMENDMENT NO . 1
to
WORK ORDER NO . 29
FOR
Continuing Contract Agreement for Professional Services
WITH
Geosyntec Consultants , Inc .
This Amendment No . 1 to Work Order No . 29 is entered into pursuant to the Continuing
Contract Agreement for Professional Services entered into August 10 , 2004 and amended July
24 , 2007 ( as so amended , the "Agreement" ) , by and between Indian River County Board of
County Commissioners ( " COUNTY" ) on the same terms as the existing Agreement , as
extended , between the Indian River County Solid Waste Disposal District , a dependent special
district of Indian River County , Florida , ( " DISTRICT' ) AND Geosyntec Consultants , Inc . , a
Florida Corporation ( " CONSULTANT' ) .
The COUNTY has selected the CONSULTANT to perform the professional services set forth on
Attachment A , attached to this Amendment No . 1 to Work Order No . 29 and made part hereof
by this reference . The professional services will be performed by the CONSULTANT for the fee
schedule set forth in Attachment B , attached to this Amendment No . 1 to Work Order No . 29
and made a part hereof by this reference . The CONSULTANT will perform the professional
services within the Schedule more particularly set forth in Attachment A , attached to this
Amendment No . 1 to Work Order No . 29 and made a part hereof by this reference all in
accordance with the terms and provisions set forth in the Agreement . Pursuant to paragraph
1 . 4 of the Agreement , nothing contained in any Work Order or Amendment to Work Order shall
conflict with the terms of the Agreement and terms of the Agreement shall be deemed to be
incorporated in each individual Work Order or Amendment to Work Order as if fully set forth
herein .
COMPENSATION .
The COUNTY agrees to pay , and the CONSULTANT agrees to accept , a fee for services
rendered according to the " Scope of Services " identified in Attachment A and Exhibit 1 .
ccizi 1018ixa1 1016 .doc
Page 2
AMENDMENT NO , 1 TO WO #29 — Geosyntec Consultants , Inc .
Former Gifford Road Landfill
A Not-to- Exceed Amount of: $ 134 , 943 . 00 to be paid on a unit price basis for actual work
performed in accordance with the schedule of services and fees set forth in Attachment A and
Exhibit 1 .
IN WITNESS HEREOF the parties hereto have executed these presents
This 17th day of May , 2011 .
OWNER GEOSYNTEC CONSULTANTS, INC .
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY, FLORIDA
772300we I, Of 4AJOfI o"
(Signature) a°��0 �, , . • • . . . . . , , / Vere)
Bob Solari , Chairman Spz} ;•' Tho •.A. Peel, Ph . D., Vice President
a : a
O ♦ • yI
Mae,
aa
Approved by BCC 05 / 17 itnesad by:
� '• ; o
ATTES �� r
Jeff K. B on , Clerk f Ci it C0NTY ' 0� '�
� 0
a184a000001�0
MAL) JZr—_enl
Deputy Clerk (Printed name)
Approved as to Form and at iciency :
A an S . P6 ackwic , r. , County Attorney
J-
oseph A Baird, County dministra or
CCRI 1018/XRI 1016 .doc
ATTACHMENT A
PROFESSIONAL SERVICES
engineers I scientists I innovators
9515 Road, Suite
Geosyntec Pensacola, Florida 32534
PH 850 .477. 6547
consultants FAX 850. 477. 6707
www. geosyntec . co m
8 March 2011
Mr. Himanshu H. Mehta, P . E .
Managing Director
Solid Waste Disposal District
Indian River County
1325 74th Avenue SW
Vero Beach , Florida 32968
Subject: Proposal to Implement FDEP Letter, Provide One Year of Groundwater
Monitoring/Reporting and Meeting Attendance
Former South Gifford Road Landfill
Vero Beach, Indian River County, Florida
Dear Mr. Mehta :
Geosyntec Consultants (Geosyntec) is pleased to submit this letter proposal to the Indian River
County (IRC ) Solid Waste Disposal District ( SWDD) to provide professional services associated
with implementation of Florida Department of Environmental Protection (FDEP) -required
activities at the site and continued implementation of the groundwater monitoring for the
chlorinated volatile organic compound (CVOC ) plume at the Former South Gifford Road
Landfill located in Vero Beach , Indian River County, Florida . This fee proposal is based on
correspondence with the FDEP, discussions with IRC , and the FDEP-approved Remedial Action
Plan (RAP) and associated addendums . This proposed scope of work is a continuation of
groundwater monitoring activities that are required by FDEP and that have been ongoing at the
site since 2002 . As requested by IRC , this fee proposal includes budget to implement activities
required by FDEP in correspondence dated 28 January 2011 , complete two semi - annual
monitoring and reporting events for the plume monitoring well network, and to participate in one
meeting . Geosyntec has prepared this proposal (professional services as Exhibit 1 ) as
Amendment 1 to existing Work Order No . 29 for the Continuing Contract Agreement for
Professional Services between IRC SWDD and Geosyntec , dated 10 August 2004 , and amended
effective 24 July 2007 .
The remainder of this letter provides an overview of the project background , a description of the
proposed scope of work, a budget estimate, and a discussion of the schedule for accomplishment
of the work described herein .
CCRI 1018/XRl 1016 .docx
engineers I scientiStS I innovators
Mr. Himanshu H. Mehta, P .E .
8 March 2011
Page 2
PROJECT BACKGROUND
As part of the long-term monitoring activities for the identified CVOC plume associated with the
Former South Gifford Road Landfill , a network of monitoring wells will require sampling on an
annual or semi -annual basis to : ( i ) confirm that the CVOC plume is not migrating by monitoring
the lateral and vertical extent ; ( ii ) evaluate the impact of source remediation to assess CVOC
plume centerline concentrations over time ; and ( iii) assess the impact of biological and physical
natural attenuation processes on CVOC plume degradation . Based on the data presented in the
semi - annual groundwater monitoring reports for the plume monitoring network, Geosyntec
recommended a reduced sampling frequency for some of the plume monitoring network wells .
The scope of work discussed herein is based on assumed approval of these recommendations
(i . e . , removal of shallow wells from the groundwater monitoring network and decreased
sampling frequency in some other monitoring wells) .
PROPOSED SCOPE OF WORK
The proposed scope of work consists of .FDEP- requested monitoring well installations, semi -
annual groundwater monitoring and reporting activities (two events) and the preparation and
submittal of a Remedial Action Plan Modification (RAPM) . For the purpose of budgeting, the
scope of work has been divided into the following four main phases :
• Phase 1 — Project Management ;
• Phase 2 — Meetings/Response to Comments ;
• Phase 3 — Implement FDEP-Required Activities ;
0 Phase 4 — Semi -Annual Sampling Activities ; and
• Phase 5 — Data Evaluation and Semi -Annual Reporting
The remainder of this section presents a general description of the activities to be performed in
each phase .
Phase 1 — Project NManagement
Under this task, Geosyntec will perform project planning and management responsibilities , such
as correspondence with IRC SWDD and FDEP, invoice review, project coordination , and project
administration . The budget includes 1 '/2 hours per month for the project manager over a 12 -
month project duration . In addition, one hour per sampling event has been included for the
associate- in - charge . Geosyntec will also work with IRC to provide updates to the County
regarding site remediation activities (up to two presentations) .
CCR11018/XR11016 . docx
f' rtg7rlt' ers I scientists ' irlllovators
Mr. Himanshu H . Mehta, P . E .
8 March 2011
Page 3
Phase 2 — Meetings/Response to Comments
Under this task, Geosyntec has included budget for preparation and attendance (by two
Geosyntec personnel) at one meeting with IRC . The budget includes 20 hours for preparation for
and attendance at the meeting for Mr. Jim Langenbach and 12 hours for these activities for Ms .
Nandra Weeks . Under this task, Geosyntec will also provide a response to FDEP comments
dated 28 January 2011 .
Phase 3 — Implement FDEP-Required Activities
Under this task, Geosyntec will implement the activities outlined in the 28 January 2011 letter
from FDEP . These activities will include : (i) preparation of a RAPM Addendum No . 2 to
propose additional bioremediation remedial activities in the vicinity of GR-MW30 ; ( ii )
installation , development, surveying and sampling of up to six requested additional monitoring
wells in the vicinity of GR-MW17 and GR-MW30 ; and ( iii) reporting . It is anticipated that the
RAPM Addendum No . 2 will also outline a plan to re -dose the existing biobarriers at the site .
Installation of the monitoring wells requested by FDEP may require brush clearing to provide
access to the area in the vicinity of GR-MW17 , as well as potential coordination and/or approval
for access onto the airport property . (Note : Budget has not been included for additional
bioremediation injection activities which will be proposed in the RAPM or the re- dosing of the
biobarrier) .
Phase 4 — Field Activities
Under this task, Geosyntec will perform all field activities related to the plume groundwater
monitoring, as discussed herein . The field activities will include field preparation , groundwater
sampling, and water level measurements . Field preparation activities will include scheduling and
staffing, subcontracting, field equipment preparation , and notifying FDEP of the field schedule .
In addition, we will coordinate with Environmental Conservation Laboratories , Inc . (ENCO) , the
analytical laboratory contracted with IRC , regarding laboratory analyses required by FDEP .
Geosyntec will perform the groundwater sampling activities associated with the CVOC plume
monitoring wells . Groundwater sampling activities will be executed using a two -person
sampling crew and will be performed in general accordance with the FDEP Standard Operating
Procedures ( SOPS) . The proposed annual field event will be conducted in the summer of 2011
(tentatively in June) and will include sampling of 56 monitoring wells . The proposed semi -
annual field event will be conducted in winter 2011 (tentatively in December) and will include
sampling of 23 monitoring wells . The annual and semi -annual field events are budgeted to be
completed with a two -person team within approximately five days and three days, respectively .
Consistent field documentation and field protocols will be utilized to develop reliable data to
support the natural attenuation of the groundwater plume . It is anticipated that purge water
(IDW) will be treated in the existing air stripper sump and discharged to the sanitary sewer
following treatment . No costs are included herein for IDW disposal .
CCR 11018/XRl I016 . docx
engineers ( 5C`,ietitists inii0:?vators
Mr . Himanshu H . Mehta, P . E .
8 March 2011
Page 4
Geosyntec will conduct a complete round of groundwater level measurements coincident with
each semi - annual groundwater sampling event . Depth to groundwater measurements will be
recorded to the nearest 0 . 01 - 11 in each monitoring well , including existing monitoring wells and
applicable City of Vero Beach wells (assumed up to 82 wells) .
As a potential cost- savings measure at the site , we are proposing the use of Passive Diffusion
Bag (PDB ) Samplers in wells sampled for exclusively for VOCs . The PDBs are an innovative
sampling technique that consists of the deployment of a semi -permeable low-density
polyethylene tube lab - filled with analyte - free water within the screened interval of a well . The
technology is based on the principal of diffusion and that compounds will migrate from an area
of high concentration to an area of low concentration until equilibrium is achieved . It is
recommended that the PDBs be deployed in the well for a minimum of 14 days up to a maximum
of one year prior to sample collection . Use of these samplers in lieu of traditional low- flow
purging techniques will save labor time in the field . More detailed technical information can be
provided upon request . Geosyntec anticipates utilizing PDB samplers in lieu of low- flow
purging techniques at a number of proposed monitoring well locations ( if approved by the
FDEP) . If PDBs are approved for use at the site by the FDEP, it is anticipated that up to 30
percent of the proposed labor budget will not be utilized .
Phase 5 — Data Evaluation and Semi-Annual Reporting
Under this task, Geosyntec will perform data evaluation activities for the CVOC plume
monitoring reporting and prepare semi -annual reports (two) for submittal to FDEP . Data
evaluation activities will include database management, data evaluation and screening ,
geographical information systems (GIS ) figure preparation , time trend analyses, and/or statistical
data analyses . The results of groundwater sampling associated with the CVOC plume
monitoring will be presented in a report supported by attachments containing Chain -of- Custody
sheets, field notes and observations, water sampling logs, maps, graphs , analytical results , and
any other applicable materials . The draft reports will be submitted to IRC SWDD for review
prior to submittal to FDEP . Each final semi - annual report will be signed and sealed by a Florida
registered professional engineer or geologist.
SCHEDULE
FDEP has requested that the County begin implementation of the required activities
immediately . Geosyntec will initiate these activities within two weeks of receipt of notice to
proceed from the County . We will conduct the groundwater monitoring and reporting activities
on a semi -annual basis as described herein . The semi -annual groundwater monitoring events
will be conducted tentatively in June and December 2011 . In addition , Geosyntec is tentatively
scheduled to attend the 22 March 2011 County Commission meeting to present a project update .
CCR11018/XRI 1016 . docx
engineers ( scientists innovators
Mr. Himanshu H . Mehta, P . E .
8 March 2011
Page 5
BUDGET ESTIMATE
A budget estimate for the scope of work outlined in Phases 1 through 5 of this proposal is
summarized below and a detailed budget estimate is provided as Exhibit 1 . The budget estimate
presented in this proposal is based on Geosyntec ' s understanding of the project requirements , our
experience gained from executing similar tasks for IRC SWDD at the site, and experience with
groundwater monitoring and reporting activities at similar facilities .
Geosyntec will not exceed the budget estimate without prior approval and written authorization
from IRC SWDD .
Phase 1 — Project Management $ 5 , 175
Phase 2 — Meetings/Response to Comments $ 7, 067
Phase 3 — Implement FDEP-Required Activities $ 575460
Phase 4 — Semi -Annual Sampling Activities $409054
Phase 5 — Data Evaluation and Semi -Annual Reporting $25 , 187
TOTAL $ 1349943
CLOSURE
Geosyntec appreciates this opportunity to offer our services . If this proposal is acceptable ,
please indicate your agreement by signing the attached work authorization , which references this
proposal . Please return one signed work authorization to Ms . Johnson ' s attention . Please call
either of the undersigned with questions you may have as you review this proposal .
Sincerely,
4xk V) jAno,
Jill Johnson , P . G .
Senior Hydrogeologist
t �
1 j
James Langenbach , P .E .
Associate
Attachments
CCR 11018/XR 11016 . docx
engineers I scientists I iriiiovators
EXHIBIT 1
BUDGET ESTIMATE
engineers I scientists I innovators
Table 1
MARCH 2011 BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 1 : Project Management
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
,. Iirofessional Services
a . Principal hr $ 195 .67 0 $0
b. Associate hr $ 185 . 32 6 $ 13112
c . Senior Project Geologist hr $ 163 . 07 18 $23935
d. Project Engineer hr $ 129 . 12 0 $0
e . Engineer hr $ 112 . 49 0 $0
f. Senior Staff Geologist hr $ 100 . 16 0 $ 0
g . Staff Engineer hr $ 84 .24 0 $ 0
Subtotal Professional Services $4,047
B. .'Technical/Administrative Services
a. Site Manager/Construction Manager hr $98 . 56 0 $0
b . Senior Engineering Technician hr $73 . 88 0 $0
c . Designer/GIS hr $ 119. 39 0 $0
d . Drafter/CADD Operator hr $72 . 79 0 $0
e . Technical/Administrative Assistant hr $ 81 . 39 12 $977
f. Technical Word Processor hr $ 83 . 08 0 $0
g . Clerical hr $49. 96 0 $0
Subtotal Technical/Administrative Services $977
C. Reimbursables
a. Lodging day $89 0 $ 0
b . Per Diem day $51 0 $0
c . Communications Fee 3 % labor 0 . 03 5 ,024 $ 151
d . CADD Computer System hr $ 15 0 $0
e. Vehicle Rental day $75 0 $0
f. 8 .5 "x11 " Photocopies each $0 . 12 0 $0
g. Second Day Letter each $6 0 $0
Subtotal Reimbursable $ 151
TOTAL ESTIMATED BUDGET : PHASE 1 $5,175 .
XRl 1016.xlsx Geosyntec Consultants
Table 2
MARCH 2011 BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 2 : Meetin saes onse to Comments
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services V " ff
a. Principal hr $ 195 . 67 12 $2, 348
b . Associate hr $ 185 . 32 20 $3 , 706
c. Senior Project Geologist hr $ 163 . 07 4 $652
d . Project Engineer hr $ 129 . 12 0 $0
e . Engineer hr $ 112 . 49 0 $0
f. Senior Staff Geologist hr $ 100 . 16 0 $ 0
g . Staff Engineer hr $ 84 .24 0 $0
Subtotal Professional Services $69707
B.% Teclinical/Administrative Services
a. Site Manager/Construction Manager hr $98 . 56 0 $0
b . Senior Engineering Technician hr $73 . 88 0 $0
c. Designer/GIS hr $ 119. 39 0 $0
d. Drafter/CADD Operator hr $ 72 . 79 0 $0
e . Technical/Administrative Assistant hr $ 81 . 39 1 $ 81
f. Technical Word Processor hr $ 83 . 08 0 $0
g. Clerical hr $49 . 96 0 $0
Subtotal Technical/Administrative Service $81
C. = Reimbursabl6s s mm,q �
a. Lodging day $89 0 $ 0
b . Per Diem day $51 0 $ 0
c. Communications Fee 3 % labor 0 . 03 6, 788 $204
d. CADD Computer System hr $ 15 0 $0
e. Vehicle Rental day $75 1 $75
f. 8 . 5 " xl l " Photocopies each $ 0 . 12 0 $ 0
g. Second Day Letter each $6 0 $0
Subtotal Reimbursable $279
TOTAL ESTIMATED =BiJDGET : PHASE
XRl 1016.xlsx Geosyntec Consultants
Table 3
MARCH 2011 BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 3 : Implement FDEP-Re uired Activities
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services ,
a. Principal hr $ 195 .67 0 $0
b. Associate hr $ 185 .32 8 $ 1 ,483
c. Senior Project Geologist hr $ 163 .07 4 $652
d. Project Engineer hr $ 129. 12 0 $0
e. Engineer (RAPM Prep) hr $ 112.49 45 $53062
f. Senior Staff Geologist (RAPM/sampling) hr $ 100. 16 40 $41006
g. Staff Engineer hr $84. 24 0 $0
Subtotal Professional Services $11,203
kfteetiniekiAdminlstrative Services
a. Site Manager/Construction Manager hr $98. 56 80 $7 ,885
b. Senior Engineering Technician hr $73 . 88 0 $0
c. Designer/GIS hr $ 119.39 4 $478
d. Drafter/CADD Operator hr $72. 79 0 $0
e. Technical/Administrative Assistant hr $81 . 39 1 4 $326
f Technical Word Processor hr $83 . 08 0 $0
g. Clerical hr $49.96 0 $0
It. Clerical hr $42 0 $0
Subtotal Technical/Administrative Services $89688
C Subcontractors ] v 4 U
�, .
a. Driller Mod/demob/prep LS $2,675 . 00 1 $2,675
b. Per Diem day $353 .00 4 $ 13412
c. Well Installations each $4 ,244.00 6 $25,464
d. Permits each $25. 00 6 $ 150
e. Well Development hr $ 185. 00 3 $555
f. Decon hr $214.00 4 $856
g. brush clearing LS $ 1 ,070. 00 1 $ 15070
Jr. Drums each $58. 85 15 $883
i. Surveying each $ 167 .00 6 $ 1 ,002
Subtotal Subcontractor Services $34,067
D'i ' Reimbuisablessip
a. Lodging day $89 7 $623
b. Per Diem day $51 7 $357
c. Communications Fee 3 % labor 0. 03 $ 195891 $597
d. CADD Computer System hr $ 15 4 $60
e. Vehicle Rental day $75 7 $525
f. 8. 5 "xIV Photocopies each $0. 12 100 $ 12
g. Overnight Cooler each $95 2 $ 190
h. Groundwater Sampling Kit day $275 2 $550
i . Well installation kit day $ 160 3 $480
j . Equipment Shipping each $54 2 $ 108
Subtotal Reimbursable $39502
TOTAL ESTIMATED BUDGET : PHASE 3 "$579460 `>
Notes :
1 . Lodging and per diem rates were taken from the GSA website for the Vero Beach area (www . gsa.gov).
2 . Groundwater Sampling Kit includes: water level indicator, oil/water probe, peristaltic or bladder pomp,
multi-meter (pH, temperature, conductivity, turbidity , dissolved oxygen , and oxidation reduction potential),
tubing, and miscellaneous supplies.
3 . Well installation kit includes PID, water level indicator.
XR11016.xlsx Geosyntec Consultants
Table 4
MARCH 2011 BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 4 : Semi-Annual Sampling Activities
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services
a. Principal hr $ 195 . 67 0 $0
b . Associate hr $ 185 .32 2 $ 371
c. Senior Project Geologist hr $ 163 . 07 4 $ 652
d. Project Engineer hr $ 129 . 12 0 $0
e. Engineer hr $ 112 .49 0 $0
f Senior Staff Geologist hr $ 100 . 16 170 $ 17, 027
g. Staff Engineer hr $84 .24 0 $ 0
Subtotal Professional Services $ 189050
B Technical/Administrative Services
a. Site Manager/Construction Manager hr $98 . 56 170 $ 16,755
b . Senior Engineering Technician hr $ 73 . 88 0 $0
c. Designer/GIS hr $ 119 .39 0 $0
d . Drafter/CADD Operator hr $72 . 79 0 $0
e . Technical/Administrative Assistant hr $ 81 . 39 0 $0
f Technical Word Processor hr $83 . 08 0 $0
g . Clerical hr $49 . 96 0 $0
h . Clerical hr $42 0 $0
Subtotal Technical/Administrative Services $ 16,755
C. Reimbursables °
a. Lodging day $ 89 7 $623
b. Per Diem day $51 14 $714
c. Communications Fee 3 % labor 0 . 03 $345805 $ 1 ,044
d. CADD Computer System lir $ 15 0 $ 0
e . Vehicle Rental day $75 7 $ 525
f 8 . 5 "xIV Photocopies each $0 . 12 100 $ 12
g . Overnight Cooler each $95 2 $ 190
h . Groundwater Sampling Kit day $275 7 $ 15925
i . Water Level Measurement Kit day $ 53 . 75 2 $ 108
j . Equipment Shipping each $ 54 2 $ 108
Subtotal Reimbursables $59249
TOTAL ESTIMATED'BUDGET : PHASE 4 $40,054
TOTAL ESTIMATED BUDGET PER EVENT - $209027
Notes :
1 . Lodging and per diem rates were taken from the GSA website for the Vero Beach area (www . gsa. gov) .
2 . Groundwater Sampling Kit includes : water level indicator, oil/water probe, peristaltic or bladder pump,
multi-meter (pH , temperature, conductivity, turbidity, dissolved oxygen, and oxidation reduction potential),
tubing, and miscellaneous supplies .
3 . Water Level Measurement Kit includes : water level indicator and miscellaneous field supplies .
XR11016.xlsx Geosyntec Consultants
Table 5
MARCH 2011 BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 5 : Data Evaluation and Semi-Annual Reporting
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services . - lnjiw
a. Principal hr $ 195 . 67 0 $0
b . Associate hr $ 185 . 32 8 $ 1 ,483
c . Senior Project Geologist hr $ 163 . 07 32 $ 5 ,218
d . Project Engineer hr 1 $ 129 . 12 0 $0
e . Engineer hr $ 112 .49 0 $0
f. Senior Staff Geologist hr $ 100 . 16 120 $ 12,019
g . Staff Engineer hr $ 84 .24 0 $ 0
Subtotal Professional Services $189720
Bli Technical/Administrative ;Services ,
a . Site Manager/Construction Manager hr $98 .56 0 $ 0
b . Senior Engineering Technician hr $ 73 . 88 0 $ 0
c . Designer/GIS hr $ 119 .39 0 $0
d . Drafter/CADD Operator hr $72 . 79 48 $ 35494
e . Technical/Administrative Assistant hr $ 81 .39 8 $651
f. Technical Word Processor hr $ 83 . 08 0 $ 0
g . Clerical hr $49. 96 8 $400
Subtotal Technical/Administrative Services $49545
a. Lodging day $ 89 0 $0
b . Per Diem day $ 51 0 $0
c . Communications Fee 3 % labor 0 . 03 $235265 $698
d . CADD Computer System hr $ 15 56 $ 840
e . Vehicle Rental day $ 75 0 $ 0
f. 8 . 5 " x11 " Photocopies each $ 0 . 12 29000 $240
g . CADD Photocopies each $3 48 $ 144
Subtotal Reimbursables $ 1 ,922
TOTAL EST]M ATED BUDGET : PHASES $25;187
TOTAL ESTIMATED BUDGET PER REPORT : i $12,593 1
XR11016.xlsx Geosyntec Consultants
ATTACHMENT E
FEE SCHEDULE
e ptleers I scientists I innovators
Exhibit 2
Geosyntec Consultants
2009 Bill Rates
Labor Classification Bill Rate
Clerical $49 . 96
Administrative Assistant $ 81 . 39
Technical Word Processor $ 83 . 08
Drafter/CADD Operator/Artist $ 72 . 79
Senior Drafter/Senior CADD Operator $ 117 . 10
Designer $ 119 . 39
Engineering Technician $ 56 . 86
Senior Engineering Technician $ 73 . 88
Field Manager $ 86 . 22
Site Manager $ 98 . 56
Field Superintendent $ 102 . 54
Staff Professional $ 84 . 24
Senior Staff Professional $ 100 . 16
Professional $ 112 . 49
Project Professional $ 129 . 12
Senior Professional $ 163 . 07
Associate $ 185 . 32
Principal $ 195 . 67
General
Direct Expenses At Cost
Subcontract Services Cost Plus 7%
Communications Fee 3 % of Professional Fees
Specialized Computer Applications $ 15 per hour
Photocopies $ 0 . 12 per page
Effective 1 August 2008 and each year thereafter the bill rates stated
above will be adjusted based on the prior twelve month Consumer Price
Index for all south urban consumers .
IRC 2009 Rates