WORK ORDER NUMBER 29
This Work Order Number 29 is entered into as of this 6 day of July 2010 pursuant to that
certain Continuing Contract Agreement for Professional Services entered into as of August 10 ,
2004 and amended July 24 , 2007 ( as so amended , the "Agreement" ) , by and between Indian
River County Board of County Commissioners ( " COUNTY" ) on the same terms as the existing
Agreement , as extended , between the Indian River County Solid Waste Disposal District , a
dependent special district of Indian River County , Florida , ( " DISTRICT" ) and Geosyntec , Inc . ,
a Florida corporation ( " CONSULTANT" ) .
The COUNTY has selected the Consultant to perform the professional services set forth
on Attachment A , attached to this Work Order and made part hereof by this reference . The
professional services will be performed by the Consultant for the fee schedule set forth in
Attachment B , attached to this Work Order and made a part hereof by this reference . The
Consultant will perform the professional services within the Schedule more particularly set forth
in Attachment A , attached to this Work Order and made a part hereof by this reference all in
accordance with the terms and provisions set forth in the Agreement . Pursuant to paragraph
1 . 4 of the Agreement , nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each
individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Work Order as of the
date first written above .
CONSULTANT
GEOSYNTEC CONSULTANTS , INC . INDIAN RIVER COUNTY
ee 6
rim Issa°°°
By : • •. 2�• y : - - -
Thomas A. Peel , Ph . D . , Ser • resid '•.���0 Peter D . O ' Bryan, Chair mdd
a � * °
Attest : K . B �- lerk of Court
Ily •
sy
•' �° uty Clerk
°
"•oq • •�o� A proved :
" loan °" "°'aop
oeph A . acrd , County Admini rator
Ap roved as to form and legal sufficiency :
County Attorney
ATTACHMENT A
PROFESSIONAL SERVICES
engineers I scientists I innovators
Holsb
9515 Pensacola,
rry Road, Suite 4
Geosyntec "
Pensacola, Florida 32534 PH 850 .477. 6547
FAX 850.477.6707
Consultants www .geosyntce. Coin
23 June 2010
Mr. Himanshu H . Mehta, P .E .
Managing Director
Solid Waste Disposal District
Indian River County
1325 74th Avenue SW
Vero Beach , Florida 32968
Subject: Proposal to Provide One Year of Groundwater Monitoring and Reporting and
FDEP Meeting Attendance
Former South Gifford Road Landfill
Vero Beach, Indian River County, Florida
Dear Mr . Mehta :
Geosyntec Consultants (Geosyntec) is pleased to submit this letter proposal to the Indian River
County (IRC) Solid Waste Disposal District (SWDD) to provide professional services associated
with continued implementation of the groundwater monitoring for the chlorinated volatile
organic compound (CVOC ) plume at the Former South Gifford Road Landfill located in Vero
Beach , Indian River County, Florida . This fee proposal is based on correspondence with the
Florida Department of Environmental Protection (FDEP) , discussions with IRC , and the FDEP-
approved Remedial Action Plan (RAP) and associated addendums . This proposed scope of work
is a continuation of groundwater monitoring activities that are required by FDEP and that have
been ongoing at the site since 2002 . As requested by IRC , this fee proposal includes budget to
complete two semi - annual monitoring and reporting events for the plume monitoring well
network and to participate in one meeting with the FDEP . Geosyntec has prepared this proposal
(professional services as Exhibit 1 ) as Work Order No . 29 for the Continuing Contract
Agreement for Professional Services between IRC SWDD and Geosyntec , dated 10 August
2004 , and amended effective 24 July 2007 .
The remainder of this letter provides an overview of the project background , a description of the
proposed scope of work, a budget estimate, and a discussion of the schedule for accomplishment
of the work described herein .
PROJECT BACKGROUND
As part of the long-term monitoring activities for the identified CVOC plume associated with the
South Gifford Road Landfill , a network of monitoring wells will require sampling on an annual
or semi -annual basis to : (i) confirm that the CVOC plume is not migrating by monitoring the
XR 101 50\XR1 00 1 6rev . docx
engineers I Scientists I innovators
Mr. Himanshu H . Mehta, P .E .
23 June 2010
Page 2
lateral and vertical extent ; ( ii ) evaluate the impact of source remediation to assess CVOC plume
centerline concentrations over time ; and ( iii ) assess the impact of biological and physical natural
attenuation processes on CVOC plume degradation . Based on the data presented in the semi -
annual groundwater monitoring reports for the plume monitoring network, Geosyntec
recommended reduced sampling frequency for some of the plume monitoring network wells .
The scope of work discussed herein is based on assumed approval of these recommendations
( i . e . , removal of shallow wells from the groundwater monitoring network and decreased
sampling frequency in some other monitoring wells) .
PROPOSED SCOPE OF WORK
The proposed scope of work consists of semi - annual groundwater monitoring and reporting
activities to be performed on behalf of IRC SWDD at the Former South Gifford Road Landfill .
For the purpose of budgeting , the scope of work has been divided into the following four main
phases :
• Phase 1 — Project Management;
• Phase 2 —Meetings/Response to Comments ;
• Phase 3 — Field Activities ; and
0 Phase 4 — Data Evaluation and Semi -Annual Reporting .
The remainder of this section presents a general description of the activities to be performed in
each phase .
Phase 1 — Prosect Management
Under this task, Geosyntec will perform project planning and management responsibilities , such
as correspondence with IRC SWDD and FDEP, invoice review, project coordination , and project
administration . The budget includes two hours per month for the project manager over a 12 -
month project duration . In addition , one hour per sampling event has been included for the
associate- in - charge .
Phase 2 — Meetings/Response to Comments
Under this task, Geosyntec has included budget for preparation and attendance (by two
Geosyntec personnel) at one meeting with IRC and /or FDEP, as needed . The budget includes 20
hours for preparation for and attendance at the meeting for the project manager and 12 hours for
these activities for the associate-in - charge . Under this task, Geosyntec will also provide a brief
response to FDEP comments dated 24 May 2010 .
XR1015MR10016rev .docx
engineers I scientists I innovators
Mr. Himanshu H. Mehta, P . E .
23 June 2010
Page 3
Task 3 — Field Activities
Under this task, Geosyntec will perform all field activities related to the plume groundwater
monitoring, as discussed herein . The field activities will include field preparation , groundwater
sampling, and water level measurements . Field preparation activities will include scheduling and
staffing, subcontracting, field equipment preparation , and notifying FDEP of the field schedule .
In addition, we will coordinate with Environmental Conservation Laboratories , Inc . (ENCO), the
analytical laboratory contracted with IRC , regarding laboratory analyses required by FDEP .
Geosyntec will perform the groundwater sampling activities associated with the CVOC plume
monitoring wells . Groundwater sampling activities will be executed using a two -person
sampling crew and will be performed in general accordance with the FDEP Standard Operating
Procedures ( SOPs) . The proposed annual field event will be conducted in summer 2010
(tentatively in July) and will include sampling of 76 monitoring wells . The proposed semi -
annual field event will be conducted in winter 2010 (tentatively in December) and will include
sampling of 22 monitoring wells . The annual and semi -annual field events are budgeted to be
completed within approximately seven days and two days, respectively . Consistent field
documentation and field protocols will be utilized to develop reliable data to support the natural
attenuation of the groundwater plume . It is anticipated that purge water (IDW) will be treated in
the existing air stripper sump and discharged to the sanitary sewer following treatment . No costs
are included herein for IDW disposal .
Geosyntec will conduct a complete round of groundwater level measurements coincident with
each semi -annual groundwater sampling event . Depth to groundwater measurements will be
recorded to the nearest 0 . 01 - ft in each monitoring well , including existing monitoring wells and
applicable City of Vero Beach wells (assumed up to 82 wells) .
Task 4 — Data Evaluation and Semi-Annual Reporting
Under this task, Geosyntec will perform data evaluation activities for the CVOC plume
monitoring reporting and prepare semi - annual reports for submittal to FDEP . Data evaluation
activities will include database management, data evaluation and screening, geographical
information systems (GIS ) figure preparation , time trend analyses, and/or statistical data
analyses . The results of groundwater sampling associated with the CVOC plume monitoring will
be presented in a report supported by attachments containing Chain -of- Custody sheets , field
notes and observations, water sampling logs , maps , graphs, analytical results , and any other
applicable materials . The draft reports will be submitted to IRC SWDD for review prior to
submittal to FDEP . Each final semi - annual report will be signed and sealed by a Florida
registered professional engineer or geologist .
XR 10 1 50\XR1 001 6rev. docx
erlgiiieers I sc:ierttists I inncivators
Mr. Himanshu H. Mehta, P . E .
23 June 2010
Page 4
SCHEDULE
Geosyntec will conduct the groundwater monitoring and reporting activities on a semi - annual
basis as described herein . The semi -annual groundwater monitoring events will be conducted
tentatively in July and December 2010 .
BUDGET ESTIMATE
A budget estimate for the scope of work outlined in Phases 1 through 4 of this proposal is
summarized in the following table , and a detailed budget estimate is provided as Exhibit 1 . The
budget estimate presented in this proposal is based on Geosyntec ' s understanding of the project
requirements, our experience gained from executing similar tasks for SWDD since 2002 at the
site , and experience with groundwater monitoring and reporting activities at similar facilities .
Geosyntec will not exceed the budget estimate without prior approval and written authorization
from IRC SWDD .
Phase 1 — Project Management $4 , 830
Phase 2 — Meetings/Response to Comments $ 8 , 108
Phase 3 — Field Activities $295404
Phase 4 — Data Evaluation and Semi -Annual Reporting $25 , 021
TOTAL $679363
CLOSURE
Geosyntec appreciates this opportunity to offer our services . If this proposal is acceptable ,
please indicate your agreement by signing the attached work authorization , which references this
proposal . Please return one signed work authorization to Ms . Johnson ' s attention . Please call
either of the undersigned with questions you may have as you review this proposal .
Sincerely,
� r
eJohnso'n ,)P .
Senior Hydrogeologist
times l ar g�nbach , P . E .
Associate
Attachments
XR l 0150\XR 10016rev. do cx
engineers I scietitists ( it' llov tors
EXTHHBIT 1
BUDGET ESTIMATE
engineers I scientists I innovators
Table 1
BUDGET ESTIMATE
ONE YEAR OF GROUNDWATER MONITORING AND REPORTING
SOUTH GIFFORD ROAD LANDFILL
PHASE 1 : Project Management
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Prof8ssio al Services
a . Principal hr $ 195 . 67 0 $0
b . Associate hr $ 185 . 32 4 $741
c . Senior Project Geologist hr $ 165 . 07 18 $2, 971
d. Project Engineer hr $ 129 . 12 0 $0
e . Engineer hr $ 112 .49 0 $0
f. Senior Staff Geologist hr $ 100 . 16 0 $0
g. Staff Engineer hr $84 .24 0 $0
Subtotal Professional Services $3,713
B:dtTechnical/Adininistrative Services k
a. Site Manager/Construction Manager lir $ 98 . 56 0 $0
b . Senior Engineering Technician hr $73 . 88 0 $0
c. Designer/GIS hr $ 119. 39 0 $0
d. Drafter/CADD Operator hr $72 . 79 0 $0
e . Technical/Administrative Assistant hr $81 . 39 12 $977
f. Technical Word Processor hr $83 . 08 0 $0
g. Clerical hr $49 . 96 0 $0
Subtotal Technical/Administrative Services $977
C. 'Reim bursables
a. Lodging day $ 89 0 $0
b. Per Diem day $51 0 1 $0
c . Communications Fee 3 % labor 0 . 03 409 $ 141
d . CADD Computer System hr $ 15 0 $0
e . Vehicle Rental day $75 0 $ 0
f. 8 . 5 "x11 " Photocopies each $0 . 12 0 $ 0
g. Second Day Letter each $6 0 $0
Subtotal Reimbursable $ 141
v
'` " TOTAL ESTIMATED BUDGET : PHASE 1 $4,830 "e
XR07014/XR10016rev.xlsx Geosyntec Consultants
Table 2
BUDGET ESTIMATE
ONE YEAR OF GROUNDWATER MONITORING AND REPORTING
SOUTH GIFFORD ROAD LANDFILL
PHASE 2 : Meetin s/Res onse to Comments
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A:,! Professional Services ,
a. Principal hr $ 195 . 67 0 $0
b . Associate hr $185 . 32 12 $2,224
c. Senior Project Geologist hr $ 165 . 07 24 $3 ,962
d. Project Engineer hr $ 129 . 12 0 $0
e. Engineer hr $ 112 .49 0 $0
f. Senior Staff Geologist hr $ 100 . 16 8 $801
g. Staff Engineer hr $ 84 . 24 0 $0
Subtotal Professional Services $6,987
B�Technical/Administrative Services
a. Site Manager/Construction Manager hr $98 . 56 0 $0
b . Senior Engineering Technician hr $73 . 88 0 $0
c. Designer/GIS hr $ 119. 39 6 $716
d . Drafter/CADD Operator hr $72 . 79 0 $0
e. Technical/Administrative Assistant hr $ 81 .39 1 $ 81
f. Technical Word Processor hr $83 . 08 0 $0
g. Clerical hr $49 . 96 0 $0
Subtotal Technical/Administrative Service $798
t Vie:
C:VReimbursables , Po
a. Lodging day $ 89 0 $ 0
b . Per Diem day $51 0 $0
C. Communications Fee 3 % labor 0 . 03 7,785 $234
d . CADD Computer System hr $ 15 6 $90
e . Vehicle Rental day $75 0 $0
f. 8 .5 "x11 " Photocopies each $ 0 . 12 0 $ 0
g. Second Day Letter each $6 0 $ 0
Subtotal Reimbursable $324
TOTAL ESTIMATED BUDGET : PHASE 2 $8,108 n
XR07014/XR10016rev.xlsx Geosyntec Consultants
Table 3
BUDGET ESTIMATE
ONE YEAR OF GROUNDWATER MONITORING AND REPORTING
SOUTH GIFFORD ROAD LANDFILL
PHASE 3 : Field Activities
ESTIMATED
ITEM BASIS RATE QUANTITY
BUDGET
Professional Services
a. Principal hr $ 195 . 67 0 $ 0
b . Associate hr $ 185 . 32 2 $371
c . Senior Project Geologist hr $ 165 . 07 4 $660
d. Project Engineer hr $ 129 . 12 0 $ 0
e . Engineer hr $ 112 .49 0 $0
f. Senior Staff Geologist hr $ 100 . 16 110 $ 11 ,018
g . Staff Engineer hr $84 .24 0 $0
Subtotal Professional Services $ 12,049
B. Tecbuical/Adrd nistrative Services
�,. �.. Aw
a. Site Manager/Construction Manager hr $98 . 56 110 $ 105842
b . Senior Engineering Technician hr $73 . 88 0 $0
c. Designer/GIS hr $ 119 . 39 0 $ 0
d . Drafter/CADD Operator hr $ 72 . 79 0 $0
e . Technical/Administrative Assistant ' hr $ 81 . 39 0 $0
f Technical Word Processor hr $ 83 . 08 0 $ 0
g . Clerical hr $49 .96 0 $0
h . Clerical hr $42 0 $ 0
Subtotal Technical/Administrative Services $ 109842
C." Reimbui�sables '
a. Lodging day $ 89 10 $ 890
b. Per Diem day $ 51 20 $ 15020
c . Communications Fee 3 % labor 0 . 03 $225890 $687
d. CADD Computer System hr $ 15 0 $0
e . Vehicle Rental day $75 10 $ 750
f. 8 . 5 "x11 " Photocopies each $0 . 12 100 1 $ 12
g. Overnight Cooler each $95 2 $ 190
h . Groundwater Sampling Kit day $275 10 $23750
i . Water Level Measurement Kit day $ 53 . 75 2 $ 108
j . Equipment Shipping each $ 54 2 $ 108
Subtotal Reimbursables $65514
e TOTAL ESTIMATED, BUDGET : PHASE+3 ' $29,404 • 1��; . t ' TOTAL ESTIMATED BUDGET PEItEVEN
$14,702` �". E '
Notes :
1 . Groundwater Sampling Kit includes : water level indicator, oil/water probe, peristaltic or bladder pump,
multi-meter (pH , temperature, conductivity, turbidity, dissolved oxygen, and oxidation reduction potential ),
tubing, and miscellaneous supplies .
2 . Water Level Measurement Kit includes : water level indicator and miscellaneous field supplies.
XR07014/XR10016rev.xlsx Geosyntee Consultants
Table 4
BUDGET ESTIMATE
ONE YEAR OF GROUNDWATER MONITORING AND REPORTING
SOUTH GIFFORD ROAD LANDFILL
PHSAE 4 : Data Evaluation and Semi=Annual Reporting
ITEM BASIS RATEQUANTITY ESTIMATED
BUDGET
A. : Professionals Services v
a. Principal hr $ 195 .67 0 $ 0
b . Associate hr $ 185 .32 6 $ 1 , 112
c . Senior Project Geologist hr $ 165 .07 32 $5 ,282
d . Project Engineer hr 1 $ 129 . 12 0 $0
e . Engineer hr $ 112 .49 0 $ 0
f. Senior Staff Geologist hr $ 100 . 16 120 $ 12 ,019
g . Staff Engineer hr $ 84 .24 0 $ 0
Subtotal Professional Services $189413
B ; TechniciUAdministrative Services
a. Site Manager/Construction Manager hr $98 . 56 0 $ 0
b . Senior Engineering Technician hr $ 73 . 88 0 $0
c . Designer/GIS hr $ 119 .39 0 $ 0
d . Drafter/CADD Operator hr $ 72 . 79 48 $3 ,494
e . Technical/Administrative Assistant hr $ 81 . 39 8 $ 651
f. Technical Word Processor hr $ 83 . 08 0 $0
g . Clerical hr $49 . 96 8 $400
Subtotal Technical/Administrative Services $49545
C. - Reimbursables
a. Lodging day $ 89 0 $0
b . Per Diem day $ 51 0 $0
c . Communications Fee 3 % labor 0 . 03 $22,958 $ 689
d . CADD Computer System hr $ 15 56 $ 840
e . Vehicle Rental day $75 2 $ 150
f. 8 . 5 " x11 " Photocopies each $ 0 . 12 2,000 $240
g . CADD Photocopies each $ 3 48 $ 144
Subtotal Reimbursables $29063
, G TOTAL ESTIMATED BUDGET : PHASE 4 ;. $25;021
TOTAL ESTIMATED BUDGET PER REPORT
XR07014/XR 100 1 6rev .xlsx Geosyntec Consultants
ATTACHMENT B
FEE SC EDULE
engi�iieers I as(vientists I innovators
s
Exhibit 2
Geosyntec Consultants
2009 Bill Rates
Labor Classification Bill Rate
Clerical $49 . 96
Administrative Assistant $ 81 . 39
Technical Word Processor $ 83 . 08
Drafter/CARD Operator/Artist $ 72 . 79
Senior Drafter/ Senior CADD Operator $ 117 . 10
Designer $ 119 . 39
Engineering Technician $ 56 . 86
Senior Engineering Technician $ 73 . 88
Field Manager $ 86 . 22
Site Manager $ 98 . 56
Field Superintendent $ 102 . 54
Staff Professional $ 84 . 24
Senior Staff Professional $ 100 . 16
Professional $ 112 . 49
Project Professional $ 129 . 12
Senior Professional $ 163 . 07
Associate $ 185 . 32
Principal $ 195 . 67
General
Direct Expenses At Cost
Subcontract Services Cost Plus 7 %
Communications Fee 3 % of Professional Fees
Specialized Computer Applications $ 15 per hour
Photocopies $ 0 . 12 per page
Effective 1 August 2008 and each year thereafter the bill rates stated
above will be adjusted based on the prior twelve month Consumer Price
Index for all south urban consumers .
IRC 2009 Rates