HomeMy WebLinkAbout2011-081 -y �O
3 -22-
4811 .
CHANGE ORDER NO , 1
DATE OF ISSUANCE :
EFFECTIVE DATE :
OWNER : INDIAN RIVER COUNTY
CONTRACTOR : Hydromentia , Inc .
PROJECT : Pilot Algal Turf Scrubber for PC South
ENGINEER : INDIAN RIVER COUNTY
You are directed to make the following changes in the Contract Documents :
Increase/ Decrease
Increase/ Decrease
Item Description in Contract Time
in Contract Price ( Calendar Days )
Operate the ATS pilot system using a 1 : 1
canal water to RO brine mix in
1 . 0 laccorclance with Attachment No . 1 $ 15 , 165 . 00 84 . 0
TOTALS $ 15 , 165 . 00 84 . 0
CHANGE IN CONTRACT PRICE
Description Amount
Original Contract Price $ 188, 000 . 00
Net increase/decrease from previous Change Orders $ 0 . 00
Contract Price prior to this Change Order $ 188, 000 . 00
Net increase/decrease of this Change Order $ 15 , 165 . 00
Contract Price with all approved Change Orders $ 203, 165 . 00
CHANGE IN CONTRACT TIME ( Calendar Days )
Description Amount
Original Contract Time for Final Completion 168 . 0
Net increase/decrease from previous Change Orders 0 . 0
Contract Time for Final Completion prior to this Change Order 168 . 0
Net increase/decrease of this Change Order to Final Completion 84 . 0
Contract Time for Final Completion with all approved Change Orders 252 . 0
3 -22-
CHANGE
-z2.-CHANGE ORDER NO , 1
DATE OF ISSUANCE :
EFFECTIVE DATE :
OWNER : INDIAN RIVER COUNTY
CONTRACTOR : Hydromentia, Inc .
PROJECT : Pilot Algal Turf Scrubber for PC South
ENGINEER : INDIAN RIVER COUNTY
You are directed to make the following changes in the Contract Documents :
I
Increase/ Decreasencrease/ Decrease
Item Description in Contract Price in Contract Time
( Calendar Days )
Operate the ATS pilot system using a 1 : 1
canal water to RO brine mix in
1 . 0 laccordance with Attachment No . 1 $ 15 , 165 . 00 84 . 0
TOTALS $ 15 , 165 . 00 84 . 0
CHANGE IN CONTRACT PRICE
Description Amount
Original Contract Price $ 188 , 000 . 00
Net increase/decrease from previous Change Orders $ 0 . 00
Contract Price prior to this Change Order $ 188, 000 . 00
Net increase/decrease of this Change Order $ 15 , 165 . 00
Contract Price with all approved Change Orders $ 203, 165 . 00
CHANGE IN CONTRACT TIME ( Calendar Days )
Description Amount
Original Contract Time for Final Completion 168 . 0
Net increase/decrease from previous Change Orders 0 . 0
Contract Time for Final Completion prior to this Change Order 168 . 0
Net increase/decrease of this Change Order to Final Completion 84 . 0
Contract Time for Final Completion with all approved Change Orders 252 . 0
ACCEPTED : RECOMMENDED :M EN DED :
By : Z/A By : gg
CONTRACTOR ( § a r EN NEE ignature ) - Keith ully,
Hydromentia , In P . E . , Indian River County Stormwater
Engineering Division
( Name and Title ) AgI.LKyT , 14Cd I Date : — 2011
Date : 3Alzeol/
0
aa,J��d COMI��ss°"•. APPROVED :
. ,
p ' • . �0,�,�,
v . , � •,
: %Ira OWNER : Bob Solari , Chairman , indian
e
River County Board of County
too cy Commissioners
off
�. c� 000� •�p�'�
Date : MArrh 99
APPROVED AS TO FO
AN IUFF l
8Y
WILLIAM K . DEBRAAL
DEPUTY COUNTY ATTORNEY
ACCEPTED : RECOMMENDED :M EN DED :
By : Z/A By : gg
CONTRACTOR ( § a r EN NEE ignature ) - Keith ully,
Hydromentia , In P . E . , Indian River County Stormwater
Engineering Division
( Name and Title ) AgI.LKyT , 14Cd I Date : — 2011
Date : 3Alzeol/
0
aa,J��d COMI��ss°"•. APPROVED :
. ,
p ' • . �0,�,�,
v . , � •,
: %Ira OWNER : Bob Solari , Chairman , indian
e
River County Board of County
too cy Commissioners
off
�. c� 000� •�p�'�
Date : MArrh 99
APPROVED AS TO FO
AN IUFF l
8Y
WILLIAM K . DEBRAAL
DEPUTY COUNTY ATTORNEY
ATTACHMENT 1
TO CHANGE ORDER NO . 1
Request for Change in Work Order Cost
Work Order PCS =1
September 7 , 2010
Pilot Algal Turf Scrubber® for PC South
Associated with Continuing Contract for Professional Services
Dated March 15 , 2005
Amended March 4 , 2008
Between
Indian River County , Florida
and
HydrofiMentia , Inc
Submitted March 4 , 2011
ATTACHMENT 1
TO CHANGE ORDER NO . 1
Request for Change in Work Order Cost
Work Order PCS =1
September 7 , 2010
Pilot Algal Turf Scrubber® for PC South
Associated with Continuing Contract for Professional Services
Dated March 15 , 2005
Amended March 4 , 2008
Between
Indian River County , Florida
and
HydrofiMentia , Inc
Submitted March 4 , 2011
Scope :
The PC South Algal Turf Scrubber(D Pilot was implemented with the intent of
determining the applicability of the technology to meet targeted performance
goals and identifying critical performance parameters to be applied to a proposed
full scale Algal Turf Scrubber® system to be designed to provide 1 ) reduction
and recovery of nutrients from the South Canal within Indian River County , as
managed by the Indian River Farms Water Control District ( IRFWCD) and 2 )
elimination of biological toxicity associated with a Reverse Osmosis ( RO )
Concentrate . The operational protocol originally delineated for the pilot was to
dilute the RO Concentrate with the water from the South Canal at a proportion of
about 10 % RO concentrate .
The pilot investigation was initiated on 1 / 17/2011 . Laboratory data to date
provides indication that the system at the stated dilution does render the blended
water non -toxic , and is effective in removing and recovering both nitrogen and
phosphorus at rates within expected ranges . To this extent , the system appears
applicable and appropriate for meeting the project intent at a 10 % RO
Concentrate , 90 % Canal water blend
Based upon reviews by the County staff and HydroMentia of historical flow
patterns within the South Canal in the vicinity of the proposed full scale facility , it
was determined that flows within the canal would not always be sufficient to
ensure the 90 % dilution of the RO Concentrate , which is projected to have a
constant flow rate of about 1 MGD . Consequently , it was decided that based
upon the worst case low flow conditions within the canal of 1 MGD , that the most
conservative dilution would be 1 : 1 , or 50 % RO Concentrate and 50 % Canal
water . To accommodate this design feature , it was decided that the pilot system
should be adjusted to receive a 1 : 1 blend , and assessed accordingly both in
terms of nutrient removal and toxicity .
Because the shift in the influent blend will result in a significant increase in
conductivity (salinity) , it will be necessary to change the bioassay protocol from
freshwater species (fathead minnows and daphnia ) to marine/estuarine species
( mysid shrimp and menidia minnows ) . To adequately assess the toxicity of this
new blend , six additional bioassay tests will be required , using these
marine/estuarine species . Three of these will be acute tests , which if found non
toxic , will be followed by three chronic tests .
Following about 12 weeks of operation under the new blend conditions , the
system will be again returned to the 10 % RO Concentrate blend , and planned
chronic bioassay testing of the freshwater species will be completed . This revised
program will not only allow assessment of the efficacy of the technology under
these two conditions , but will permit assessment of performance during the
transitional period associated with changes in blends , during which time the algal
turf community will undergo ecological adjustments .
Scope :
The PC South Algal Turf Scrubber(D Pilot was implemented with the intent of
determining the applicability of the technology to meet targeted performance
goals and identifying critical performance parameters to be applied to a proposed
full scale Algal Turf Scrubber® system to be designed to provide 1 ) reduction
and recovery of nutrients from the South Canal within Indian River County , as
managed by the Indian River Farms Water Control District ( IRFWCD) and 2 )
elimination of biological toxicity associated with a Reverse Osmosis ( RO )
Concentrate . The operational protocol originally delineated for the pilot was to
dilute the RO Concentrate with the water from the South Canal at a proportion of
about 10 % RO concentrate .
The pilot investigation was initiated on 1 / 17/2011 . Laboratory data to date
provides indication that the system at the stated dilution does render the blended
water non -toxic , and is effective in removing and recovering both nitrogen and
phosphorus at rates within expected ranges . To this extent , the system appears
applicable and appropriate for meeting the project intent at a 10 % RO
Concentrate , 90 % Canal water blend
Based upon reviews by the County staff and HydroMentia of historical flow
patterns within the South Canal in the vicinity of the proposed full scale facility , it
was determined that flows within the canal would not always be sufficient to
ensure the 90 % dilution of the RO Concentrate , which is projected to have a
constant flow rate of about 1 MGD . Consequently , it was decided that based
upon the worst case low flow conditions within the canal of 1 MGD , that the most
conservative dilution would be 1 : 1 , or 50 % RO Concentrate and 50 % Canal
water . To accommodate this design feature , it was decided that the pilot system
should be adjusted to receive a 1 : 1 blend , and assessed accordingly both in
terms of nutrient removal and toxicity .
Because the shift in the influent blend will result in a significant increase in
conductivity (salinity) , it will be necessary to change the bioassay protocol from
freshwater species (fathead minnows and daphnia ) to marine/estuarine species
( mysid shrimp and menidia minnows ) . To adequately assess the toxicity of this
new blend , six additional bioassay tests will be required , using these
marine/estuarine species . Three of these will be acute tests , which if found non
toxic , will be followed by three chronic tests .
Following about 12 weeks of operation under the new blend conditions , the
system will be again returned to the 10 % RO Concentrate blend , and planned
chronic bioassay testing of the freshwater species will be completed . This revised
program will not only allow assessment of the efficacy of the technology under
these two conditions , but will permit assessment of performance during the
transitional period associated with changes in blends , during which time the algal
turf community will undergo ecological adjustments .
Change in Work Order Costs
Noted in Table 1 is a listing of proposed cost changes . The laboratory costs are
from direct quotes from the pre -selected laboratory , Marinco Inc , of Sarasota ,
Florida . Hourly rates for HydroMentia labor is as listed within the existing
Agreement between the County and HydroMentia .
•
Mysid /Menidia Each $ 850 3 $ 2 , 550
Acute
Bioassay '
Mysid /Menidia Each $ 2 , 900 3 r$ 8 , 700
Chronic
Bioassay
Fedex for Delivery $ 65 3 $ 195
Acute Test
Fedex for Delivery $ 140 9 $ 1 , 260
Chronic Test2
Ice for Acute 20 lb bag $4 . 00 3 $ 12
Test
Ice for 20 lb bag $4 . 00 27 $ 108
Chronic Test
A Stewart Hour $ 135 6 $ 810
Labor
R Bazurto Hour $ 85 18 $ 1 , 530
Labor
TOTAL $ 159165
1 . Three acute tests need to be shown non -toxic before proceeding with
chronic testing . This request does not include costs of additional acute tests
which might be needed .
2 . Chronic testing requires delivery of 5 gallons of composited samples on
Tuesday , Thursday and Saturday for each of the 3 tests . Samples need to
be sent one day delivery in AM .
Change in Work Order Costs
Noted in Table 1 is a listing of proposed cost changes . The laboratory costs are
from direct quotes from the pre -selected laboratory , Marinco Inc , of Sarasota ,
Florida . Hourly rates for HydroMentia labor is as listed within the existing
Agreement between the County and HydroMentia .
•
Mysid /Menidia Each $ 850 3 $ 2 , 550
Acute
Bioassay '
Mysid /Menidia Each $ 2 , 900 3 r$ 8 , 700
Chronic
Bioassay
Fedex for Delivery $ 65 3 $ 195
Acute Test
Fedex for Delivery $ 140 9 $ 1 , 260
Chronic Test2
Ice for Acute 20 lb bag $4 . 00 3 $ 12
Test
Ice for 20 lb bag $4 . 00 27 $ 108
Chronic Test
A Stewart Hour $ 135 6 $ 810
Labor
R Bazurto Hour $ 85 18 $ 1 , 530
Labor
TOTAL $ 159165
1 . Three acute tests need to be shown non -toxic before proceeding with
chronic testing . This request does not include costs of additional acute tests
which might be needed .
2 . Chronic testing requires delivery of 5 gallons of composited samples on
Tuesday , Thursday and Saturday for each of the 3 tests . Samples need to
be sent one day delivery in AM .
-y �O
3 -22-
4811 .
CHANGE ORDER NO , 1
DATE OF ISSUANCE :
EFFECTIVE DATE :
OWNER : INDIAN RIVER COUNTY
CONTRACTOR : Hydromentia , Inc .
PROJECT : Pilot Algal Turf Scrubber for PC South
ENGINEER : INDIAN RIVER COUNTY
You are directed to make the following changes in the Contract Documents :
Increase/ Decrease
Increase/ Decrease
Item Description in Contract Time
in Contract Price ( Calendar Days )
Operate the ATS pilot system using a 1 : 1
canal water to RO brine mix in
1 . 0 laccorclance with Attachment No . 1 $ 15 , 165 . 00 84 . 0
TOTALS $ 15 , 165 . 00 84 . 0
CHANGE IN CONTRACT PRICE
Description Amount
Original Contract Price $ 188, 000 . 00
Net increase/decrease from previous Change Orders $ 0 . 00
Contract Price prior to this Change Order $ 188, 000 . 00
Net increase/decrease of this Change Order $ 15 , 165 . 00
Contract Price with all approved Change Orders $ 203, 165 . 00
CHANGE IN CONTRACT TIME ( Calendar Days )
Description Amount
Original Contract Time for Final Completion 168 . 0
Net increase/decrease from previous Change Orders 0 . 0
Contract Time for Final Completion prior to this Change Order 168 . 0
Net increase/decrease of this Change Order to Final Completion 84 . 0
Contract Time for Final Completion with all approved Change Orders 252 . 0