HomeMy WebLinkAbout2010-142 � Ile
ITO1 .
AMENDMENT NUMBER 2 TO WORK ORDER NUMBER12
This Amendment Number 2 to Work Order Number 12 is entered into as of this 1 st day
of June 2010 , pursuant to that certain Continuing Contract Agreement for
Professional Services entered into as of April 6 , 2004 and amended effective April 7 , 2007
(as so amended , the "Agreement") , by and between Indian River County , a political
subdivision of the State of Florida (" County") and MASTELLER & MOLER , INC .
(" CONSULTANT") .
1 . The County has selected the Consultant to perform the professional services set
forth in existing Work Order Number 12 , Effective Date April 8 , 2008
2 . The County and the Consultant desire to amend this Work Order as set forth on
Exhibit 1 attached to this Amendment and made a part hereof by this reference . The
professional services will be performed by the Consultant for the fee schedule set forth in
Exhibit 2 and within the timeframe more particularly set forth in Exhibit 3 , all in accordance
with the terms and provisions set forth in the Agreement.
3 . From and after the Effective Date of this Amendment , the above- referenced Work
Order is amended as set forth in this Amendment . Pursuant to paragraph 1 . 4 of the
Agreement , nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each
individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Amendment to Work
Order as of the date first written above .
�M� S S i OPrF�s.,•y
CONSULTANT: BOARD OF COUNTY COMMISSIONE�F�,�, • • .o
MAST LER & MOLER , INC . OF INDIAN RIVER COUNTY ;° :•
• a Q :
a
o • C
By . Stephen E . Moler, PE By Peter D . O' Bryan , Chairm :� ,,'
Title : Vice President BCC Approved Date : June 1 , 2010 ,PIVER �
Date : 5/10/2010 Attest: J . K . Barton , Clerk of Court
By
Deputy C erk
Approved :
Jose . Baird , County Administrator
Approved as to form and legal sufficiency :
Com,--� -�------�
County Attorney
Our File #0770
May 10 , 2010
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT #2 TO WO #12
" EXHIBIT 1 "
Work Authorization # 12 , which was approved by the Board of County Commissioners , includes
Engineering Services in connection with the design and construction of 3 . 0 million gallon reuse
water ground storage tank and related pump station to facilitate reuse service to North Indian
River County . Amendment # 1 was approved to authorize Engineering Services related to
Reuse Water Alternative Services .
IRCDUS staff, after reviewing the design of the Facility as completed under the original Work
Order, has determined that additional features must be added to the design of the Facility in
order to ensure a successful project . The incorporation of these additional features into the
project ' s Construction Plans and Specifications shall require additional professional services not
included in the original contract .
This Amendment #2 is therefore presented to include tasks for additional professional services
necessary to support remote Facility monitoring and control functions , pump station control
panel upgrades , and security fencing .
A brief description of the scope of services and deliverables for Work Authorization # 12 ,
Amendment #2 is provided below:
Scope of Services
I . DESIGN SERVICES
Task A — Pumping and Storage Systems —
Task I (A) shall be revised to include design services for the following additional features :
1 . Conduit System - It is understood the County desires to provide for Remote Facility
Monitoring and Control of the pump station . In order to support that system , we shall
modify our Construction Plans to illustrate the design of a 2" - inch diameter conduit from
the proposed pump station to the north side of the existing Parks and Recreation
building between the Facility and the Lateral G Canal . The conduit is intended to support
installation of a fiber-optic cable between these two locations . The design of the conduit
shall be coordinated with the IRC Telecommunications Division . It is understood that the
IRC Telecommunications Division shall select and install the fiber optic cable including
providing the appropriate terminations in the proposed pump station building and at the
existing fiber optic panel on the Parks and Recreation Site .
The conduit and fiber-optic cable installation will support the ability for the County to
remotely monitor and operate the pump station . The coordination and preparation of any
specifications for the programming , hardware and software modifications shall be
completed by the County .
AMENDMENT #2 TO EXHIBIT # 1
5/ 10/2010
Page 2
2 . NEMA 3 Control Panel — We shall modify the Construction Plans and specifications to
require NEMA 3 control panels in the pump station building to provide additional water
intrusion protection over the NEMA 1 panels originally specified .
11 . LAND SURVEY SERVICES
In order to support the design of the fiber-optic conduit described in Task I (A) , above , Task II of
the original work order shall be revised to include a limited topographic survey of the Parks and
Recreation site . The survey shall illustrate the existing building and other features along the
proposed route of the conduit .
The survey data collected as part of this task shall be incorporated into the survey performed as
part of the original scope of services .
III . SITE PLAN PERMITTING SERVICES ( NORTH PLANT SITE )
( No additional services proposed . )
IV. CONSTRUCTION SERVICES ( NORTH PLANT SITE )
The scope of services described in Task IV of the original work order will be expanded by
construction of the additional features described in Task I (A) , above . This task is therefore
revised to include the additional construction services required .
Y: \mm\Projects\2007\0770\0770_LAWDMIN\ContractsWMENDMENT #2\0770LA_Exhibit 1 _Amen#2_Rev #2 .doc
Our File #0770
May 10 , 2010
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT #2 TO WO #12
" EXHIBIT 2 "
Method and Amount of Compensation
Masteller & Moler, Inc . proposes to provide the above Scope of Services based on the following lump
sum fees :
Original Amend #1 Amend #2 Total
Fee Fee Fee Fee
I . DESIGN SERVICES :
Addition of Engineering Construction
Plans ; preparation of Specifications and
Bid Documents . $ 191 , 885 . 00 $ 0 . 00 $ 31200 . 00 $ 195 , 085 . 00
IL SUB -CONSULTANT SPECIALIZED SERVICES :
Land Surveying $ 20 , 800 . 00 $ 0 . 00 $ 21500 . 00 $ 23 , 300 . 00
Soils Investigations $ 71200 . 00 $ 0 . 00 $ 0 . 00 $ 71200 . 00
Structural Engineering Design $ 51500 . 00 $ 0 . 00 $ 0 . 00 $ 51500 . 00
Electrical Engineering Design $ 3 , 200 . 00 $ 0 . 00 $ 0 . 00 $ 31200 . 00
life SITE PLAN PERMITTING SERVICES $ 20 , 000 . 00 $ 0 . 00 $ 0 . 00 $ 20 , 000 . 00
( North Plant Site ) :
IV. CONSTRUCTION SERVICES :
Expand Assistance during Bidding , Bid
Evaluation , Contract Award & Construct-
ion Administration & Periodic
Administration & Periodic Construction
Field Observation $ 73 , 262 . 00 $ 0 . 00 $ 11200 . 00 $ 74 , 462 . 00
V. PRELIMINARY ENGINEERING REPORT :
Collect, Compile, and Analyze Existing
Water Quality & Irrigation Data ; Review
Available Minimum Flows Information ;
Prepare Alternative Reuse Water Concept
Plan ; Develop Preliminary TMDL
Estimate ; Meet FDEP & SJRWMD ;
Develop Budget Capital Construction Cost
Estimates $ 0 . 00 $ 49 , 000 . 00 $ 0 . 00 $ 49 , 000 . 00
Totals $ 3219847 .00 $ 499000 .00 $ 6 ,900 .00 $377 , 747 .00
Our File #0770
May 10 , 2010
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT #2 TO WO # 12
" EXHIBIT #3 "
• Time of Performance
The estimated time frame for completion of services from the approval of this Amendment #2 to Work
Order # 12 is as follows :
MILESTONE COMPLETION
Task I (A) — Design Services 30 days
Task II — Land Survey Services 15 days
Task III — Site Plan Permitting 30 days
Note : Since the Pumping and Storage Facility project is otherwise prepared to bid we shall execute the
scope of services described in Amendment #2 as expeditiously as possible .
Y:\mm\Projects\2007\0770\0770_LA\ADMIN\Contracts\AMENDMENT #2\0770LA.Exhibit 3 Amen#2_Rev #2.doc