HomeMy WebLinkAbout2011-155 AMENDMENT NUMBER 1 TO WORK ORDER NUMBER 13
torr -
This Amendment Number 1 to Work Order Number 13 is entered into as of this 12 day
of July 20 1j pursuant to that certain Continuing Contract Agreement for
Professional Services entered into as of April 6 , 2004 and amended effective April 7 , 2007
(as so amended , the "Agreement" ) , by and between INDIAN RIVER COUNTY , a political
subdivision of the State of Florida ( " County " ) and MASTELLER & MOLER , INC .
( " CONSULTANT" ) .
1 . The County has selected the Consultant to perform the professional services set
forth in existing Work Order Number 13 , Effective Date October 21 , 2008 .
2 . The County and the Consultant desire to amend this Work Order as set forth on
Exhibit 1 attached to this Amendment and made a part hereof by this reference . The
professional services will be performed by the Consultant for the fee schedule set forth in
Exhibit 1 and within the timeframe more particularly set forth in Exhibit 1 , all in accordance
with the terms and provisions set forth in the Agreement .
3 . From and after the Effective Date of this Amendment , the above- referenced
Work Order is amended as set forth in this Amendment . Pursuant to paragraph 1 . 4 of the
Agreement , nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each
individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Amendment to
Work Order as of the date first written above .
CONSULTANT: BOARD OF COUNTY COMMISSIONERS
MAST R & MOLER , INC . OF INDIAN RIVER COUNTY
By : By : L� C C",--
St phen E . Moler , PE Bob Solari , Chairman
Title : Vice President
BCC Approved Date : July 12 , 2011
Date : CZ4
Attest : J . K. Baron , Clerk of Court
poaaoanaoa
°°°a�° ����s�pOea° By :
1Q o . o • a . oese • A O
p/����� • ° •.�!F�°°° Deputy Clerk
6 ° °*0
Ve : °P
• a Appr . ed :
e
g
0 0°
J seph AlBaird , County Administrator
oe��•• . .•
e° � • • . . ueN • pe
°ee ;fRpCOtl ,aa°°°° App d s to form an e s fficiency :
7
:
y
B
°n
W � f( r-ru k. 4,sr�j ChOX04,/County Attorney
AMENDMENT NUMBER 1 TO WORK ORDER NUMBER 13
torr -
This Amendment Number 1 to Work Order Number 13 is entered into as of this 12 day
of July 20 1j pursuant to that certain Continuing Contract Agreement for
Professional Services entered into as of April 6 , 2004 and amended effective April 7 , 2007
(as so amended , the "Agreement" ) , by and between INDIAN RIVER COUNTY , a political
subdivision of the State of Florida ( " County " ) and MASTELLER & MOLER , INC .
( " CONSULTANT" ) .
1 . The County has selected the Consultant to perform the professional services set
forth in existing Work Order Number 13 , Effective Date October 21 , 2008 .
2 . The County and the Consultant desire to amend this Work Order as set forth on
Exhibit 1 attached to this Amendment and made a part hereof by this reference . The
professional services will be performed by the Consultant for the fee schedule set forth in
Exhibit 1 and within the timeframe more particularly set forth in Exhibit 1 , all in accordance
with the terms and provisions set forth in the Agreement .
3 . From and after the Effective Date of this Amendment , the above- referenced
Work Order is amended as set forth in this Amendment . Pursuant to paragraph 1 . 4 of the
Agreement , nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each
individual Work Order as if fully set forth herein .
IN WITNESS WHEREOF , the parties hereto have executed this Amendment to
Work Order as of the date first written above .
CONSULTANT: BOARD OF COUNTY COMMISSIONERS
MAST R & MOLER , INC . OF INDIAN RIVER COUNTY
By : By : L� C C",--
St phen E . Moler , PE Bob Solari , Chairman
Title : Vice President
BCC Approved Date : July 12 , 2011
Date : CZ4
Attest : J . K. Baron , Clerk of Court
poaaoanaoa
°°°a�° ����s�pOea° By :
1Q o . o • a . oese • A O
p/����� • ° •.�!F�°°° Deputy Clerk
6 ° °*0
Ve : °P
• a Appr . ed :
e
g
0 0°
J seph AlBaird , County Administrator
oe��•• . .•
e° � • • . . ueN • pe
°ee ;fRpCOtl ,aa°°°° App d s to form an e s fficiency :
7
:
y
B
°n
W � f( r-ru k. 4,sr�j ChOX04,/County Attorney
Our File # 0831 LG
June 27 , 2011
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT # 1 TO W0# 13
" EXHIBIT 1 "
The Indian River County Utilities Department has decided to amend Work Authorization # 13
which was approved by the Board of County Commissioners on October 21 , 2008 . The original
project involved Engineering Services in connection with conversions of an existing 16" brine
main , an existing 12 " force main , and an existing 12 " potable water main to reuse mains . The
Brine Main Project' s design/as- built drawings were used to design the proposed connection
between the brine line and force main just west of the beginning of the Wabasso Causeway (SR
510 ) . The original design plans for the brine line reveal the existing force main to be located to
the south of an existing Johns Island irrigation main and next to the existing brine mains . In the
field , however , Contractor' s excavations have revealed thhe f,,��"" a ai to be located north of the
existing irrigation main and under the existing SR .n ei�sW i banes . The irrigation mains
position between the existing brine main and force main requires a change to the proposed
connection between reuse facilities . This Amendment , therefore , provides for Engineering
Services to modify the design of the brine/force main and brine/water connections including
structural engineering for design of pipe stanchions to support 12 " , 16 " , and 18" diameter pipes
to be placed on the most westerly headwall beneath the Wabasso Causeway . The additional
services covered by this Amendment # 1 to the project will generally consist of the following
revisions to the original project :
• Scope of Services
L DESIGN SERVICES
Task A — Reuse Main Improvements
1 . Conversion of Existing Mains into Reuse Mains
Masteller & Moler , Inc . will provide for the necessary modifications to the Contract
Construction Plans covering the following project Modifications and Additions :
d . Modify the design of the brine to force main connection and brine to water main
connection to all be converted into reuse mains at the west Wabasso Causeway
Bridge . Design modification will require structural engineering services to be
completed by ML Engineering .
Ill. PERMITTING SERVICES
Task A (d ) — Brine to WM / FM Connections
Coordinate with the FDOT to obtain a permit modification for the revised design .
Our File # 0831 LG
June 27 , 2011
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT # 1 TO W0# 13
" EXHIBIT 1 "
The Indian River County Utilities Department has decided to amend Work Authorization # 13
which was approved by the Board of County Commissioners on October 21 , 2008 . The original
project involved Engineering Services in connection with conversions of an existing 16" brine
main , an existing 12 " force main , and an existing 12 " potable water main to reuse mains . The
Brine Main Project' s design/as- built drawings were used to design the proposed connection
between the brine line and force main just west of the beginning of the Wabasso Causeway (SR
510 ) . The original design plans for the brine line reveal the existing force main to be located to
the south of an existing Johns Island irrigation main and next to the existing brine mains . In the
field , however , Contractor' s excavations have revealed thhe f,,��"" a ai to be located north of the
existing irrigation main and under the existing SR .n ei�sW i banes . The irrigation mains
position between the existing brine main and force main requires a change to the proposed
connection between reuse facilities . This Amendment , therefore , provides for Engineering
Services to modify the design of the brine/force main and brine/water connections including
structural engineering for design of pipe stanchions to support 12 " , 16 " , and 18" diameter pipes
to be placed on the most westerly headwall beneath the Wabasso Causeway . The additional
services covered by this Amendment # 1 to the project will generally consist of the following
revisions to the original project :
• Scope of Services
L DESIGN SERVICES
Task A — Reuse Main Improvements
1 . Conversion of Existing Mains into Reuse Mains
Masteller & Moler , Inc . will provide for the necessary modifications to the Contract
Construction Plans covering the following project Modifications and Additions :
d . Modify the design of the brine to force main connection and brine to water main
connection to all be converted into reuse mains at the west Wabasso Causeway
Bridge . Design modification will require structural engineering services to be
completed by ML Engineering .
Ill. PERMITTING SERVICES
Task A (d ) — Brine to WM / FM Connections
Coordinate with the FDOT to obtain a permit modification for the revised design .
Our File # 0831 LG
June 27 , 2011
NON - EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT # 1 TO WO # 13
" EXHIBIT 2 "
Method and Amount of Compensation
Masteller & Moler , Inc . proposes to provide the above Scope of Services based on the following lump
sum fees :
I . DESIGN SERVICES :
Provide for Engineering Design ; Preparation of Original Amendment # 1 Total
Specifications & Bid Documents Utilizing Fee Fee Increase Fee
Standard IRC Bid Documents . Forms ,
Documents & Drawings will be in electronic
Format Acad & MS Word
Task A ( 1 abcd ) - Reuse Main Conversions
Engineering Design $ 24 , 520 . 00 $ 4 ,400 . 00 $ 28 , 920 . 00
Task B (2abcd ) - Reuse Main Improvements
Engineering Design $ 28 , 814 . 00 $ 0 . 00 $ 28 , 814 . 00
11 . LAND SURVEYING SERVICES : $ 169300 . 00 $ 0 . 00 $ 167300 . 00
III , PERMITTING
Task A ( 1 abcd ) - Brine to WM / FM Connections :
Indian River County / FDOT Utility Right-of-way $ 0 . 00 $ 500 . 00 $ 500 . 00
Permit
Task A (2d ) -State Highway AM 8" Reuse Main :
Florida DOT Utility Permit $ 0 . 00 $ 0 . 00 $ 0 . 00
IV , CONSTRUCTION SERVICES :
Assistance during Bidding , Bid Evaluation ,
Contract Award & Construction Administration ;
Periodic Administration and Periodic
Construction/Field Observation
Task A ( 1 abcd ) - Reuse Main Conversions
Construction Services $ 81500 . 00 $ 0 . 00 $ 81500 . 00
Task B (2abcd ) - Reuse Main Improvements
Construction Services $ 13 , 124 . 00 $ 0 . 00 $ 13 . 124 . 00
Totals $ 91 , 258 . 00 $ 41900 . 00 $ 961158 .00
Our File # 0831 LG
June 27 , 2011
NON - EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT # 1 TO WO # 13
" EXHIBIT 2 "
Method and Amount of Compensation
Masteller & Moler , Inc . proposes to provide the above Scope of Services based on the following lump
sum fees :
I . DESIGN SERVICES :
Provide for Engineering Design ; Preparation of Original Amendment # 1 Total
Specifications & Bid Documents Utilizing Fee Fee Increase Fee
Standard IRC Bid Documents . Forms ,
Documents & Drawings will be in electronic
Format Acad & MS Word
Task A ( 1 abcd ) - Reuse Main Conversions
Engineering Design $ 24 , 520 . 00 $ 4 ,400 . 00 $ 28 , 920 . 00
Task B (2abcd ) - Reuse Main Improvements
Engineering Design $ 28 , 814 . 00 $ 0 . 00 $ 28 , 814 . 00
11 . LAND SURVEYING SERVICES : $ 169300 . 00 $ 0 . 00 $ 167300 . 00
III , PERMITTING
Task A ( 1 abcd ) - Brine to WM / FM Connections :
Indian River County / FDOT Utility Right-of-way $ 0 . 00 $ 500 . 00 $ 500 . 00
Permit
Task A (2d ) -State Highway AM 8" Reuse Main :
Florida DOT Utility Permit $ 0 . 00 $ 0 . 00 $ 0 . 00
IV , CONSTRUCTION SERVICES :
Assistance during Bidding , Bid Evaluation ,
Contract Award & Construction Administration ;
Periodic Administration and Periodic
Construction/Field Observation
Task A ( 1 abcd ) - Reuse Main Conversions
Construction Services $ 81500 . 00 $ 0 . 00 $ 81500 . 00
Task B (2abcd ) - Reuse Main Improvements
Construction Services $ 13 , 124 . 00 $ 0 . 00 $ 13 . 124 . 00
Totals $ 91 , 258 . 00 $ 41900 . 00 $ 961158 .00
Our File #0831 LG
June 27 , 2011
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT # 1 TO WO # 13
" EXHIBIT #3 "
• Time of Performance
The estimated time frame for completion of services from the approval of this Amendment # 1 to Work
Authorization # 13 is as follows :
MILESTONE COMPLETION DATE
Engineering Design &
Preparation of Construction Plans 10 Days
Coordination with FDOT & approval 10 Days
Our File #0831 LG
June 27 , 2011
NON -EXCLUSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
AMENDMENT # 1 TO WO # 13
" EXHIBIT #3 "
• Time of Performance
The estimated time frame for completion of services from the approval of this Amendment # 1 to Work
Authorization # 13 is as follows :
MILESTONE COMPLETION DATE
Engineering Design &
Preparation of Construction Plans 10 Days
Coordination with FDOT & approval 10 Days