March 14 , 2011
Mr Erik Olson
Indian River County Department of Utility Services
1801 27th Street
Vero Beach, FL 32960
Subject : Proposal / Contract for Professional Engineering Services
Indian River County,,,South County WWTF , Permit Renewal , ID# FLA010435
Indian River County , Florida
Engineer' s Project Number : 1. 1 - 184
Dear Mr. Olson :
At your request, we are hereby submitting our proposal to provide professional services for the
above subject project .
PROJECT DESCRIPTION
According to the Florida Department of Environmental. Protection (FDEP) Wastewater
Treatment Facility (WWTF) records, the Indian River County, South County WWTF , Operating
Permit (FLA010435 ) will expire on July 15 , 2012 . Rule 62 - 620 . 335 of the Florida
Administrative Code (F . A . C . ) requires that all wastewater treatment facilities renew the FDEP
Operating Permit every five years . Applications for permit renewal must be submitted to the
appropriate FDEP office six months prior to the expiration of the FDEP Permit . Therefore , the
renewal application for the Indian River County , South County WWTF , is due on or before
January 15 , 2012 . The following scope is provided to address these items .
SCOPE OF SERVICES
Task 1 — Site Inspection
MBV Engineering, Inc . will conduct the required site inspections to inspect the site and meet
with the plant operators . The inspections will include an evaluation of the following :
1 . The general condition of the facility
2 . Component, system, and process reliability standards as required by Rule 17 -
600 . 400 ( 1 )(b) , F . A. C .
3 . Component, system , and process operations
4 . Hydraulic and organic loading
5 . Safety features
1835 20th Street 1600 W. Eau Gallie Blvd . , Suite 203 806 Delaware Avenue
Vero Beach , FL 32960 Melbourne , FL 32935 Ft. Pierce , FL 34950
772. 569 .0035 32 1 .253 . 15 10 772.468 . 9055
Fax: 772. 778 . 3617 Fax: 321 . 253 . 091 1 Fax: 772. 778 . 36 17
Mr . Erik Olson
March 14 , 2011
Page 2
Proposal : 11 - 184
6 . Operator certifications
7 . Facility maintenance program
8 . Facility records
9 . Sampling procedures
10 . Laboratory analysis procedures
Task 2 — Tabulation and Analysis of Plant Operating Data
MBV Engineering, Inc . will tabulate and analyze , as required by FDEP , historical plant
operating data, which documents plant operating conditions for the duration of the current
operating permit . Plant operating data will be provided by Indian River County Utilities (IRCU)
staff as specified in the "Information Provided by Owner" section found within this Scope of
Services .
Task 3 — Preparation and Submittal of )FDEP Permit Renewal Application
MBV Engineering, Inc will prepare and provide to FDEP and IRCU , the following applications
and forms necessary to obtain the facility ' s required operating permit .
1 . FDEP Wastewater Facility or Activity Permit Form 1 , (DEP Form 62 - 620 . 910 ( 1 ))
2 . FDEP Wastewater Facility or Activity Permit Form 2A (DEP Form 62 - 620 . 910 (2 ))
Task 4 — Preparation of FDEP Required Backup Documentation
MBV Engineering, Inc . will provide to FDEP and IRCU the following backup documents , maps ,
and diagrams that are necessary to obtain the facility ' s required operating permit .
1 . Process Flow Diagram
2 , Site Plan
3 . Location and Vicinity Maps
4 . Facilities Description
Task 5 — Preparation of )FDEP Required Capacity Analysis Report
MBV Engineering, Inc . will prepare a Capacity Analysis Report in accordance with Rule 17 -
600 . 405 , F . A . C . This report will document the permitted plant capacity , along with our analysis
and evaluation of the Indian River County , South County WWTF flows and current plant
capacity .
Task 6 — Preparation of FDEP Required Operation and Maintenance Performance Report
MBV Engineering, Inc will prepare an Operation, Maintenance and Performance Report, in
accordance with Rule 17 -600 . 735 , F . A . C . This report will document the capability of the Indian
oa
Mr. Erik Olson
March 14 , 2011
Page 3
Proposal : 11 - 184
River County, South County wastewater treatment, reuse , and disposal facilities to function as
intended during the period for which the permit is requested .
SCHEDULE
MBV Engineering, Inc will prepare the permit renewal application in a timely manner . The
renewal application for the Indian River County , South County WWTF and all supporting
documentations specified above will be submitted to FDEP and IRCU on or before January 15 ,
2012 ,
FEES
MBV Engineering, Inc will provide these services for a lump sum fee as follows :
Task No . Task Task Fee
Task 1 Site Inspection $2 , 250
Task 2 Tabulation of Plant Operating Data $ 2 , 500
Task 3 Preparation and Submittal of FDEP Permit Renewal Application $ 2 , 500
Task 4 Preparation of FDEP Required Backup Documentation $45500
Task 5 Preparation of Capacity Analysis Report $ 5 , 500
Task 6 Preparation of Operation , Maintenance , and Performance Report $ 3 , 500
Total Lump Sum Fee = $20 , 750
This fee schedule assumes the subject plant is not under enforcement action , has no outstanding
violations and is operating with no deficiencies . Should involvement with enforcement action or
violation be required and/or should responses to FDEP be required to address plant deficiencies
resulting from the permit submittal , our services will be available on an hourly basis .
ADDITIONAL, SERVICES
Tne following services are not included in the Scope of Services for this project, but may be
required depending on circumstances that may arise during the execution of this project .
Additional services include , but may not be limited to the following :
® Additional site visits that are not described in the Scope of Services
® Attendance at meetings that are not described in the Scope of Services
e Reponses to agency requests for additional information beyond what is listed herein
e Research of FDEP/client files to obtain information necessary for permitting
® Preparation of updated Effluent Disposal and Reclaimed Water Use Protocol (if requested by
FDEP)
e Preparation of updated Reuse Feasibility Study ( if requested by FDEP)
Mr . Erik Olson
March 14 , 2011
Page 4
Proposal : 11 - 184
® Preparation of updated Operation & Maintenance Manual (if requested by FDEP )
REQUIRED INFORMATION TO BE PROVIDED BY OWNER :
The Owner shall provide the following information related to the Indian River County, South
County, Wastewater Treatment Facility , FDEP Permit Renewal :
• Access to the facility for site inspection(s)
0 Last 4 years of DMRs
® Current operating permit
® Residuals Dewatering Permit
® Current Reclaimed Water or Effluent Analysis Report
® Current Effluent Disposal and Reclaimed Water Use Protocol
® Current Reuse Feasibility Study
O RPZ certification (s)
e Flow meter calibration report(s)
® Violations / Inspections from FDEP
® List of Modifications to WWTF since the last permit renewal (2006 )
® Agreements with Individual Users of Reclaimed Water
® Current Reclaimed Water or Effluent Analysis Report
® Operation Manager ' s name & certification number
® Chief Plant Operator ' s name & certification number
® Sample Testing Laboratory — Name , Address & Certification Number
® Year facility was placed into service
® Name and title of person signing applications for renewal
® Residual Hauler Agreement — Facility information : name , address , phone , ID number, and
treatment process
Y Provide existing facility volumes (i . e . aeration basins, - chlorine contact chamber, etc . ) either
from design plans or recent permit renewal plans .
REQUESTED INFORMATION TO BE PROVIDED BY OWNER (if available) :
The Consultant requests that Owner provide the following information, if available , in an effort
to expedite the preparation and submittal of the permit renewal application :
® Copy of the current permit ' s Operation & Maintenance Report
® Copy of the current permit' s Capacity Analysis Report
® Copy of the Facility ' s current Operation and Maintenance Manual
® Facility Process Flow Diagram
a°
Mr. Erik Olson
March 14 , 2011
Page 5
Proposal : 11 - 184
® Current Service Area Map
® Copy of Design Plans
Invoices for our services will be billed upon submittal of the FDEP Permit Renewal Application,
with payment due upon your receipt of the invoice . A service charge of 1 - /2 % per month will be
billed for late payments .
We are available to begin work described herein upon our receipt of your written acceptance of
this proposal /contract. i his proposai is valid if accepted within ninety (90) days from the date of
this proposal/contract .
Should you require further information or clarification , please contact our office .
Sincerely,
MBV EN EERING, INC .
Aaron Bowles , P . E . , Vice President Witness
AJB/jeh
Accepted this 5th day of July 20 1. 1
g eooaaoaoab°oog0
Signature Bob Solari , Chat rtomRNfss Witness
to
• Qy°ee
O
c
a
O b
b b
O p
II < b
gyp• e. �
G a/ •. OQO
• OQe°°
° ee
cou ` pee e
°pbb bbebbepe