HomeMy WebLinkAbout2011-087 p 1�
INDIAN RIVER COUNTY
Change Order No . 4 O
PROJECT : SECTOR 3 BEACH AND DUNE RESTORATION
CONTRACTOR RANGER CONSTRUCTION INDUSTRIES , INC .
4510 GLADES CUT- OFF ROAD
FT . PIERCE , FL 34921
Ranger Construction Industries , Inc . (Ranger and Contractor) has requested an additional
payment of $ 1 . 01 per cubic yard , as a fuel price adjustment, to account for increases in the cost
of diesel fuel during the construction of the Sector 3 Beach and Dune Restoration Project
(Project) . The additional $ 1 . 01 per cubic yard was requested by Ranger to cover the increase in
fuel costs experienced by Ranger since the project was bid in August, 2009 .
On March 15 , 2011 , the Board of County Commissioners designated March 23 , 2010 as the
baseline date for fuel price adjustments , and $ 3 . 00 per gallon as the baseline cost of diesel fuel .
On March 23 , 2010 , Ranger agreed to freeze the price of all remaining Phase 1 and Phase 2 sand
at $ 15 . 66 per cubic yard , and diesel fuel sold at an average of $ 3 . 00 per gallon on that date .
To account for fluctuating fuel prices , tinder this change order, a weekly average fuel cost will be
used to determine all fuel adjustments for "Ultra Low Sulfur Fuel " , as updated and published
weekly by the U . S . Energy Infonnation Administration (EIA) for the lower Atlantic region ,
including Florida . Subject to the maximum increase set forth below , fuel prices above $ 3 . 00 will
be applied as an additional payment to Ranger while fuel prices below $ 3 . 00 will be applied as a
credit to the County .
All fuel adjustments will be applied following verification of sand (cubic yards) surveyed on the
beach via the pay profiles prescribed by the Contract Documents .
The maximum per cubic yard fuel adjustment increase , as applied by this change order, shall not
exceed $ 1 . 01 per cubic yard or a total price to process , haul , place , and grade the sand of $ 16 . 67
per cubic yard . Fuel adjustments will only apply to the sand required to complete Phase 2 of the
Project . Based on the January, 2011 survey, the estimated sand volume to complete Phase 2 is
261 , 077 cubic yards . This change order shall not apply to the remaining sand to complete Phase
1 of the Project (estimated in the January, 2011 survey to be 19 , 129 cubic yards) .
p <i
Sector 3 Beach and Dune Restoration Project Page 2 of 4
Change Order No . 4
Fuel Consumption
Ranger ' s request cites three (3 ) elements of construction and identifies the corresponding fuel
consumption rate ( gallons per cubic yard) as follows :
1 . Tricking — transporting sand from the mine to the beach = 0 . 267 gal /CY
2 . Dredging and Processing — processing and refining to produce beach compatible sand
= 0 . 576 gal/cy
3 . Construction — place and grade sand on the beach = 0 . 191 gal/cy
The total fuel consumption rate = 1 . 034 gal/cy . Therefore, the percentage of the total
consumption rate for each element of construction is as follows :
1 . Trucking = 25 . 82 %
2 . Dredge and Processing = 55 . 71 %
3 . Constriction = 18 . 47 %
Fuel Price Adiustment
To determine the applicable fuel price adjustment (increase or decrease as a price per cubic yard)
to be applied under this change order, the total fuel consumption rate of 1 . 034 gallons per cubic
yard is to be multiplied by the difference in fuel price between the March 2010 baseline rate of
$ 3 . 00 per gallon and the current weekly fuel index (published each Monday by EIA) for the
corresponding week that sand is placed on the beach — be the date of the post- fill survey, where
the applicable weekly quantities of Phase 2 sand are to be determined from the pay profiles .
For example, with the weekly price of fuel for the week ending March 7 , 2011 at $ 3 . 85 per
gallon, the cost to truck, dredge and process , and place sand along a portion of Phase 2 would
increase by $ 0 . 88 per cubic yard — per the breakdown described below :
a) Trucking = $ 0 . 23 per cubic yard
( $ 3 . 85 /gal - $ 3 . 00/gal) x 0 . 267 gal/cy = $0. 23per cubic yard
b) Dredging_/processing = $ 0 . 49 per cubic yard
($ 3 . 85 /gal - $ 3 . 00/gal) x 0 . 576 gal/cy = $ 0 .49 per cubic yard .
c) Construction = $ 0 . 16 per cubic yard
( $ 3 . 85 /gal - $ 3 . 00/gal) x 0 . 191 gal/cy = $ 0 . 16 per cubic yard .
Total = $ 0 . 88 per cubic yard
Sector 3 Beach and Dune Restoration Project Page 3 of 4
Change Order No . 4
Adiusted price per cubic yard Not-To-Exceed
Notwithstanding any language herein to the contrary, the maximum per cubic yard increase, as
applied by this change order, shall not exceed $ 1 . 01 per cubic yard or a total maximum price to
process , haul, place , and grade the sand at $ 16 . 67 per cubic yard.
Based on the January, 2011 survey, the estimated sand volume required to complete Phase 2 is
261 , 077 cubic yards . Therefore based on the most recent survey, the maximum fuel adjustment
payment to Ranger would be $ $ 263 , 687 . 77 ( $ 1 . 01 per cubic yard x 261 , 077 cubic yards) .
By execution of this change order, Ranger confirms that the maximum per cubic yard price for
all remaining sand in the Phase 2 area ( 261 , 077 cubic yards and any additional. amounts required
to complete the Phase 2 area) is $ 15 . 66 , plus or minus the fuel adjustment , up to a maximum
price of $ 16 . 67 ( $ 15 . 66 , plus the fuel adjustment not to exceed $ 1 . 01 ) .
Retainage will not be withheld at the time of payment under this Change Order for fuel
adjustments . However, retainage will be withheld from total payment for the work under the
terms of the current contract .
CURRENT CONTRACT PRICE $ 1. 05319 , 233 . 90
MAXIMUM NET CHANGE IN CONTRACT PRICE
DUE TO THIS CHANGE ORDER $ $ 2633687 . 77
CONTRACT COMPLETION DATE 4/30/ 11
MAXIMUM CONTRACT PRICE INCLUDING
THIS CHANGE ORDER $ 10, 582 , 920
Sector 3 Beach and Dune Restoration Project Page 4 of 4
Change Order No . 4
ENGINEER ' S RECOMMENDATION
I have examined the above changes . The price changes are reasonable and I recommend that the
changes be made .
Engineer :
Witness : COASTAL TECHNOLOGY CORPORATION
r
�� � By: G'',
�& i/
Print Name : �_ 1, « �( c � 1 l—mhta� ` Michael P . Walther, President
CONTRACTOR' S APPROVAL
I agree that the above changes in said Contract, in accordance with Specifications for the price
changes shown are satisfactory.
Contractorz
Wit ss : RANGER CONSTRU I TRIES
By :
Print Name : 42 / � _ Bob Schafer, Vice Preside t
Date : A V ; , 2011
BOARD OF COUNTY COMMISSIONERS ,
ATTEST : Jeffrey K . Barton , Clerk of Court INDIAN RIVER COUNTY, FLORIDA
B Y : �-\ x�°�`° . (% ^�' By : !�Deputy Clerk Clerk Bob Solari, Chairman
p0 ytl•N • • I.tl.p*
Approved : *sotl60NOso
���
otlo«VO''• � •' G:���u
•p � 8• i tl0
By: tl 8
p
6 eph A . aird, County Admini trator
A oved as to form and le ficiency. SO
o • •. �o
41*4v 04,
- �tltltltltltltltltltltl��
a/
By :
Alan S . Polackwich, r . , County Attorney