HomeMy WebLinkAbout2010-008CHANGE ORDER
PROJECT Spoonbill Marsh Wetland Facility
DATE OF ISSUANCE 10/22/09
EFFECTIVE DATE 10/22/09
No. 4
OWNER: Indian River County Utilities
OWNER's Contract No. UCP 2785 ENGINEER: Masteller & Moler. Inc.
CONTRACTOR: Timothy Rose Contracting ENGINEER Project No. 0544LH
You are directed to make the following changes in the Contract Documents:
Description: IRCUD request additions and contract time extension
Reason for change order: IRCUD added pump station electrical service main disconnect.
i
\ttachments: List documents supporting chane
Contractors
Request
Exhibit.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times
$ 21211,870.00
Substantial Completion: March 1, 2009
Ready for final payment: March 19, 2009
Days or dates
Net changes from previous Change Orders
Net change from previous Change Orders
No. 1 to No. 3
No. 2 to No. 3
$152,845 a30
134 days
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$2,265,715 30
Substantial Completion: July 13, 2009
Ready for final payment: See Note
Das or dates
Net Increase (decrease) in this Change Order
Net Increase in this Change Order
$ 19,494.00
155 da s
Contract Price with all approved Change
Contract Time with all approved Change
Orders
Orders
Substantial Completion: December 15, 2009
$ 2,285,209.30
Ready for final payment: See Note
Days or dates
Note: To be based on receipt of clearance for operation and testing from the FDEP WW Division and
FDEP Environmental Resources Department and acceptance of the s;teby 'Indian River County_
RECOMMENDED:
By
Engineer . .
APPROVED:
t
By. ,
Owner (Authorized Sign re)
Peter D. O'Bryan, Chairman
Date: o1 /o5/1 o
ACCEPTED: .
Co Authorized Signature)
Date: / �7 --, /0 D 7
EJCDC No. C-700 (2002 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General
Contractors of America
/ `•
Y
October 22, 2009
Indian River County
Attn: Art Pfeffer
RE: Spoonbill Marsh Wetland
REQUESTED CHANGE ORDER
Change Order Proposal For Additional Work Per IRCO:
Add Item # 15 — Meyers Hub Add: $ 11023.00
Add Item # 17 — Three Phase SS Disconnect Add: $18,471.00
Total Proposed Change Order $19,494.00
Time:
Addition of Days
155 Days
Substantial Completion Date: December 15, 2009
Final Completion Date / Final Pay Request: To be based on
receipt of clearance for operation and testing from the FDEP WW Division and FDEP
Environmental Resources Department and acceptance of the site by Indian River County.
The above reflects additional work requested by IRCU. Many items are complete such as wiring
and piping. The SS disconnect has been ordered. At this time we do not have a delivery date.
We are anticipating completing this work by the end of October, and will then need
approximately one week after for inspection by IR County and connections by Florida Power &
Light.
If you have any questions, do not hesitate to contact our office.
Thank you —
Vickie Wright
Timothy Rose Contracting, Inc.