CHANGE ORDER did , as
No . 5
PROJECT Spoonbill Marsh Wetland Facility
DATE OF ISSUANCE 04/20/ 10 EFFECTIVE DATE 04/20/ 10
OWNER : Indian River County Utilities
OWNER ' s Contract No . UCP 2785 ENGINEER : Masteller .& Moler, Inc .
CONTRACTOR : Timothy Rose Contracting ENGINEER Project No . 0544LH
You are directed to make the following changes in the Contract Documents :
You are directed to make the following changes in the Contract Documents :
Description : IRCUD request additions and contract time extension .
Reason for change order: IRCUD added baffle bar screen and vegetation removal (a), pump station .
Attachments : List documents supporting chan e )
CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME
Original Contract Price Original Contract Times
$ 29112 , 870 ° 00 Substantial Completion : 03/ 19/2009
Ready for final payment :
Days or dates
Net changes from previous Change Orders Net change from previous Change Orders
No . 1 to No . 4 No . 2 to No . 3
$ 163 , 814 . 30 289 days
Contract Price prior to this Change Order Contract Time prior to this Change Order
$ 27276 , 684 . 30 Substantial Completion : Dec . 15 , 2009
Ready for final payment :
Days or dates
Net Increase ( decrease ) in this Change Net Increase in this Change Order
Order
76
$ 51 , 681 . 12 days
Contract Price with all approved Change Contract Time with all approved Change
Orders Orders
$ 21328 , 365 . 42 Substantial Completion : July 20 , 2010
Ready for final payment : July 20 , 2010
Days r dates
RECOMMENDED : APP `UES "` �� : , ACCEPTED .
° � ° r
PPP
0�j
By : By y . -�
Engineer (Au Kori ed igna e )
Reber D .: yByan , ChairmanIF
Contractor (Authorized Signature )
°
Date : DatQ 2f, 5 a" , 4 Date :
EJCDC No . C - 700 ( 2002 Edition )
Prepared by the Engineers Joint Cont�ra'ct_, f` Ducuments' Committee and endorsed by The
Associated General Contractors of America .
TIMOTHY ROSE CONTRACTING, INC.
1360 Old Dixie Highway SW Suite 106
Vero Beach , Florida 32962
( 772 ) 564 7800
( 772 ) 564 7888
Timrose7@bellsouth . net
April 20, 2010
Indian River County Utilities
180027 1h Street, Bldg . A
Vero Beach , FI 32960
RE : Spoonbill Marsh Wetland Facility
Contract # : UCP 2785
REQUESTED CHANGE ORDER #5
Exhibit : A
Change Order Proposal For Sedimentation Basin Debris Screen And Mixer For Algae Removal And Silt
Suspension To Prevent Pump Clogging :
Construct and Install Baffle Bar Screen and
Clean Vegetation and Sediment from Bottom Of Pump Station Add : $ 4, 614 . 00
Mobilize / Demobilize Add : $ 6, 000 . 00
ABS Pump Mixer Add : $ 15 , 188 . 00
Debris Screen Consisting of:
40' x 8' — 16 Gauge Stainless Steel Add : $ 61289 . 00
Three — 8" Pilings Add : $ 3 , 288 . 00
64' — 2 " %" Stainless Steel Add : $ 466 . 92
64' — 4" x 4" Aluminum Angle Add : $ 1 , 347 . 60
140' — 3 " x 8" PT Add : $ 1 , 628 . 39
192 ' — 2" x 6" PT Add : $ 293 . 21
Hardware , Screws, Bolts, Straps Add : $ 466 . 00
Labor and Equipment Add : $ 7, 260 . 00
Welder Add : $ 2, 040 . 00
Structural Engineer Add : $ 2 , 800 . 00
Total Requested Change in Contract Amount Add : $ 51 , 681 . 12
If you have any questions , do not hesitate to contact our office .
Thank you —
Vickie Wright
Timothy Rose Contracting, Inc .