HomeMy WebLinkAbout2012-113A SECTION 00942 - Change Order Form
No . 1t13A-
DATE OF ISSUANCE : June 19 , 2012 EFFECTIVE DATE : June 19 , 2012
OWNER : Indian River County
CONTRACTOR : Timothy Rose Contracting Inc
Bid No . : N/A
Project : LAGOON GREENWAY — PHASE I CONSTRUCTION AGREEMENT
OWNER ' s Proj . # LG Ph I
This Change Order authorizes the following changes in the Contract Documents for the Lagoon
Greenway — Phase I Construction Agreement :
Description :
Change Order No . 1 is to make miscellaneous adjustments to the bid line items by adding
and deducting certain items based on field review , resulting in a net increase to the contract
amount .
Reason for Change Order :
Adjustment of work needs determined by county staff and contractor based on field
conditions .
Attachments : ( List documents supporting change )
Requested Change Order Summary
CHANGE IN CONTRACT PRICE :
Description Amount
Original Contract Price $ 32 , 701 . 89
Net Increase of this Change Order: $ 1 , 175 . 00
Contract Price with all approved Change Orders : $ 337876 . 89
ACCEPTED : �� f✓Y� APPROVED : I
By
CONTRACTOR (Signature) LEDa7:
WR ( Sig ature)
Date : ' / Approved by the BCC 6/ 19/ 12
Timothy Rose Contracting Inc Change Order 1 . doc
00942 - 1
F :\Community Development\Users\ROLAND\LAAC\Flinn Tract\FIND Grant App Phase A\Timothy Rose Contracting Inc Change Order 1 _ doc Rev. 05/01
ATTACHMENT
TIMOTHY ROSE CONTRACTING, INC.
1360 Old Dixie Highway SW, Suite 106
Vero Beach , Florida 32962
( 772 ) 564 7800
( 772 ) 564 7888
Tim roseMDcomcast , net
December 8, 2011
Indian River County
Attn : Roland Deblois
180027 th Street
Vero Beach , FL 32960
RE : Indian River Lagoon Greenway
REQUESTED CHANGE ORDER
Change Order Proposal for Final Miscellaneous Contract Modifications :
Additional Clearing; Remove Pepper Trees @ Corner;
Remove Fence — Three ( 3 ) Loads @ $ 250 . 00 Each Add :
$ 750 . 00
Additional Shell ; Excavate & Place ;
Shell @ Island to Wider Parking Lot Add : $ 515 . 00
Additional Hog Wire Fence with Posts Add : $ 600 . 00
Additional Aluminum Gates — Two ( 2 ) @ $ 1 , 460 . 00 Each Add : $ 2 , 920 . 00
Deduct 6 ' High Aluminum Coated Fence DEDUCT : < $ 440 . 00>
Deduct 6' High Chain Link Gate — 15 ' Wide DEDUCT : < $ 21070 . 00 >
Deduct Landscape Costs DEDUCT : < $ 800 . 00>
Deduct Sodding of Swale DEDUCT : <$ 300 . 00>
Total Requested Change in Contract Add : $ 11175 . 00
If you have any questions, do not hesitate to contact our office .
Thank you —
Vickie Wright
Timothy Rose Contracting, Inc .