HomeMy WebLinkAbout2008-197Contract No.: AP -168
FM No: 228627-1-A8-01
Vendor No: VF 596-000-679
STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION
AND
INDIAN RIVER COUNTY
ADVANCE REIMBURSEMENT LOCALLY FUNDED AGREEMENT
AMENDMENT NUMBER ONE
THIS AMENDMENT, made and entered into this day of ,
200_, by and between the STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION,
hereinafter called the DEPARTMENT, and INDIAN RIVER COUNTY, located at 1801 27Th
STREET, VERO BEACH, FLORIDA 329606, hereinafter called the PARTICIPANT.
WITNESSETH
WHEREAS, on January 289 2008, the parties entered into a Locally Funded Agreement,
hereinafter referred to as the AGREEMENT, wherein the PARTICIPANT agreed to provide advance
funding for certain improvements in connection with the Reconstruction and Widening of SR -60 from
82°d Avenue/CR-609 to 66th Avenue/CR-615 in Indian River County, Florida for FM# 228627-1-A8-
01 and hereinafter referred to as the PROJECT, and,
WHEREAS, the parties desire to amend the AGREEMENT; and
WHEREAS, the parties hereto mutually agree that this Amendment is in their best interest;
NOW, THEREFORE, in consideration of the mutual covenants, promises and representations
herein, the parties agree to further amend that certain Locally Funded Agreement dated January 28,
2008, as follows:
1. The recitals set forth above are true and correct and are deemed incorporated herein.
2. The estimated cost for the PROJECT is hereby reduced by TEN MILLION EIGHT
HUNDRED THIRTY SIX THOUSAND TWO HUNDRED THIRTY NINE DOLLARS
($10,836,239.00), thus making the PARTICIPANT'S PROJECT share TWENTY THREE
MILLION EIGHT HUNDRED THIRTY THREE THOUSAND THREE HUNDRED
SIXTY TWO DOLLARS ($23,833,362.00).
3. Paragraph 4 of the Agreement shall be removed in its entirety and replaced as follows:
The construction of the PROJECT is estimated to be completed in January, 2011. The
PARTICIPANT'S advanced funding for this PROJECT is in the amount of TWENTY
THREE MILLION EIGHT HUNDRED THIRTY THREE THOUSAND THREE
HUNDRED SIXTY TWO DOLLARS ($23,833,362.00).
Page 1
The PARTICIPANT will submit the advance funding for the Project in three payments. The
PARTICIPANT has previously furnished the DEPARTMENT with a check for the first
payment which is 14.5% of the PROJECT estimate in the amount of THREE MILLION
FOUR HUNDRED SIXTY SIX THOUSAND NINE HUNDRED SIXTY DOLLARS
AND TEN CENTS ($3,466,960.10). The PARTICIPANT has furnished a second payment
made to the DEPARTMENT, which is 58.2% of the PROJECT estimate, in the amount
THIRTEEN MILLION EIGHT HUNDRED SIXTY SEVEN THOUSAND EIGHT
HUNDRED FORTY DOLLARS AND FORTY CENTS ($13,867,840.40). The third and
final payment, which is 27.3% of the PROJECT estimate, is in the amount of SIX MILLION
FOUR HUNDRED NINETY EIGHT THOUSAND FIVE HUNDRD SIXTY ONE
DOLLARS AND FIFTY CENTS ($6,498,561.50) and is due seven days prior to the
execution of the construction contract by the DEPARTMENT. Currently, the construction
contract is scheduled to be executed on May 29, 2008.
The DEPARTMENT agrees to reimburse the PARTICIPANT for their participation in
accordance with Section 339.12(4)(c), Florida Statutes. The PARTICIPANT acknowledges
and agrees that it will not invoice the DEPARTMENT for any portion of the TWENTY
THREE MILLION EIGHT HUNDRED THIRTY THREE THOUSAND THREE
HUNDRED SIXTY TWO DOLLARS ($23,833,362.00) prior to July 1, 2009, the fiscal year
the PROJECT is scheduled in the Department's Work program. After a receipt of a properly
documented invoice, the payments will be made to the PARTICIPANT in eight (8) equal
quarterly payments of TWO MILLION NINE HUNDRED SEVENTY NINE
THOUSAND ONE HUNDRED SEVENTY DOLLARS AND TWENTY FIVE CENTS
($2,979,170.25), which equals TWENTY THREE MILLION EIGHT HUNDRED
THIRTY THREE THOUSAND THREE HUNDRED SIXTY TWO DOLLARS
($23,833,362.00).
Remittance shall be made payable to the Department of Financial Services, Revenue
Processing. Payment shall be clearly marked to indicate that it is to be applied to FM Project
No. 228627-1-32-02, 228627-1-52-01, & 228627-1-62-01. The DEPARTMENT shall utilize
this deposit for payment of the cost of Projects No. 228627-1-32-02, 28627-1-52-01, &
228627-1-62-01.
Payment shall be mailed to:
Florida Department of Transportation
Professional Services Unit -
3400 W. Commercial Boulevard
Fort Lauderdale, Florida 33309-3421
Attention: Leos A. Kennedy, Jr.
Page 2
Breakdown of Funding
Design Services
FM# 228627-1-32-02
Construction
FM# 228627-1-52-01
CEI Services
FM# 228627-1-62-01
$250,000.00
$20,346,473.00
$3,236,889.00
Total estimated Project Cost = $23,833,362.00
(A) The DEPARTMENT intends to have it final and complete accounting of all costs
incurred in connection with the work performed hereunder within three hundred
sixty (360) days of final payment made to the Contractor. The DEPARTMENT
considers the PROJECT complete when the final payment is made to the
Contractor, not when the construction work is complete. All PROJECT cost
records and accounts shall be subject to audit by a representative of the
PARTICIPANT for a period of five (5) years after final close out of the
PROJECT. The PARTICIPANT will be notified of the final cost. Both parties
agree that in the event the final accounting of total PROJECT costs pursuant to the
terms of this Agreement is less than the total deposits to date, a refund of the excess
will be made by the DEPARTMENT to the PARTICPANT. If the final
accounting is not performed within three hundred and sixty (360) days, the
PARTICIPANT is not relieved from its obligation to pay.
(B) In the event the final accounting of total PROJECT costs is greater than the total
deposits to date, the PARTICIPANT will pay the additional amount within forty
(40) calendar days from the date of the invoice from the DEPARTMENT. The
PARTICIPANT agrees to pay interest at a rate as established pursuant to Section
55.03, F. S., on any invoice not paid within forty (40) calendar days until the
invoice is paid.
(C) The payment of funds under this Agreement will be made:
Directly to the DEPARTMENT for deposit and as provided in the Memorandum
of Agreement (MOA) between PARTICIPANT, DEPARTMENT, and the State
of Florida, Department of Financial Services, Division of Treasury, a copy of which
is attached hereto as Exhibit "B".
NOTE: The MOA is a benefit to both the DEPARTMENT and the
PARTICIPANT. Interest earned will be used for any additional costs of
PARTICIPANT responsibility. Any unused funds, including interest, will be
provided to the PARTICIPANT after the final accounting of the PROJECT has
been performed.
(D) The DEPARTMENT'S obligation to pay any sum pursuant to this Agreement is
contingent upon an annual appropriation by the Florida Legislature.
Page 3
All provisions, covenants, terms and conditions of the AGREEMENT between the parties
theretofore entered into on January 28, 2008, as originally set forth therein, which are not hereby
expressly amended or modified and not in conflict with the terms hereof, are hereby ratified and
confirmed and shall remain the same and be unaffected by these presents.
IN WITNESS WHEREOF, this AMENDMENT to be executed by the parties below for the purposes
specified herein. Authorization has been give to enter into and execute this Amendment by Resolution No. 2008-090
on ___________July 1, _ _, 2008, hereto attached
INDIAN RIVER COUNTY
BY: C'ik, 'ID) (J 6
NAME: S�Addra L. Bowden
TITLE: Chairman
ATTEST: �
bq
J.K. BARTON
CLERK CIRCUIT COURT
COUNTY CLERK (SEAL)
APPROVED:
BY:
i COUNTY ATTORNEY
STATE OF FLORIDA
DEPARTMENT OF TRANSPORTATION
BY:
ROSIELYN QUIROZ
DIRECTOR OF TRANSPORTATION SUPPORT
APPROVED: (AS TO FORM)
M3
DISTRICT GENERAL COUNSEL
APPROVED:
BY:
PROFESSIONAL SERVICES ADMINISTRATOR
Page 4