Water
Billing Charge - Per Account
$
1.29
Service Availability Charge [formerly known as Base Facility Charge]:
Where lines are available -
Single -Family (per ERU
$
7.76
Manufactured Home 0.85(per ERU
$
6.60
Multi -Family 0.85(per ERU
$
6.60
Commercial(per ERU
$
7.76
Service Availability Charge [formerly known as Base Facility Charge]:
Capacity is Reserved But Where Lines Are Not Available -
Single -Family (per ERU
$
3.88
Manufactured Home 0.85(per ERU
$
3.30
Multi -Family 0.85(per ERU
$
3.30
Commercial(per ERU
$
3.88
0 to 3,000 Gallons Per Month Per Connection - Per 1,000 Gallons
$
2.20
3,001 to 7,000 Gallons Per Month Per Connection - Per 1,000 Gallons
$
2.42
Over 7,000 Gallons Per Month Per Connection - Per 1,000 Gallons
$
3.85
Greater than 13,000 Gallons Per Month Per Connection Per ERU -
Per 1,000 Gallons
$
7.70
Sewer
Billing Charge - Per Account
$
1.29
Service Availability Charge (formerly known as Base Facility Char e :
Where lines are available -
Single -Family (per ERU
$ 14.58
Manufactured Home 0.85(per ERU
$ 12.40
Multi -Family 0.85(per ERU
$ 12.40
Commercial(per ERU
$ 14.58
Service Availability Charge [formerly known as Base Facility Chargel:
Capacity is Reserved But Where Lines Are Not Available -
Single -Family (per ERU
$
7.29
Manufactured Home 0.85(per ERU
$
6.20
Multi -Family 0.85(per ERU
$
6.20
Commercial(per ERU
$
7.29
Volume Char a Per 1,000 Gallons - 12,000 Gallons Per Month Maximum for:
Single -Family & Manufactured Homes Individual meters),
0 to 12,000 Gallons Billed Water Flow Per 1,000 Gallons
$
2.86
August 18, 2009 - 1 -
Volume Charge Multi -Family Master -Metered & Commercial:
0 to 13,000 Gallons Billed Water Flow Per 1,000 Gallons
$ 2.86
Above 13,000 Gallons Billed Water Flow Per 1,000 Gallons
$ 4.29
Bulk Water
Billing Charge — Per Account Per Month
$ 1.29
Service Availability Charge [formerly known as Base Facility Charge] Where Lines
Are Available — Per ERU
$ 6.19
Service Availability Charge [formerly known as Base Facility Charge] Where Capacity
is Reserved
But Lines Are Not Available — Per ERU
$ 3.10
Volume Charge — Per 1,000 Gallons Water Meter Basis
$ 2.63
Excess Volume Surcharge — Greater than 7,600 Gallons Per Month — Per ERU*
$ 4.45
*Surchar a for Bulk users will apply to flow exceedingtotal capacity
reserved by bulk user in all meters
Bulk Sewer
Billing Charge — Per Account Per Month
$ 1.29
Service Availability Charge [formerly known as Base Facility Charge] Where Lines
Are Available — Per ERU
$ 13.41
Service Availability Charge [formerly known as Base Facility Charge] Where Capacity
is Reserved
But Lines Are Not Available — Per ERU
$ 6.71
Volume Charge — Per 1,000 Gallons Water Meter Basis
$ 2.63
Volume Charge — Per 1,000 Gallons Sewer Meter Basis
$ 2.98
Excess Volume Surcharge — Greater than 7,600 Gallons Per Month — Per ERU*
$ 4.45
*Surcharge for Bulk users will apply to flow exceeding total capacity
Reserved by bulk user in all meters
Excess Sewage Strength Charge Sewage Charge X Ration of Total
Dissolveds Solids or Biochemical
Oxygen Demand in Milligrams
Per Liter / 250
Excess Sewage Strength Charge applicable to customers required to use Grease
Traps, but who have obtained a variance due to hardship or financial unfeasibility
Sewage
Charge*
Reclaimed Water— Per 1,000 Gallons
$ 00.15
Sludge and Septage Rates (b)
Charge Per 1,000 Gallons a
$ 30.82
Charge Per Wet Ton b
$ 7.51
Notes:
August 18, 2009 - 2 -
(a) Recommended rates assume domestic sludge with solids concentration of between .5 and 2.0
percent.
(b) Costs incurred by County to sample, monitor and/or test wastes to verify solids concentrations, metals,
content, etc., or additional costs incurred to handle or dispose of wastes with high metal concentrations or
other non-domestic waste characteristics should be recovered from the users discharging the wastes in
addition to the above charges based on formula's available in the Department of Utility Services,
IMPACT FEE [formerly known as CAPACITY CHARGEI
Water— Per ERU
Water Treatment
$
320.00
Water Transmission
980.00
Total
$1,300.00
Sewer — Per ERU
Wastewater Treatment
$2,087.00
Wastewater Transmission
$
709.00
Total
$2,796.00
Line Extension Char es
Main Extension — Water
Per foot measured along front of property served
$
11.25
Main Extension — Sewer and Sewer Laterals
Per foot measured along front of property served
$
15.77
Note: Charge doubles if service available on one side only,
Minimum of 50 feet per ERU, maximum of 100 feet per ERU
OTHER CHARGES
Deposits — Required Upon Opening, Transferrin or Reconnecting Service
Residential and Commercial — Per ERU
$
50.00
Hydrant Meter
$
345.00
Charge for Returned Check
$
20.00
Issuance of Duplicate Bill
$
1.50
SewerTap
Cost Plus Overhead
Meter Replacement
5/8 Inch
$
100.00
1Inch
$
125.00
1-1/2 Inch
$
300.00
2 Inch or larger
Cost Plus Overhead
Meter Removal
5/8 Inch
$
30.00
1Inch
$
30.00
1-1/2 Inch and larger
$
40.00
August 18, 2009 - 3 -
Water Service Connection
5/8 Inch Meter
$ 400.00
1 Inch Meter
$ 460.00
1-1/2 Inch Meter
$ 810.00
Larger than 1-1/2 Inch Meter
Cost Plus Overhead
Sewer Service Connection
Residential
$ 500.00
Commercial and Other
Cost Plus Overhead
Paved Road Cuts
Cost Plus Overhead
$200 minimum
Road Jacking and Boring
Cost Plus Overhead
$200 minimum
Grass Restoration
Cost Plus Overhead
Unauthorized use of Fire Hydrants
$ 115.00
Other and Extraordinary Services
Cost Plus Overhead
Meter Installation
5/8 Inch
$ 130.00
1 Inch Meter
$ 250.00
1 142 Inch Meter
$ 500.00
2 Inch Meter
Cost Plus Overhead
3 Inch Meter
Cost Plus Overhead
Fire Hydrant Meter
$ 25.00
Water Service Reconnection
During Working Hours
$ 25.00
After Working Hours
$ 35.00
Meter Rereads and Leak Inspection
$ 20.00
Delinquency Charge
$2.00 plus 1.5%
per month
General Service Call
Cost Plus Overhead
Meter Test
5/8 Inch Meter
$ 25.00
1 Inch Meter
$ 25.00
1-1/2 Inch Meter or Larger
Cost Plus Overhead
Damage Repair
Cost Plus Overhead
Line Location
Cost Plus Overhead
August 18, 2009 - 4 -
En ineerin Services
Cost Plus Overhead
Site Plan Review
Cost Plus Overhead
Under 40 Units and Without Lift Station
$50 minimum
Site Plan Review
Cost Plus Overhead
Over 40 Units and With Lift Station
$150 minimum
($ 575.00 minimum)
Inspection Fee
Cost Plus Overhead
Water — Per Connection
$25.00 $50.00 after hours
Sewer— Per Connection
$25.00 $50.00 after hours
Hydrant Flow Test $ 60.00
urged aatlRer—Year $x0.00
Utility Master Plan Revisions required by requested changes to the Indian
River County Comprehensive Plan shall be paid by the Applicant
requesting the change. Cost Plus Overhead
Franchise Charges
Application Fees Cost Plus Overhead
($ 50.00 minimum)
Establish Franchise Cost Plus Overhead
($ 1,100.00 minimum)
Franchise Name Charge Cost Plus Overhead
($ 115.00 minimum)
Franchise Territory Charge Cost Plus Overhead
($ 115.00 minimum)
Change of Ownership Cost Plus Overhead
49 ERU's or Fewer ($ 115.00 minimum)
50 ERU's or More
Cost Plus Overhead
($ 300.00 minimum)
Rate Hearing
Cost Plus Overhead
49 ERU's or Fewer
($ 300.00 minimum)
50 ERU's or More
Cost Plus Overhead
($ 575.00 minimum)
Public Hearing
Cost Plus Overhead
($ 115.00 minimum)
August 18, 2009 - 5 -