Loading...
HomeMy WebLinkAbout2016-078 i BRIDGE REPLACEMENTS AND WIDENING OF 66TH AVENUE FROM SOUTH OF SR 60 TO NORTH OF 57TH STREET IRC PROJECT NUMBER 0545 PROFESSIONAL CIVIL ENGINEERING& STRUCTURAL ENGINEERING SERVICES AMENDMENT NO. 16 TO THE PROFESSIONAL ENGINEERING/LAND SURVEYING SERVICES AGREEMENT BETWEEN ARCADIS US, Inc. (tka ARCADIS G&M, Inc.), Inc. AND INDIAN RIVER COUNTY, FLORIDA. This is an amendment to the existing Engineering Services Agreement (AGREEMENT) dated September 6, 2005 between ARCADIS US, Inc. (ENGINEER) and Indian River County (COUNTY). This amendment addresses changes in "Section I—Project Limits and Description', "Section III - Scope of Services", and "Section V - Compensation". Amendment Description This Amendment includes the following: "SECTION I - PROJECT LIMITS AND DESCRIPTION" is being modified to incorporate the following: Consultant services are required for the preparation of road design plans; bridge plans; landscape and irrigation plans; permit applications and utility relocations associated with the construction of 66th Avenue. Plans have been prepared for the widening of 66`h Avenue from SR 60 to north of 57`h Street. Construction has been completed for 66`h Avenue from SR 60 to north of 49`h Street. A final set of construction plans will now be prepared for the section of 66`h Avenue from north of 491' Street to north of 57`h Street. The following plan sheets will be modified: • Cover Sheet • Drainage Maps • Typical Sections • Quantities and General Notes • Summary of Drainage Structures • Plan and Profile Sheets • Side Street Plan and Profile Sheets • Cross Sections • Stonnwater Pollution Prevention Plans • Signing and Pavement Marking Plans • Bridge Plans • Landscape and Irrigation Plans Page 1 of 6 G\LNR Support\Proposa1s\WPB\2016\66th Avenue\66th Avenue AVE AMENDMENT 4-25-16 doe Quantities had previously been computed for the section from SR 60 to north of 57`h Street. The quantities will now be adjusted to include only the section from North of 49th Street to north of 57th Street. The plans will be modified to show the previously constructed transition section north of 49th Street, and to show the work necessary within the transition area for the final 4-lane roadway. Additionally, the intersection of 57h Street and the bridge over the IRFWCD Lateral A canal has been widened to a three lane section. The plans will be modified to show the connection to the widened bridge and to eliminate the work shown east of the Lateral A Canal. Survvey information will be obtained within the transition area and at 57`h Street to verify the existing conditions. The plans for the bridges at 53`d Street, the North relief canal, and 57th Street will be updated to conform to the current design criteria. The landscape and irrigation plans will be updated and will be revised to include only the area from north of 49th Street to north of 59th Street. The work included in Amendment No. 16 is in accordance with the existing AGREEMENT dated November 6, 2005 between ARCADIS US, Inc. (ENGINEER) and Indian River County (COUNTY). "SECTION III — SCOPE OF SERVICES" is being modified to incorporate the following: 30% and 60%, and 90% plans have been submitted to the County. Engineer will prepare revised 90%, and 100% plans. The plan modifications will consist of the following: The Roadway set of plans shall consist of the following: 30% 60% 90% 100% Cover Sheet X X Drainage Maps X X Typical Sections X X Summary of Quantities X X Summary of Drainage Structures X X Reference Ties X X General Notes X X Details X X Plan and Profile Sheets (40 scale) X X Page 2 of 6 G\INR Support\Proposa1s\WPB\2016\66th Avenue\66th Avenue AVE AMENDMENT 4-25-16.doc Side Street Plan and Profile Sheets X X Cross Sections at 100 ft interval X X Signage & Pavement Marking Plans (40 scale) X X Plateau Plan and Profile Sheets X X Drainage Structure Sheets X X Detention Areas & Details X X Driveway Cross Sections X X Cross Sections X X i Side Street Cross Sections X X Stormwater Pollution Prevention Plans (SWPPP) X X Signing and Pavement Marking Plans X X Bridge Plans X X Landscape Plans X X Irrigation Plans X X Computation Book X X Construction Cost Estimate and Quantities X X "SECTION IV - TIME FOR COMPLETION" is being modified to incorporate the following: 1. Project shall be completed as follows: a. The time for completion of the 90% design drawings, permit applications, and Engineer's Opinion of Probable Construction Cost for the project shall be four (4) months from the date of execution of this ADDENDUM. Once permits are received, 100% design drawings shall be completed one month (1) month thereafter. 2. Deliverables -The ENGINEER shall provide the COUNTY: a. Three (3) 11" x 17 paper signed and sealed of the 90% plans. Also, a pdf format set of the plans on a cd. b. Microstation drawing file and PDF formats on CD. c. Work Product shall be prepared and supplied in State Plane geometry(NAD83 2007 adjustment if applicable); digital versions are to be prepared and submitted so that the COUNTY or other consultants can readily use it for the design and analysis of the area, as defined. It shall contain all information necessary for third-party surveyor to independently recreate and/or utilize the survey work. It is acknowledged all final products become property of Indian River COUNTY and will be available for use by the public at large. Page 3 of 6 G:\LNR Support\Proposals\WPB\2016\66th Avenue\66th Avenue AVE AMENDMENT 4-25-16.doc i "SECTION V—COMPENSATION" is being modified to incorporate the following: The COUNTY agrees to pay and the ENGINEER or agrees to accept for services rendered pursuant to this Agreement fees in accordance with the following: A. Professional Services Fee 1. The basic compensation mutually agreed upon by the ENGINEER and the COUNTY follows: The following is a summary of costs: Charge Associated with Change in Project Scope New Total And Proiect Limits Compensation Geotechnical Services (Tierra)(Lump Sum) ................................$0.00 $139,460.00 Engineering(ARCADIS) (Lump Sum).................................$24,834.66 $988,222.16 Signal Plans (ARCADIS)................................................................$0.00 $84,726.66 Design Survey (66th Avenue) (ARCADIS)................................ $3,577.00 $173,077.00 Design Survey (Sidestreets) (ARCADIS)......................................... $0.00 $71,428.00 Right-of-Way Survey and Map (66th Avenue)................................. $0.00 $117,821.00 Right-of-way Survey (Sidestreets).................................................... $0.00 $61,963.00 Structural Design for 3 bridges (BDA, now the Wantman Group,Inc) ................................... $19,400.00 $226,622.00 Landscape& Irrigation........................................................... $23,500.00 $100,660.00 (Thomas Lucido &Associates) (Lump Sum) PondSurveys..................................................................................... $0.00 $25,790.00 Water Main Plans (ARCADIS).....................................................$0.00 $86,145.00 (Lump Sum) Corridor Study (ARCADIS)...........................................................$0.00 $15,581.00 Cultural Resource Assessment......................................................$0.00 $8,925.93 TOTAL PROFESSIONAL SERVICES................................. $71,311.66 $2,100,421.75 Page 4 of 6 C:\Users\jwilliams\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Outlook\DA3K8007\66th Avenue AVE AMENDMENT 5-16-16.doc HOURLYRATE ALLOWANCES Allowance for Sketch and Legal Descriptions and staking ofparcels(375.001each)................NTE$0.00 $51,000.00 Allowance for miscellaneous roadway design changes due to right of way negotiations...............................NTE$0.00 $20,000.00 Allowance for Survey Crew and Soft Dig Machine for Horizontal and Vertical Utility Locations at Potential Conflicts (Survey$112Mr)......................................................................NTE$0.00 $20,000.00 Allowance for Survey and Design Of a transition to match the existing pavement At the north end of the project................................................NTE$0.00 $27,000.00 Construction Engineering Services-Public Works .............NTE$0.00 $92,877.12 Construction Engineering Services-Utility Dept.................. NTE$0.00 $10,446.24 Construction Engineering Services-Structural Engineer. NTE$920.00 $920.00 TOTAL HOURLY RA TE ALLOWANCES.......................NTE$920.00 $222,243.36 Compensation for the hourly rate allowances will be made on an hourly basis at the hourly rates listed below: Project Engineer Manager..............................................$146.64 Project Engineer............................................................... $109.70 Senior CADD Operator...................................................... $85.84 CaddDrafts»rarr.................................................................. $56.89 Survey Project Manager................................................... $106.40 Professional Surveyor........................................................ $98.30 SurveyCADD Tech............................................................ $68.17 3 Man Field Crew............................................................. $126.84 2 Man Field Crew............................................................. $114.14 Sr. Field Coordinator......................................................... $75.00 The AGREEMENT is hereby amended as specifically set forth here in. All other sections of the AGREEMENT shall remain in full force and effect and are incorporated herein. Page 5 of 6 G.\LNR Support\Proposals\WPB\2016\66th Avenue\66th Avenue AVE AMENDMENT 4-25-16 doc i This Amendment No. 16 to the AGREEMENT regardless of where executed, shall be governed by and,constructed by the laws of the State of Florida. In witness whereof the parties have executed this Amendment this 24th day of May , 2016. i ARCADI S, I C. INDIAN RIVER COUNTY, FLORIDA 1500 G B levard. Suite 200 Boynton eac 33426 B . By: Ro Lawson, P.E. o•'. C..A.,y�s'ti Bob Solari, Chairman : Board of County Commissioners WITNESSED BY: o' r ' Approved by BCC Mav 24, 2016 /� •9COUtdT`1•�•' l Attest: Jeffrey R. Smith, Clerk of Circuit Court By: County Attorney Deputy Clerk Approvedas to F and Legal Sufficiency Joseph . B 'rd, Count Ad inistrator i i Page 6 of 6 G:\LNRI Support\Proposals\WPB\2016\66th Avenue\66th Avenue AVE AMENDMENT 4-25-16 doc I ESTIMATE OF WORK EFFORT FOR ENGINEERING --66th Avenue --- — — Amendment 17 Total Contract Cost Computations $ 24,834 66 Total Activity Salary Costs (a)Overhead Additives: (a1)Combined OH Percent 0.00% (a2)Combined OH Cost $ - Subtotal(Salary+Overhead) $ 24,834 66 (b)Operating Margin Percent 0.00% (b)Operating Margin Cost $ - Subtotal(Salary Related Cost) $ 24,834.66 Subtotal(Cost Elements of Basic Activities) $ 24,834.66 SUBCONTRACTOR ITEMS(Limiting Amount) TOTAL SUBCONTRACTOR ITEMS $ - LUMP SUM= 66th AVENUE Amendment 16 4-22-16.xis ESTIMATE OF WORK EFFORT FOR ENGINEERING ----- --- - 66th Avenue - - --- -- --- - - ---- - -- Amendment 17 PROJECT MANAGER PROJECT ENGINEER SR.CADD OPERATOR ACTIVITY TOTAL MAN HOURLY MAN HOURLY MAN HOURLY MAN PLAN REVISIONS 30.0 $ 146.64 37.0 $ 109.70 143.0 $ 85.84 210.0 DRAINAGE DESIGN $ 146.64 $ 109.70 $ 85.84 ROADWAY PLANS $ 146.64 $ 109.70 $ 85.84 UTILITIES 8.0 $ 146.64 8.01s 109.70 $ 85.84 16.0 PERMITTING 8.0 $ 146.64 8.0 $ 109.70 1 1$ 85.84 16.0 SIGNING A PAVEMENT MARKING PLANS $ 146.64 109.70 1$ 85.84 SIGNALIZATION PLANS $ 146.64 $ 109.701 1$ 85.84 TOTALS 46.0 53.0 143.0 242.0 DESIGN ANALYSIS $ 4,399.20 $ 4,058.90 $ 12 275.12 DRAINAGE ANALYSIS $ $ $ ROADWAY PLANS $ $ $ UTILITIES $ 7173.12 $ 877.60 $ PERMITTING $ 1173.12 877.60 $ SIGNING A PAVEMENT MARKING PLANS $ $ TOTALS $ 6,745.44 E 5,814.10 E 12,275-.12 24 834.66 BY COSTFOR HOURLY ACTIVITY ACTIVITY RATE DESIGN ANALYSIS 210.0 $ 20 733.22 98.73 DRAINAGE ANALYSIS $ #DN/0! ROADWAY PLANS $ #DN/01 UTILITIES 16.0 $ 2,050.72 128.17 PERMITTING 16.0 $ 2,050.72 128.17 SIGNING 8 PAVEMENT MARKING PLANS $ SIGNALIZATION PLANS $ #DN/0! TOTALS 242.0 $ 24 834.66 $102.62 Average per hour 661h AVENUE Amand-M 16 4.22-10.ft 66th Avenue HIGHWAY PAGE 2 OF 3 HIGHWAY TASK LIST ACTIVITY'A.ROADWAY PLANS PACKAGE SUBACTIVITY.1 -Plan Revisions BASIS OF NO OF NO OF TOTAL PROJECT PROJECT TASK ESTIMATE UNITS HOURS/UNIT SHEETS HOURS MANAGER ENGINEER SR.CADD REMARKS 1 Cover Sheet Sheet 1 2 1 2 2.0 2 Typical Sections Sheet 3 2 3 6 2.0 4.0 1 Drainage Ma s Sheet 1 4 1 4 1.0 3.0 2. Roadway Plan&Profile Sheets Sheet 11 12 4 132 12.0 20.0 100.0 3. Cross Sections Each 8 4 3 32 6.0 6.0 20.0 4. Plateau Plans Sheet 0 5. Drainage Structure Sheets Sheet 6 1 6 0 6.0 7 Driveway Profiles Each 0 8 Summa of Quantities LS 1 12 1 12 4.0 8.0 9 Signing and Paevment Marking Plans Each 2 4 2 8 2.0 6.0 10 Quantity computations Each 1 16 16 8.0 8.0 SUBTOTAL THIS SHEET 204 30 37 143 66th Avenue HIGHWAY PAGE 7 OF 12 HIGHWAY TASK LIST ACTIVITY A.ROADWAY PLANS PACKAGE SUBACTIVITY.4-UTILITIES/RAILROADS BASIS OF NO OF NO.OF TOTAL PROJECT PROJECT TASK ESTIMATE UNITS HOURS/UNIT SHEETS HOURS MANAGER ENGINEER SR.CADD REMARKS 1 Utility conflict matrix Ea. 1 4 0 4.0 2. Profiles Ea. 0 3. Coordination with Utility Companies Ea. 1 4 4 4.0 4. Details Ea. 0 5. Utility Coordination Meetings Ea. 2 4 8 8.0 6 Pre Work Meeting Ea. 0 SUBTOTAL THIS SHEET 12 8 8 0 6. Quality Control 0% 0 7 Supervision 0% 0 8. Utilit Meetings TOTAL 12 8 8 0 66th Avenue HIGHWAY PAGE 3 OF HIGHWAY TASK LIST ACTIVITY A.ROADWAY PLANS PACKAGE SUBACTIVITY:5-ENV.SERVICES/PERMITS BASIS OF NO,OF NO OF TOTAL PROJECT PROJECT TASK ESTIMATE UNITS HOURS/UNIT SHEETS HOURS MANAGER ENGINEER SR.CADD REMARKS 1 Indian River Farms Water Control District Permit L.S 1 8 8 4.0 4.0 2. St.Johns River Water control District Permit L.S 1 8 8 4.0 4.0 SUBTOTAL THIS SHEET 16 8 8 0 WGIW February 29, 2016 Henry' W.Deibel,Jr. Associate Vice President Arcadis U.S., Inc. 1500 Gateway Boulevard. Suite 200 Boynton Beach, FL 33426 H a n k.D ei b el lAarca d is.co m RE: Indian River County 66"Ave.Bridges Dear IMr. Deibel, Wantman Group, Inc., (WGI) is pleased to provide this scope of services and fee proposal to Arcadis US., Inc. for Structural Engineering Services associated with the production of Construction Plans for two new bridges: Bridge No. 884036(66th Avenue at 53'd Street over Lateral "A"Canal)and Bridge No. 880006(661 Avenue over the North Relief Canal); and for modifications to existing Bridge No. 884093 (571 Street over Lateral "A"Canal). Our Scope of Services and corresponding fees are detailed below. SCOPE OF SERVICES ENGINEERING SERVICES 1. Bridge No. 884036 — 66" Avenue at 531 Street over Lateral "A" Canal. Update Pian Set prepared by BDA. Inc. (dated 06.13.12)to Final Signed &Sealed Plans for Construction. This task to be performed for a lump sum of......................................................$5,540.00 2. Bridge No. 880006 — 66t° Avenue over the North Relief Canal. Update Plan Set prepared by BDA, Inc. (dated 08.15.07)to Final Signed & Sealed Plans for Construction. This task to be performed for a lump sum of......................................................$8,320.00 3. Bridge No. 884093 —57"h Street over Lateral "A" Canal. Modify Plans prepared by BDA, Inc. (dated 03.16.09)for Final Signed & Sealed Plans to complete"Phase Il"Construction. This task to be performed for a lump sum of......................................................$5,540.00 4. Post Design Services. During bidding process,attend one pre-bid meeting. Respond to RFPs from Contractor. This task to be performed for a lump sum of........................................................$920.00 Our fees do not include Construction Phase Services. All fees quoted in this agreement are applicable for one year from date of agreement. At that time, fees are reviewed and adjusted accordingly. Any hourly charges or reimbursable costs shall be subject to the current fee schedule in effect at the time services are performed. I : . • _ _ _ fi f: ° - wantmangroup. Arcadis U.S., Inc. February 29, 2016 Page 2 of 2 We appreciate the opportunity to be of service to you. Upon acceptance of this proposal, please sign and return!one(1)copy to this office. RespeIctfully submitted, WANTMAN GROUP,INC. kI . rian Rheault, P:E. Structures Project Principal Corporate Representative: I Name(Printed) This Proposal accepted this day of , 2016 By Name(Signature) i . wantmangroup. -: lucido&associates Lan i Planning J Landscape Architecture i April 18, 2016 via email: Han k.Deibel anarcadis-us.com Consider this to be the original Mr.Hank Deibel Arcadis 15001Gateway Boulevard, Suite 200 Boynton Beach,FL 33426 RE: 66"Avenue Station 295+00 to Station 354+00—Proposal of Services for Landscape i Architecture (LA REF NO. 16-260 fna 11-165FP) i Dear Mr.Deibel: This agreement authorizes Lucido&Associates, hereinafter referred to as"Consultant,"to provide to Arcadis,hereinafter referred to as"Client"with landscape architecture and irrigation design services for proposed roadway improvements from Station 295+00 to Station 354+00, located in Indian River County, FL. SCOPE OF SERVICES Our understanding is that we will provide the following specific services: • Preparation of one(1)set of final landscape plans for bidding and installation purposes for landscape medians, including littoral zone and lake bank landscape plans for three(3)stormwater treatment ponds; • Provide one(1)set of final irrigation plans for bidding and installation purposes for areas noted above. Note: Landscape and irrigation plans to include locations, notes and details for proposed landscape and irrigation material. FEES: Fees shall be billed on a fixed fee basis, based on the hourly billing rates included in this contract, in the amount of Twenty Three Thousand Five Hundred ($23.500.00)dollars. Consultant shall not exceed the fee amount without authorization from Client. Fees may be increased based on changes or additions to the proposed Scope of Services. Fees shall be billed monthly on a percentage of completion basis,and are due upon receipt. 701 S_E.Ocean Boulevard Stuart,Florida 34994 tel:772:220.2100 fax:777-223.0220 web:www.lucidodesign.com I I Mr.Hank Deibel,Arcadis LA#16-260 66"Avenue April 12, 2016 Page;2 of 5 I 2016 HOURLY_BILLING RATES President $235.00 Environmental Specialist $105.00 Senior Vice President $225.00 Senior Designer $ 95.00 Vice President $195.00 Executive Administrator $ 85.00 Senior Planner/Landscape Architect $135.00 Project Designer $ 80.00 Senior Project Manager $125.00 Bookkeeper $ 75.00 Senior Designer II $120.00 Design Technician $ 65.00 Senior Planning Assistant $115.00 Administrative Assistant $ 55.00 Project Manager $110.00 Technfcal Assistant $ 45.00 Hourly,rates are valid for a period of thirty(30)days from date of proposal. Hourly rates may change at the beginning of each calendar year based on annual review EXPENSES: Reimbursable expenses may include: reproduction,travel expenses, courier,telephone costs, and outside vendors, and shall be billed on a monthly basis in addition to professional services fees. All vendor reimbursable expenses shall be charged direct costs plus 15%. I ADDITIONAL SERVICES: Additional services required as a result of substantial changes in the established scope of services,project program or concept; unforeseen constraints; new,revised or improper interpretations or applications by government staff or officials of local development regulations or Comprehensive Plan policies; revisions to plans or documents prepared by others-not directly affiliated with Lucido and Associates; or as requested by the Client will be billed at either the hourly rates referenced herein or at agreed upon fixed fees. Additional services include,but are not limited to, planned unit development agreements; governmental applications for development approval not specifically listed herein; conceptual site plans, master plans,final site plans;phasing plans;meetings/site visits not listed in the scope of services no site visits or construction meetings;traffic analyses or review and coordination of traffic related issues; revising previously approved drawings; additional graphics, elevations, cross-sections, perspectives,color renderings or photo boards not specifically listed herein; tree surveys or mitigation plans; architectural services,review of architectural plans or coordination of architectural issues; engineering services,review of engineering plans or coordination of engineering issues; site lighting or electrical engineering; structural plan; governmental or building permits; permit drawings;environmental surveys or review and coordination of environmental related issues; and other such services not otherwise listed in the scope of services. i INSURANCE: The Consultant carries Worker's Compensation insurance,professional liability insurance, and general liability insurance. If the Client directs the Consultant to obtain increased insurance coverage,the Consultant will acquire such additional insurance, if obtainable,at the Client's expense. TERMS: Invoices shall be considered past due thirty(30) days from the date of billing. Work process shall stop after account is thirty(30)days in arrears. In connection with any litigation,including appellate proceedings arising out of this Agreement,the prevailing party shall be entitled to recover any amounts due and/or unpaid,together with costs, interest and reasonable attorney's fees. In the event any invoice or any portion thereof remains unpaid for more than thirty(30)days following the invoice date,the Consultant may initiate collection and/or legal proceedings to collect the same. Any sum due the Consultant which is not paid within thirty(30)days after submission of an invoice shall bear interest at a rate of one and one-half percent(1-1/2%)per month from the date of submission of the invoice until paid Mr.Hank Deibcl,Arcadis LA#16-260 66h Avenue April 12,2016 Pag i 3 of 5 in full. If the Client objects to an invoice, it must advise the Consultant in writing providing its reasons within 14 days of receipt of the invoice,or the Client's objections will be waived, and the invoice shall conclusively be deemed due and owing. The parties acknowledge that a substantial portion of negotiations and anticipated performance of this agreement occurred or shall occur in Indian River County,Florida,and that, therefore,without limiting the jurisdiction or venue of any other federal or state courts, each of the parties irrevocably and unconditionally(a)agrees that any suit,action or other legal proceeding arising out of or relating to this Agreement may be brought in the courts of record of the State of Florida in Indian River County;(b) consents to the jurisdiction of such court in any such suit,action or proceeding; and(c)waives any objection which he or she may have to the laying of venue of any such suit,action or proceeding in such court. The Client understands and agrees that if all fees and reimbursable expenses are not paid,that after the conclusion and/or termination of the representation,the Consultant may report such non-payment to the appropriate credit reporting agencies. In addition, the Client understands and agrees that after the conclusion and/or termination of the representation,the Consultant may assign any unpaid fees and costs to an appropriate collection agency for collection, or initiate a collection action itself. All original drawings and information are to remain the property of the Consultant(all copies of drawings to be supplied to Client for their files). The Client will be provided with copies of final drawings and/or reports for information and reference purposes. Plans and documents are not to be used for Construction purpose without Consultant approval. Boundary survey shall be provided by Client in digital format in State Plane Coordinate System. All Consultant information and materials may not be used for the benefit of any third party without approval by the Consultant. Technical and pricing information in this proposal is confidential and the proprietary property of the Consultant, and is not to be disclosed or made available to third parties without the written consent of the Consultant. All plans,documents and graphics are to be considered accepted after submittal to the appropriate governing jurisdiction. The Consultant will not be responsible for Government Certification of our landscape designs or other associated planting or site problems if not contracted to provide site inspection services during plant installation. All conceptual,master and final site plans produced by the Consultant are diagrammatic and not to be used for construction purposes. All master and final site plans must be horizontally controlled and brought into compliance with regulatory site design standards by the Client's engineer for construction purposes. The obligation to provide further services under this Agreement may be terminated by the Client upon thirty,(30)days written notice in the event of any substantial failure by the other party to perform in accordance with the terms hereof through no fault of the terminating party. In the event of any termination,the Consultant will be paid for services rendered to the date of notice,all expenses subject to reimbursement hereunder,and other reasonable expenses incurred by the Consultant as a result of such termination. The fee and timing for the quote above is valid for a period of thirty(30)days from the date of this contract. In the event the Consultant's compensation under this agreement is a fixed fee, upon such termination, the amount payable to the Consultant for services rendered will be a proportional amount of the total fee I I i Mr.Hank Deibel,Arcadis LA 416-260 60b Avenue April 12, 2016 Page 4 of 5 based on the ratio of the amount of the work done, as reasonably determined by the Consultant,to the total amount of services which was to have been performed, less prior partial payments, if any, which have been made. Consultant shall not be responsible for,or liable for: 1. Changes to the Client-approved or submitted site plan or development application that may result from Client directives; changes to construction plans or surveys. 2. New, revised or improper interpretations or applications by government staff or government officials of development regulations or Comprehensive Plan policies. 3. Amendments to government approved final site plans that may result from platting requirements. 4: Delays to site plan or development applications or responses to staff reports that may be created by project team members,government agencies or any other unforeseen circumstances that may result from the development review process. 5. The quality of work or technical data and analysis provided by other project team members such as plans, documents,or electronic data prepared by the project engineer, surveyor,attorney, architect,traffic consultant,environmental consultant or others not employed by Lucido& Associates. This contract does not guarantee government approval of the development application. Consultant shall not be responsible for,or liable for,the denial of a government application based on failure to perform by project team member; or new, revised,or improper interpretations or applications of local development regulations or Comprehensive Plan policies by government staff or officials; or any other unforeseen circumstances that may result from the development review process. The Client acknowledges and agrees that land use matters at all levels of government are time consuming and unpredictable.The Consultant cannot guarantee success nor can the Consultant guarantee the timing of the governmental process.All time estimates, if any, are simply estimates based upon past experience and eventual time frames may vary considerably from any estimates given. The Consultant is not responsible for any time delays or damages to the Client because of any time delays regardless of the source of the delays. All fees charged by government are to be paid by the Client,regardless of the amount of the fee or the reason for the fee. The Consultant is not responsible for any fees charged by the government.The governmental process in land use matters may also involve the Client engaging other professionals to assist the Client.The Client is responsible for engaging all other professionals to assist the Client in achieving the Client's land use goals.The Consultant is not responsible for engaging other professionals, is not responsible for work product of other professionals and is not responsible for any fees of other professionals.The Consultant is not responsible for the government misinterpreting government regulations or making new interpretations of government regulations inconsistent with past interpretations. Mr.Hank Deibel,Arcadis LA#16-260 66'Avenue April 12,2016 Page 5 of 5 I SIGNATURE Please sign and return a copy of the proposal to us via mail or email. Retain the original proposal for your records. Work will commence upon receipt of the executed proposal. APPROVED AND ACCEPTED THIS DAY OF ,2016. LUCIDO &ASSOCIATES,LLP ARCADLS-US By: Thomas Lucido&Associates, P.A. a Florida Corporahon Its Managing Partner By: 1A cr By: Tho as P. u o, RLA,ASLA Hank Deibel Pres dent Associate Vice President BN/kpa ARCADIS SURVEY ESTIMATE WORKSHEET BY: W.DIVINE DATE: 4/11/2016 _ - -- CLIENT: INDIAN-RIVER-COUNTY PROJECT: 66TH AVENUE - - -- SECTION: TASK SENIOR EXPERT PROJECT ENGINEER CADD DRAFTER 2MAN 3MAN EXPENSE CLERICAL TOTAL PM WITNESS MANAGER SURVEYOR FIELD INSP. CREW CREW COST TASK PROJECT MANAGEMENT $ HEALTH AND SAFETY $ TRAVEL 4.00 70.00 $ 590.00 RUN CONTROL 1.00 4.00 $ 670.00 TOPO 296+00 TO 302+00 1.00 6.00 6.00 $ 1,458.00 TOPO 58TH STREET BRIDGE 0.50 3.00 4.00 $ 859.00 $ $ $ TOTAL HOURS 0.00 0.00 2.50 0.00 9.00 0.00 18.00 0.00 70.00 0.00 LABOR COST 175.00_[_ 195.00 150.00 115.00 88.00 75.00 130.00 180.00 1.00 55.00 TOTAL COST 1 0.00 L 0.00 375.00 0.00 792.00 0.00 2340.00 0.00 70.00 0.00 CONTRACT TYPE: LS LABOR X 1.00 FRINGE% 1.00 TOTAL $ 3,577.00 TOTAL LABOR: