HomeMy WebLinkAbout2016-176 i 't SECTION 00942 -Change Order Form No. 1 I i DATE OF ISSUANCE: August 31, 2016 EFFECTIVE DATE: nrtoher 1R, ?n1r, iI OWNER: Indian River Countv CONTRACTOR Ham R/O Systems. Inc. j Project: N. Hobart WTP Membrane Replacement OWNER'S Bid No. 2016025 I You are directed to make the following changes in the Contract Documents: Description: Task 1 —purchase of additional spares for membrane replacement Task 2—instrumentation upgrades to NF trains to meet DOW monitoring requirements Reason for Change Order: Comply with DOW membrane warranty requirements for monitoring membrane performance Attachments: (List documents supporting change)—change order backup for materials and labor for Task 1 (spare parts) and Task 2 (instrumentation) CHANGE IN CONTRACT CHANGE IN CONTRACT TIMES PRICE: Description Amount Description Time Original Contract Price $1,041,629.00 Original Contract Time: (days or dates) Substantial Completion. 180 Final Completion: 210 Net Increase(Decrease) $0.00 Net change from previous Change 0 from previous Change Orders No. . (days) Orders No. Substantial Completion: 180 Final Completion. 210 Contract Price prior to this $ 1.041.629.00 Contract Time prior to this Change Change Order: Order: (days or dates) Substantial Completion: 180 Final Completion: 210 Net increase(decrease)of $90.007.58 Net increase(decrease)this 60 this Change Order: Change Order: (days or dates) Substantial Completion: Final Completion: Contract Price with all $1.131,636.58 Contract Time with all approved approved Change Orders: Change Orders: (days or dates) j Substantial Completion: �6- h`;+C9 �\M�SSIO�IEgs.�, Final Completion: -24-a ,,�I® _ ..•,K�� ACC EP D. RECOMMENDED, APPROVED, e� •�Q: :o: By: ti Z B Y:7. , By C RACTOR(Signature) EN (NEER(Signature) OWNER(Signature) t �'`��:�• Bob Solari, Chairman Date: %0 —7—�� Date: 8/31/2016 Date: 10118116 "' •a;... ... .••' i ATTEST: Jeffrey?,- Smith, Cle of Cou d Comptr BY: 00942-1 t Clerk f i PROPOSAL dao o� 6d %Z9 HARK R/O SYSTEiNIS,INC.-310 CENTER COURT-VENICE,FLORIDA 3428 (P)941-488-9671 -(F)941-488-9400 Kimley-Horn ATTN: NICK BLACK 8/24/2016 1920 Wekiva Way, Email: Nick.Black@kimley-horn.com West Palm Beach, FL 33411 Proposal Request: Finished Water Sample Panel, Total Permeate Pressure Transmitters(Trains#1 & #2), Total Permeate Conductivity Transmitters(Trains#1-8), Trains#I &#2 Spare Parts Dear Mr. Black, Harn R/O Systems, Inc. is pleased to present the following combined change request proposal for The North Hobart WTP Membrane Replacement Project. Task#1: This request includes this supply, installation, and calibration of the instrumentation scope of supply detailed below: - Provide eight(8) Rosemount 1056 total permeate conductivity analyzers; one for each train (1-8). Analyzers shall be 24VDC loop powered. Analyzer will be provided with 2 Channel contacting conductivity capabilities and 4-20mA output. Should HART protocol be required please add $635.00 per transmitter. - Provide eight(8) Rosemount 400 VP total permeate conductivity sensors; one for each train(1-8). Sensors to be installed on the total permeate line of each train. - Provide two(2) Rosemount 3051 smart pressure transmitters; one for train 1 and one for train 2. Pressure transmitters shall be 24VDC loop powered and provided complete with-14.7-300 psig pressure range 4- 20mA output with HART protocol, local LCD operator display, and integral 3 valve manifold. - Provide and install electrical wiring as required to add instruments to existing trains. Verify existing cables and or provide cables from proposed added instruments to RIO-2 for Train 1-4 and RIO-5 for Trains 5-8 Label all new cables and terminate within the RIO cabinets. - Installation includes PVC installation fittings complete with 316 stainless steel hardware as required for a complete installation. - Integration of instrumentation into plant SCADA shall be by others. Exceptions and Clarifications: 1. SCADA Programming, 2. Additional Instrument 1/0 cards(if required) 3. Additional time may be required and will be requested upon receipt of additional equipment for incorporation into the work. 4. Expected lead time for equipment 6-8 weeks after receipt of order. Task#2: This pricing includes each prices for the following recommended vessel spare parts for Codeline E8U pressure vessels. 1. Qty 96- Head Seals, P/N#45320..................................................................................................$18.15 each 2 Qty 3 - Permeate Port Seals, P/N#CH50292 (20 per kit) ............. .............................................$24.75 per kit 3. Qty 5 - Securing Rings, P/N# 50562..............................................................................................$85.80 each 4. Qty 5 - Locking Ring Sets, P/N#CH45098-3K.............................................................................$99.00 per set 5. Qty 96 - Permeate Port Retaining Clips.........................................................................................$16.50 each 6. Qty 288 - Securing Screws, PM#45228....... ............................................................ ..................$2.20 each Exceptions and Clarifications: 1. Lead time: 3-4 weeks ARO. Task#3 This price ' cludes the installation of the sample piping from the clearwell area to the process roo - Supply and in one(1)three valve sample panel designed to sample the n ank blend, south bank blend, and finished water. anel shall be constructed of/4" FRP sheet provided complete with three(3)316 SS Swagelok '/4"turn plug es. T to e wall via 1 5/8"aluminum unistrut. EXCLUDED - Provide and install one (1)2" Sch. 80 FROM THIS ed into the wall for routing of the 1/4" sample tubing. CHANGE ORDER - Provide and install '/4"sample ng ple is to the sample panel. See exclusions. ExceptionsRoposal atio I. f the 2"PVC sleeves under the concrete drive only. 2. udes the PVC sleeves and hand digging the trench in the grass area on either side of the e. est fit to saw cut and replace concrete drives. Totalfor asks 1-3 ................................................................................................. .88 TASKS 1-2, $90,007.58 ONLY We Propose hereby to furnish material and labor—complete in accordance with above specifications,for the sum of See above All materials is guaranteed to be as specified.All work to be completed in a workmanlike manner according to standard practices.Any alteration or deviation from above specifica- ions involving extra costs will be executed only upon written orders,and%will become an Authorized Signature: extra charge over and above the estimate.All agreements contingent upon strikes,accidents or delays beyond our control.Owner to carry fire,tomado and other necessary insurance. NOTE.This proposal may be Our workers are fully covered by Workmen s Compensation Insurance. Withdrawn by HARN if not accepted within 30 calendar days. Acceptance of Proposal-The above prices,specifications and conditions are satisfactory and are hereby accepted.You are authorized Signature to do the work as specified.Payment will be made as outlined above. Signature: Date of Acceptance: IRCU-Hobart WTP a Pressure Vessel Spare Parts Cost Extended MATERIALS Head Seals 96 Ea 16.50 1,584.00 Permeate Port Seal kits(20 seals per kit) 3 Ea 22.50 67.50 Securing Rings 5 Ea 78.00 390.00 Locking Ring Sets 5 Ea 90.00 450.00 Permeate Port Retainer Clips 96 Ea 15.00 1,440.00 Securing Screws 288 Ea 2.00 576.00 0.00 0.00 Adder 4,507.50 0% Overhead 0 Sub Total 4,507.50 10% Mark up 450.75 4,958.25 Freight 100.00 5,058.25 Total 5,058.25 b Finis d Water Sample Panel Cost Extended MATERI Shop Fab ' ate&supply three valve sample panel-1/4"FRP,Aluminum Strut&Hardware 1 Ea 384.00 384.0 316 SS Swage k 1/4 turn plug valves 3 Ea 125.00 3 .00 PVC Sample tubin Sleeves 0 Ea 0.00 0.00 2"Long Radius 90 Ben 3 Ea 26.75 80.25 2"PVC Piping Sleeves 120 Ft 4 504.00 1/4"Sample Tubing low press 1 Roll) 1000 LF .20 200.00 Compression Fittings 1 LS 62.00 62.00 Misc Materials 1 LS 290.00 290.00 0 E 0.00 0.00 Adder 1,895.25 5% Overhead 94.7625 Sub Total 1,990.01 10% Mark up 199.00125 2,189.01 Freight 0.00 2,189.01 b Finished Water Sample Panel Cost Extended LABOR Engineering 10 Ea 125.00 1,250.00 Onsite Labor-2 Men 5 days 80 Ea 65.00 5,200.00 Onsite Labor OT-2 per day&6 travel 32 Ea 97.50 3,120.00 0.00 0.00 Onsite Expenses(Hotel,Vehicle,Fuel,Per-diem) LS 1,99562 1,995.62 Adder 11,565.62 5% Overhead 578.281 Sub al 12,143.90 10% <up 1214.3901 13,358.29 Freight 0.00 58.29 Tota I 15,547.3 c Additional Conductivity Instrumentation Cost Extended MATERIALS Rosemount 1056 total permeate conductivity analyzers p/n 56-03-20-30-AN 8 Ea 1,470.00 11,760.00 Rosemount 400 VP Sensor-P/N 400VP-11-36 8 Ea 626.00 5,008.00 Rosemount 45'Sensor Cable Extension w/VP connectors 8 Ea 315.00 2,520.00 Rosemount 3051 Total Permeate Pressure Transmitters 2 Ea 3,365.92 6,731.84 0 Ea 000 0.00 10x4 PVC Reducing Saddle 8 Ea 432.77 3,462.16 4x3 PVC Reducing Bushing 8 Ea 42.51 340.08 3 x 3/4 SS Reinforced Reducing Bushing 8 Ea 6749 539.92 1/4"Sample Tubing low pressure(1 Roll) 1000 LF 0.20 200.00 316 SS hardware&Consumables 8 Ea 26000 2,080.00 8 Ea 0.00 0.00 0 Ea 0.00 0.00 0 Ea 0.00 0.00 Adder 32,642.00 5% Overhead 1632.1 Sub Total 34,274.10 10% Mark up 3427.41 37,701.51 Freight 875.00 38,576.51 c Additional Conductivity Instrumentation Cost Extended SUBCONTRACTS Paragon Electric 1 LS 18,667.00 18,667.00 Integration-Excluded 0 Ea 0.00 0.00 0 Ea 0.00 0.00 Adder 18,667.00 5% Overhead 933.35 Sub Total 19,600.35 10% Mark up 1960.035 21,560.39 Freight 0.00 21,560.39 c Additional Conductivity Instrumentation Cost Extended LABOR Engineering 40 Ea 125.00 5,00000 Onsite Labor-3 Men 5 days 120 Ea 65.00 7,800.00 Onsite Labor OT-2 per day&6 travel 48 Ea 97.50 4,680.00 000 0.00 Onsite Expenses(Hotel,Vehicle,Fuel,Per-diem) 1 LS 2,993.43 2,993.43 Adder 20,473.43 5% Overhead 1,023.67 Sub Total 21,497 10 10% Mark up 2,149.71 23,646.81 Bond 1,165.62 24,812.43 Total 84,949.33 Grand Total 105, <8 $90,007.58