HomeMy WebLinkAbout2017-015 AMENDMENT NUMBER 2 WORK ORDER NUMBER 4
South Gifford Road Landfill
This Amendment 2 to Work Order Number 4 is entered into as of this 24th day of January, 2016, pursuant to
that certain Continuing Contract Agreement for Professional Services, dated November 15, 2011, and
that certain Extension and Amendment of Continuing Contract Agreement for Professional Services entered
into as of this 4th day of November, 2014 (collectively referred to as the "Agreement"), by and between
INDIAN RIVER COUNTY, a political subdivision of the State of Florida ("COUNTY") and Geosyntec
Consultants, Inc. ("Consultant").
1.The COUNTY has selected the Consultant to perform the professional services set forth in existing Work Order
Number 4, Effective Date March 1,2016.
2. The COUNTY and the Consultant desire to amend this Work Order as set forth on Exhibit 1 (Scope of Work)
attached to this Amendment and made part hereof by this reference. The professional services will be
performed by the Consultant for the fee schedule set forth in Exhibit 1 (Fee Schedule), and within the timeframe
more particularly set forth in Exhibit 1 (Time Schedule), all in accordance with the terms and provisions set forth
in the Agreement.
3. From and after the Effective Date of this Amendment, the above-referenced Work Order is amended as set
forth in this Amendment. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order
shall conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF,the parties hereto have executed this Work Order as of the date first written above.
CONSULTANT: BOARD OF COUNTY COMMISSIONERS
Geosyntec Consultants,Inc. OF INDIAN RIVER COUNTY
By: By:
Joseph E. Flescher,Chairman
Title: Sv
rinci al
•...~ BCC Approved Date:
..........
7�uarTy 24. 2(117
tv 0 61 ty�s~•.
oJ`,�• S���rF'�; Attest:Jeffrey R.Smith,Clerk of Court and Comptroller
*s By:
Depu erk
'i" off•' Approved:
Jason E Bro ,County Administrator
Approved as to form and legal sufficiency:
ylan T. Reingold,County Attorney
EXHIBIT 1
PROFESSIONAL SERVICES
GeosptecO' 316 South Baylen Street,Suite 201
Pensacola,Florida 32502
PH 850.477 6547
consultants FAX 850 477 6707
www.geosyntee.com
28 December 2016
Mr. Himanshu H. Mehta, P.E.
Managing Director
Solid Waste Disposal District
Indian River County
1325 74th Avenue SW
Vero Beach, Florida 32968
Subject: Proposal to Implement FDEP-Approved Remedial Action Plan Modification
(RAPM)Addendum No.3
Former South Gifford Road Landfill
Vero Beach,Indian River County, Florida
Dear Mr. Mehta:
Geosyntec Consultants (Geosyntec) is pleased to submit this letter proposal to the Indian River
County (IRC) Solid Waste Disposal District(SWDD) to provide professional services associated
with implementation of Florida Department of Environmental Protection (FDEP)-approved
RAPM Addendum No.3 related to the recalcitrant chlorinated volatile organic compound(CVOC)
plume at the Former South Gifford Road Landfill located in Vero Beach, Indian River County,
Florida. As requested by IRC, this fee proposal includes budget to implement activities required
by FDEP as outlined in the RAPM Addendum No. 3 dated 31 May 2016 and approved by FDEP
in a letter dated 15 July 2016. Geosyntec has prepared this proposal (professional services as
Exhibit 1)as Amendment No.2 to existing Work Order No.4 for the Continuing Contract Agreement
for Professional Services between IRC SWDD and Geosyntec.
The remainder of this letter provides a project background, an overview of a description of the
proposed scope of work, a budget estimate, and a discussion of the schedule for accomplishment
of the work described herein.
PROJECT BACKGROUND
Remedial activities have been completed at the Site historically r
p s y to address CVOC concentrations
identified in groundwater as outlined in the FDEP-required Remedial Action Plan (RAP) for the
Site, as well as subsequent RAP Modifications (RAPMs). Source removal activities were
completed in 2004 and subsequently bioremediation activities were implemented. Performance
monitoring data has been collected during subsequent semi-annual groundwater monitoring events
and the results of these monitoring events have been included within the semi-annual groundwater
XR16044-Gifford RAPM3 Imp
engineers I scientists I innovators
Mr. Himanshu H. Mehta, P.E.
28 December 2016
Page 2
monitoring reports provided to the FDEP. As outlined in the RAPM Addendum No. 2, it was
anticipated at the time that additional bioremediation injection activities would likely be warranted
in 3 to 5 years as the injected electron donor was depleted.
Trichloroethene (TCE) concentrations in the former source area (GR-MW30B) have fluctuated
following the injection activities associated with RAPM Addendum No. 2, with semi-annually
reported concentrations above the Groundwater Cleanup Target Level (GCTL) ranging from 124
to 3,150 micrograms per liter (µg/L) since June 2014, indicating that while groundwater
concentrations at the Site have significantly improved(with concentrations lower by several orders
of magnitude over pre-source removal concentrations), there may be recalcitrant CVOC mass in
the vicinity of the former source area that continues to contribute CVOCs to groundwater.
A RAPM3, requested by FDEP in correspondence dated 21 September 2015, was approved by
FDEP on 15 July 2016 and proposed a follow up injection of electron donor and dechlorinating
microbial culture in the former source area. Former source area pre-injection investigation
activities, including collection of discrete groundwater samples via direct push technology (DPT)
and collection of groundwater samples from site monitoring well injection wells, were conducted
in July 2016 and resulted in a refined target treatment area within the former source area.
PROPOSED SCOPE OF WORK
The proposed scope of work includes the activities required to implement the FDEP-approved
RAPM Addendum No. 3, including the procurement of injection amendment and drilling
subcontractor and performance of the injection activities. The remainder of this letter provides
details regarding the proposed scope of work and a budget estimate to accomplish the work
described herein.
For the purpose of budgeting,the scope of work has been divided into the following four phases:
• Phase 1 —Project Management;
• Phase 2—Meetings/Regulatory Interaction;
• Phase 3 —Injection Activities; and
• Phase 4—UIC and Performance Monitoring and Reporting.
The remainder of this section presents a general description of the activities to be performed in
each phase.
Phase 1 —Project Management
Under this task, Geosyntec will perform project planning and management responsibilities, such
as correspondence with IRC SWDD and FDEP, invoice review,project coordination.
XR16044-Gifford RAPM3 Imp
engineers I scientists I innovators
Mr. Himanshu H. Mehta, P.E.
28 December 2016
Page 3
Phase 2—Meetings/Regulatory Interaction
Under this task, Geosyntec will prepare for, and attend a project meeting with FDEP, as requested
by IRC SWDD. It has been assumed that two Geosyntec personnel will attend the meeting, which
will be held at the IRC SWDD office. A powerpoint presentation will be prepared for use during
the meeting.
Phase 3—Iniection Activities
Under this task, Geosyntec will implement the proposed injection activities, as outlined in the
FDEP-approved RAPM Addendum No. 3 and detailed information provided to IRC SWDD via
email on 28 December 2016 regarding the proposed injection approach and refined treatment area.
These activities will include monitoring well installation,procurement of injection amendment and
drilling subcontractor and performance of the injection activities. It has been assumed that the
injection activities can be completed in five field days(one day for onsite field prep,three days for
monitoring well installation and injection activities, and one day for breakdown). IDW will be
containerized and staged on-site for proper disposal.
Underground Injection Control (UIC) monitoring is required after injecting remedial fluids into
the aquifer according to Chapter 62-528 of the Florida Administrative Code (F.A.C.). UIC
monitoring will be included with the semi-annual sampling events until criteria are met.
Performance monitoring of CVOCs and total organic carbon will continue to be included as part
of the semi-annual sampling events. Budget for UIC and performance monitoring will be
conducted concurrently with semi-annual groundwater monitoring at the Site as a cost-savings
measure. Budget has not been included herein for these activities at this time.
Phase 4—Reporting
Implementation of RAPM Addendum No. 3 will be summarized in the semi-annual groundwater
monitoring report that follows completion of the implementation activities. A limited budget has
been included herein to incorporate a description of these activities and a summary of the results
into the currently authorized semi-annual groundwater monitoring reports.
SCHEDULE
Geosyntec will initiate project scheduling and implementation activities within two weeks of
receipt of notice to proceed from the County. The final field schedule will be based on
subcontractor availability and the delivery schedule for the injection materials. We anticipate that
the field activities will tentatively be conducted in February 2017. A description of the well
installation and dosing activities will be included in future semi-annual groundwater monitoring
report(s).
XR16044-Gifford RAPM3 Imp
engineers I scientists I innovators
Mr. Himanshu H. Mehta, P.E.
28 December 2016
Page 4
BUDGET ESTIMATE
A budget estimate for the scope of work outlined in Phases I through 4 of this proposal is
summarized in the following table, and a detailed budget estimate is provided as Exhibit 1. The
budget estimate presented in this proposal is based on Geosyntec's understanding of the project
requirements,our experience gained from executing similar tasks for SWDD since 2002 at the site,
and experience with groundwater remediation activities at similar facilities.
Geosyntec will not exceed the budget estimate without prior approval and written authorization
from IRC S WDD.
Phase 1 —Project Management $3,339
Phase 2—Meetings/Regulatory Interaction $4,901
Phase 3 —Injection Activities $41,379
Phase 4—Reporting $3,829
TOTAL $53,448
CLOSURE
Geosyntec appreciates this opportunity to offer our services. If this proposal is acceptable,please
indicate your agreement by signing the attached work authorization, which references this
proposal. Please return one signed work authorization to Ms. Johnson's attention. Please call
either of the undersigned with questions you may have as you review this proposal.
Sincerely,
rillh ,P.G.
Senior Hydrogeologist
J esn enbach, P.E.
Principal ngineer
Attachments
XR16044-Gifford RAPM3 Imp
engineers I scientists I innovators
ATTACHMENT A
BUDGET ESTIMATE
XR16044-Gifford RAPM3 Imp
engineers I scientists I innovators
Attachment A
BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE l: Project Management
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services
a.Senior Principal hr $221 2 $442
b.Principal hr $197 0 $0
c.Senior Project Geologist hr $184 4 $736
d.Project Engineer hr $143 12 $1,716
e.Engineer hr $124 0 $0
f. Senior Staff Geologist hr $109 0 $0
g.Staff Engineer hr $93 0 $0
Subtotal Professional Services $2,894
B. Technical/Administrative Services
a. Site Manager/Construction Manager hr $105 0 $0
b Senior Engineering Technician hr $78 0 $0
c.Designer/GIS hr $127 0 $0
d.Drafter/CADD Operator hr $77 0 $0
e.Technical/Administrative Assistant hr $87 4 $348
f.Technical Word Processor hr $89 0 $0
g. Clerical hr $92 0 $0
Subtotal Technical/Administrative Services $348
C. Reimbursables i
a.Lodging day $89 0 $0
b.Per Diem day $51 0 $0
c.Communications Fee 3%labor 003 3,242 $97
d.CADD Computer System hr $15 0 $0
e.Vehicle Rental day $75 1 0 $0
f. 8.5"x11"Photocopies each $012 0 $0
g.Airfare each $300 0 $0
Subtotal Reimbursables $97
TOTAL ESTIMATED BUDGET:PHASE 1 53,339
XR 16044.xlsx Geosyntec Consultants
Attachment A
BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 2: Meetings/Regulatory Interaction
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services
a.Senior Principal hr $221 0 $0
b.Principal hr $197 0 $0
c.Senior Project Geologist hr $184 10 $1,840
d.Project Engineer hr $143 0 $0
e.Engineer hr $124 0 $0
f. Senior Staff Geologist hr $109 16 $1,744
g.Staff Engineer hr $93 0 $0
Subtotal Professional Services $3,584
B. Technical/Administrative Services
a. Site Manager/Construction Manager hr $105 0 $0
b. Senior Engineering Technician hr $78 0 $0
c.Designer/GIS hr $127 0 $0
d.Drafter/CADD Operator hr $77 0 $0
e.Technical/Administrative Assistant hr $87 2 $174
f.Technical Word Processor hr $89 0 $0
g. Clerical hr $92 0 $0
Subtotal Technical/Administrative Services $174
C. Reimbursables
a.Lodging day $89 2 $178
b.Per Diem day $51 2 $102
c.Communications Fee 3%labor 0.03 3,758 $113
d.CADD Computer System hr $15 0 $0
e.Vehicle Rental day $75 2 $150
f. 8.5"xl l"Photocopies each $0.12 0 $0
g.Airfare each $300 2 $600
Subtotal Reimbursables $1,143
TOTAL ESTIMATED BUDGET:PHASE 2 $4,901
XR 16044.xlsx Geosyntec Consultants
I
Attachment A
BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 3:Injection Activities
ITEM BASIS RATE, QUANTITY ESTIMATED
BUDGET
A. Professional Services '�:I
a.Principal hr $221 2 $442
c.Senior Project Geologist hr $184 4 $736
d.Project Engineer hr $143 12 $1,716
e.Staff Engineer hr $93 60 $5,580
Subtotal Professional Services $8,474
B. Technical/AdministrativeServices st
a. Site Manager/Construction Manager hr $105 60 $6,300
Subtotal Technical/Administrative Services $6,300
x.
C. Subcontractors �:,:'.....+,,'
a.Driller Mod/demob/prep LS $428.00 1 1 $428
b.DPT Daily Rate day $1,444.50 3 $4,334
c.Per Diem,per night day $214.00 2 $428
d.Injection Pump Rental day $214.00 3 $642
e.Monitoring Well Installation each $323 14 1 $323
f.Decon LS $267.50 1 $268
g.Permits LS $53.50 1 $54
h.Drums each $53.50 1 $54
i.GPS Unit/Level/Rod for Surveying day $6300 1 $63
Subtotal Subcontractor Services $6,592
D. Reimbursables
a.Lodging day $89 4 $356
b.Per Diem day $51 5 $255
c.Communications Fee 3%labor 003 $14,774 1 $443
d.CADD Computer System br $15 0 $0
e.Vehicle Rental day $75 4 $300
f. SRS Delivery LS $1,169.51 1 $1,170
g. SRS Purchase drum $858.68 10 $8,587
h. SRS Injection Trailer/Injection Manifold week $700.00 1 $700
i. Tank Rental Delivery/Pickup LS $1,471.25 1 $1,471
j. Tank Rental day $5564 5 $278
k. Tank Cleaning Fee LS $802.50 1 $803
1. KB-I Plus(with delivery) LS $4,682.00 1 $4,682
m. Hydrant hookup and water usage LS $200.00 1 $200
n. Dedicated Miscellaneous Injection Supplies LS $250 1 $250
o. O&M Kit day 1 $65 4 $260
p. Well Installation Kit day $150.00 1 $150
q. Equipment Shipping each $54 2 $108
Subtotal Reimbursables $20,012
TOTAL ESTIMATED BUDGET:PHASE 3 $41,379
Notes:
1 Lodging and per diem rates were taken from the GSA website for the Vero Beach area(www.gsa.gov).
2. O&M Kit includes various small iterms for minor work/repairs(valves,PVC fittings,gaskets,etc.).
3 Well Installation Kit includes:water level indicator,PID/FID OVA,GPS unit,field geology kit,measuring
wheel,multi-meter(pH,temperature,conductivity,turbidity,dissolved oxygen,and oxidation reduction
potential),and miscellaneous supplies.
XR16044.xtsx Ge synlm Consultants
Attachment A
BUDGET ESTIMATE
SOUTH GIFFORD ROAD LANDFILL
PHASE 4: Reporting
ITEM BASIS RATE QUANTITY ESTIMATED
BUDGET
A. Professional Services
a.Principal $221 $195.67 2 $391
b Associate $197 $185.32 0 $0
c. Senior Project Geologist $184 $163.07 8 $1,305
d.Project Engineer $143 $129.12 8 $1,033
e.Engineer $124 $112.49 0 $0
f. Senior Staff Geologist $109 $100.16 0 $0
g. Staff Engineer $93 $84.24 0 $0
Subtotal Professional Services $2,729
B. Technical/Administrative Services
a. Site Manager/Construction Manager hr $105 0 $0
b. Senior Engineering Technician hr $78 0 $0
c.Designer/GIS hr $127 4 $508
d.Drafter/CADD Operator hr $77 0 $0
e.Technical/Administrative Assistant hr $87 2 $174
f Technical Word Processor hr $89 0 $0
g. Clerical hr $92 2 $184
Subtotal Technical/Administrative Services $866
C. Reimbursables
a.Lodging day $89 0 $0
b Per Diem day $51 0 $0
c.Communications Fee 3%labor 0.03 $3,595 $108
d.CADD Computer System hr $15 2 $30
e.Vehicle Rental day $75 0 $0
f. 8.5"x11"Photocopies each $0.12 500 $60
g. CADD Photocopies each $3 12 $36
Subtotal Reimbursables $234
TOTAL ESTIMATED BUDGET:PHASE 4 $3,829