RESOLUTION NO. 2000- 127
A RESOLUTION OF INDIAN RIVER COUNTY CERTIFYING
"AS -BUILT" COSTS FOR CERTAIN PAVING AND
DRAINAGE IMPROVEMENTS TO 18Tn AVENUE BETWEEN
1ST PLACE AND 2ND STREET, DESIGNATED AS PROJECT
NO. 9606, AND OTHER CONSTRUCTION NECESSITATED
BY SUCH PROJECT; PROVIDING FOR FORMAL
COMPLETION DATE, AND DATE FOR PAYMENT
WITHOUT PENALTY AND INTEREST.
WHEREAS, the Board of County Commissioners of Indian River County
determined that the improvements described herein specially benefitted the property located
within the boundaries as described in this title, designated as Project No. 9606, are in the public
interest and promote the public welfare of the county; and
WHEREAS, on April 6, 1999, the Board held a public hearing in the
Commission Chambers at which time the owners of the property to be assessed were afforded an
opportunity to appear before the Board to be heard as to the propriety and advisability of making
such improvements; and
WHEREAS, after such public hearing was held the County Commission adopted
Resolution No. 99-33, which confirmed the special assessment cost of the project to the property
specially benefitted by the project in the amounts listed in an attachment to that resolution; and
WHEREAS, the Director of Public Works has certified the actual "as -built" cost
now that the project has been completed is $19.77 per front foot, which is less than $20.19 per
front foot in the confirming Resolution No. 99-33.
LC) AirOcin
1
a.
RESOLUTION NO. 2000-127
NOW THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY
COMMISSIONERS OF INDIAN RIVER COUNTY, FLORIDA, that:
I. Resolution No. 99-33 is modified as follows: The completion date for Project
No. 9606 is declared to be August 30, 2000, and the last day that payment may be made avoiding
interest and penalty charges is ninety (90) days after passage of this resolution.
2. Payments bearing interest at the rate of 8.5% per annum may be made in
two equal installments, the first to be made twelve (12) months from the due date and the
subsequent payments to be due yearly from the due date. The due date is ninety (90) days after
the passage of this resolution.
3. The assessment roll for said project listed in Resolution No. 99-33 shall be as set forth
in attached Exhibit "A" to this resolution.
4. The assessments as shown in attached Exhibit "A" shall stand confirmed and remain
legal, valid, and binding first liens against the property against which such assessments are made
until paid.
5. The assessments shown in Exhibit "A", attached to Resolution No.99-33 were
recorded by the County on the public records of Indian River County, and the lien shall
constitute prima facie evidence of its validity.
2
RESOLUTION NO. 2000- 127
This resolution was moved for adoption by Commissioner
Ginn , and the motion was seconded by Commissioner
Stanbridge and, upon being put to a vote, the vote was as follows:
Chairman Fran B. Adams
Vice -Chairman Caroline D. Ginn
Commissioner Kenneth R. Macht
Commissioner Ruth Stanbridge
Commissioner John W. Tippin
Aye
Aye
Aye
Aye
Aye
The Chairman thereupon declared the resolution duly passed and adopted this
10th day of October ,2000,
9606 Resolution As-Built-mag.wpd
BOARD OF COUNTY COMMISSIONERS
OF INDIAN RIVER COUNTY, FLORIDA
B„ c5D)am, K7
Oid6ist,c)
Fran B. Adams, Chairman
Indian River County
Administration
Budget t✓
Legal
Risk Management
I Public Works
Engineering
3
Aonroved
Date
10
/0 3 00
d,
FINAL COST FOR:
18TH AVENUE BETWEEN 1ST PLACE AND 2ND STREET
DATE: August 15, 2000 TOTAL F.F.
PROJECT NO. 9606 TOTAL L.F.
FINAL COST
846.00
432.13
CONSTRUCTION
I Labor $7,060.23
�j
Outside Labor $133.04
Equipment $5,311.03
,I Equipment Rental $75.87
Asphalt $2,269.12
Concrete $85.96
Sod $2,098.80
Pipe/Culverts $923.66
Stabilizer& Limerock $1,649.53
Engineering Tests $56.55
Miscellaneous $6.50
TOTAL CONSTRUCTION COSTS: $19,670.29 $19,670.29
PERMIT FEES $350.00 $350.00
TITLE SEARCH FEES
($2.59/L.F.) $2.59x432.13 $1,119.21 $1,119.21
Sub -Total $21,139.50
Administration 3.005227% $635.29
Recording Fees $88.50
TOTAL $21,863.29
25% County's Cost
75% Property Owner's Assessment
2% Collection Fee (75% Figure)
TOTAL COST TO PROPERTY OWNERS:
Assessment =
$16,725.42
846 FF
$5,465.82
$16,397.47
$327.95
$16,725.42
$19.77
$16,725.42
9606FCST.WK4 09/29/2000
P
FINAL ASSESSMENT ROLL FOR PAVING AND DRAINAGE IMPROVEMENTS
TO: 18TH AVENUE FROM 1ST PLACE TO 2ND STREET
PROJECT NO. 9606
NAME & ADDRESS
William C. Ware
166 18th Avenue
Vero Beach, Florida 32962
* 2. Harold D. & Wilma Lee Ballard
176 18th Avenue
Vero Beach, Florida 32962
* 3.
Grace L. Miller
186 18th Avenue
Vero Beach, Florida
TOTAL FRONT FEET 846
COST TO PROPERTY OWNERS. $16,725.42
COST PER FRONT FOOT$19.77
FRONT
LEGAL DESCRIPTION FOOTAGE COST/F.F. TOTAL COST
14-33-39-00017-0001-00008.0
Lot 8, Block A, Moreland S/D
PBI 4-12
14-33-39-00017-0001-00009.0
Lot 9, Block A, Moreland S/D
PBI 4-12
14-33-39-00017-0001-00010.0
Lot 10, Block A, Moreland S/D
32962 PBI4-12
* 4. George A. & Patricia DeForest, III
196 18th Avenue
Vero Beach, Florida 32962
* 5 Roman J. & Virginia J. Walewski
1805 2nd Street
Vero Beach, Florida 32962
9606FIN.WK4
14-33-39-00017-0001-00011.0
Lot 11, Block A, Moreland S/D
PBI 4-12
14-33-39-00017-0002-00001.0
Lot 1, Block B, Moreland S/D
PBI 4-12, OR Book 444, PP 594
1
106.30 $19.77 $2,101.55
105.50 $19.77 $2,085.74
105.00 $19.77 $2,075.85
106.20 $19.77 $2,099.57
106.3 $19.77 $2,101.55
'A"
09/25/2000
FINAL ASSESSMENT ROLL FOR PAVING AND DRAINAGE IMPROVEMENTS
TO: 18TH AVENUE FROM 1ST PLACE TO 2ND STREET
PROJECT NO. 9606
NAME & ADDRESS
6. George F. & Beveraly Jean Evans
27920 Knickerbocker
Bay Village, OH 44140
• 7.
Daniel L. & Rose B. Schmitz
175 18th Avenue
Vero Beach, Florida 32962
• 8. Neil R. & Linda Manning
1820 1st Place
Vero Beach, Florida 32962
* = SIGNED PETITION
9606F1N.WK4
TOTAL FRONT FEET
COST TO PROPERTY OWNERS.
COST PER FRONT FOOT
846
$16,725.42
$19.77
FRONT
LEGAL DESCRIPTION FOOTAGE COST/F.F. TOTAL COST
14-33-39-00017-0002-00002.0
Lot 2, Block B, Moreland S/D
PBI 4-12, OR Book 459, PP 791
14-33-39-00017-0002-00003.0
Lot 3, Block B, Moreland S/D
PBI 4-12
14-33-39-00017-0002-00004.0
Lot 4, Block B, Moreland S/D
PBI 4-12
2
105 $19.77 $2,075.85
105.5 $19.77 $2,085.74
106.2 $19.77 $2,099.57
846.00 $19.77 $16,725.42
TOTAL FRONT COST PER F.F. iAL ASSESSMENT
FOOTAGE
EXffl"rr
'
09/25/2000