HomeMy WebLinkAbout2017-031 ATTACHMENT 1
-r
WORK AUTHORIZATION DIRECTIVE
No. 2017-002
St.David's lane at Grand Harbor Water Services Replacement Project
BLUE GOOSE CONSTRUCTION
DATE OF ISSUANCE: March, 2017 EFFECTIVE DATE: March 7, 2017
OWNER: Indian River County
CONTRACTOR: Blue Goose Construction
CONTRACT:WATER,SEWER AND RECLAIM WATER LINE REPLACEMENT/EXTENSIONS
AND MISCELLANEOUS LABOR CONTRACT, BID NO. 2015001,AWARDED September 9, 2014
PROJECT:St.David's Lane at Grand Harbor Water Services Replacement Prosect
COUNTY UTILITY PROJECT NO.: UCP#4130 CONTRACTOR'S PROJECT NO.: N/A
COUNTY WIP. No.
You are directed to proceed promptly with the following work:
Description:The project will consist of replacing approximately 42 single and double water services
serving the residences at St.David's Lane located in Grand Harbor.
Attachments: Attachment 2
Method of determining Contract Price:
M Unit Prices: Bid Items as established pursuant to Bid No. 2015001,and awarded by the Board of
County Commissioners on September 9, 2014 to Blue Goose Construction, Inc.
CO Lump Sum
17 Cost of the Work
The Cost of Labor, Contingency and Contract Time is summarized below:
Labor Cost (rounded)_ $89,255.65 Estimated 90 days from NTP
Contract Time:
ACCEPT RECOMD: APPROVED:
By: � By: B
Blue Goose Construction Arjun e , P.E. C N , CHA MAN
Labor Contractor Capital rojects Manager oseph E. Flescher
G ll
Date: � Date: algaln Date: March 7, 2017
.• 1SS10
••�pb�M... .•,!'✓FqsATTEST: Jeffrev R. Smith, Clerk of CourtAPPROVED AS TO FORM
%', • and C troller AND LEGAL SUFFICIENCY
Jt t
"• $Q. BY
be�ui
ty C erk
D LAN REINGOLD
j COUNTY ATTORNEY
a i••
•,�$t sej�•• ish taU ocaMicrosoft\Windowffemporaty Intemet Files\Content.Outlook\8BETR4YV\Work Authorization No.2017-
UBdVERCO•..
Indian River County Department of Utilities
LABOR AND MATERIAL COST
Project: GRAND HARBOR-St.David's Lane-WATER SERVICE REPLACEMENT PROJECT
Date: January 11,2017
IF
MATERIAL COSTS(HD
LABOR COSTS Waterworks)
Bid Bid Item Estimated Unit of Labor Unit Total Labor Material Unit Total Material
Item No. Description Quantity Measure Price Price Price Price
71 Mobilization,Demobilization,MOT 1 10 % $7,376.50
23 Test Holes/Potholes 84 EA. $250.00 $21,000.00
700 LF $4.80 $3,360.00 2.75 $1,925.00
01a Ilnstall 1"or 1-1/2"'pe or PVC Service Line
300 LF $33.35 $10,005.00 2.00 $600.00
07a Install 2-4"HDPE Directional Bore
Install Water Service Single Short with 2"Saddle and 6 EA. $300.00 $1,800.00 300.00 $1,800.00
18a Corp Stop at Main
Install Water Service Double Short with 2"Saddle and 9 EA. $350.00 $3,150.00 510.00 $4,590.00
18e Corp Stop at Main
Install Water Service Single Long with 2"Saddle and Corp 7 EA. $425.00 $2,975.00 310.00 $2,170.00
18g Stop at Main
Install Water Service Double Long with 2"Saddle and 20 EA. $425.00 $8,500.00 570.00 $11,400.00
18j Corp Stop at Main
181 Install 2"service casing 25 EA. $400.00 $10,000.00 2.75 $1,925.00
Install Asphalt Cement Replacement over full trench
width including Base&Sub-grade Compacted to County 100 TON $45.00 $4,500.00 $75.00 $7,500.00
67a Specifications
86a Lawn Restoration(Topsoil&Sod)up to 12'Wide 100 SY $2.25 $225.00 $2.16 $216.00
Well Point Dewatering,Each Tier depth up to 25'
2 EA. $3,500.00 $7,000.00
66a (Minimum 30'X 30'Work Area)
66b Well Points,Additional Points as Needed 50 EA $25.00 $1,250.00
Subtotal SubtotalWater System Labor $81,141.50 $32,126.00
Contingency 1 % 10% $8,114.15 20%
$6,425.20
Subtotal Water System Labor, Mob.,Demob.,MOT,
Subtotal Materials, &Permitting $89,255.65
$38,551.20
SubTotal Labor Cost $89,255.65 Materials $38,551.20
TOTAL COST $127,806.85
ATTACHMENT 2
BLUE Blue QUOTATION/ESTIMATE
GOOSE
6se
Construction
Heavy Mill Underground Utilities/Complete Site Development l Marine
Project: GRAND HARBOR-St.David's Lane-WATER SERVICE REPLACEMENT PROJECT
To: Indian River County Utilities
CONTACT: Steve.Bush
PHONE: 772-216-1873
Date: January 11,2017 EMAIL
LABOR COSTS
Bid Bid Item Estimated Unit of Labor Unit Total Labor
Item No. Description Quantity Measure Price Price
71 Mobilization,Demobilization,MOT 1 10 % $7,376.50
23 Test Holes/Potholes 84 EA. $250.00 $21,000.00
700 LF $4.80 $3,360.00
01a Install 1"or 1-1/2"'pe or PVC Service Line
300 LF $33.35 $10,005.00
07a Install 2-4"HDPE Directional Bore
Install Water Service Single Short with 2"Saddle and 6 EA. $300.00 $1,800.00
18a Corp Stop at Main
Install Water Service Double Short with 2"Saddle and 9 EA. $350.00 $3,150.00
18e Corp Stop at Main
Install Water Service Single Long with 2"Saddle and Corp 7 EA. $425.00 $2,975.00
18g Stop at Main
Install Water Service Double Long with 2"Saddle and 20 EA. $425.00 $8,500.00
18j Corp Stop at Main
181 Install 2"service casing 25 EA. $400.00 $10,000.00
Install Asphalt Cement Replacement over full trench
width including Base&Sub-grade Compacted to County 100 TON $45.00 $4,500.00
67a Specifications
86a Lawn Restoration(Topsoil&Sod)up to 12'Wide 100 SY $2.25 $225.00
Well Point Dewatering,Each Tier depth up to 25'
2 EA. $3,500.00 $7,000.00
66a (Minimum 30'X 30'Work Area)
66b Well Points,Additional Points as Needed 50 EA $25.00 $1,250.00
Subtotal SubtotalWater System Labor $81,141.50
Contingency 1 % 10% $8,114.15
Labor Total= $89,255.65
ATTACHMENT 3