Loading...
HomeMy WebLinkAbout2017-065 ATTACHMENT 1 WORK AUTHORIZATION DIRECTIVE No.2017-005 17''Street Existing Watermain Relocation Project BLUE GOOSE CONSTRUCTION DATE OF ISSUANCE:March,2017 EFFECTIVE DATE:May 9,2017 OWNER: Indian River County CONTRACTOR:Blue Goose Construction CONTRACT:WATER,SEWER AND RECLAIM WATER LINE REPLACEMENT/EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT, BID NO.2015001,AWARDED September 9,2014 C PROJECT:St.David's Lane at Grand Harbor Water Services Replacement Proiect P COUNTY UTILITY PROJECT NO.:UCP NIA CONTRACTOR'S PROJECT NO.:iL v COUNTY WIP. No. You are directed to proceed promptly with the following work: +, Description: Florida Department of Transportation (FDOT) is planning to widen a portion of 17"'Street v from US Highway 1 to the 171 Street Causeway Bridge. The subject widening is to begin in the summer 4a of 2017. As part of the widening, FDOT is also relocating drainage structures and pipes. The county's O existing water main will be in conflict with the :proposed roadway improvements and will need to be relocated. Attachments:Attachment 2 M thod of determining Contract Price: Unit Prices:Bid Items as established pursuant to Bid No2015001,and awarded by the Board of a County Commissioners on September 9,2014 to Blue Goose Construction, Inc. x ❑Lump Sum �4 El Cost of the Work 44-44 � The Cost of Labor,Contingency and Contract Time is summarized below: H04 Labor Cost(rounded)_ $109,457.92 Estimated 45 days from NTP Contract Time: �.c0 •.S ACCEPT RE COM EN jos'e OVED: r�oJ�� S/o^✓`�9; By. By: Blue Goose Construction Arjun ragoda TY,CHAIRMAN :—y: Labor Contractor Capita ro anager h E.Flescher '�'y•• f .�o�:� / LFR 000N�:E-'�'a Date: ( Zy Date: Date: May 9, 2017 APPROVED AS TO FOIN,4 AND LEGAL SUF-FIGii:,.l' C y F:\Utilities\UTIIdTY-EMPLOYEB FOLDERS\Arjuna wi 6goda\FDO'I\l7th Strect\[abor OonXot "AA"e M 6 GW0C COUNTY ATTORNEY