Loading...
HomeMy WebLinkAbout2017-066 ATTACHMENT 3 WORK AUTHORIZATION DIRECTIVE No. 2017-004 Heron Cay Mobile Home Park: Longpointe Court Water Main Replacement Project BLUE GOOSE CONSTRUCTION DATE OF ISSUANCE:April 21, 2017 EFFECTIVE DATE: May 9, 2017 OWNER: Indian River County CONTRACTOR: Blue Goose Construction CONTRACT:WATER,SEWER AND RECLAIM WATER LINE REPLACEMENT/EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT, BID NO. 2015001,AWARDED September 9, 2014 PROJECT.:Longpointe Court Water Main Replacement +' COUNTY UTILITY PROJECT NO.: UCP#N/A CONTRACTOR'S PROJECT NO.: N/A U COUNTY WIP. No. 471-169000-17518 You are directed to proceed promptly with the following work: +, Description: Construct new water main to serve existing homes along Longpointe Court in Heron Cay v MHP and abandon the existing water main. Project includes the construction of new water services and 4-4 o connection of existing homes to new system. x a� Attachments:Attachment 3 U Method of determining Contract Price: IN Unit Prices: Bid Items as established pursuant to Bid No. 2015001,and awarded by the Board of County Commissioners on September 9, 2014 to Blue Goose Construction, Inc. a Ed Lump Sum 0 Cost of the Work a� >1 The Cost of Labor, Contingency and Contract Time is summarized below: h a H Labor Cost (rounded)= $59,334.17 Estimated90 days from NTP w Contract Time: y; .V,��c�.M/S�•se ACCEP RECOMM LADED: APPROVED: •�: ?V1 BY: BY. � — 60sephE, FleschE!!r� Blue Goose Construction John M. Bo r, P.E. N Y,CHAIRMAIjI. Labor Contractor Utilities En ineer :?.--.. Date: 4 ` Date: 3 Date: May 9, 2017 APPROVED AS TO FORM AND LEGAL SUFFICjEj: jCy BY F•\Utilities\UTILITY-Engineering\Projects-Utility Construction Permits\[RC-Heron Cay-Longpointe WM8W1 Aft*W1,L"k Authorization No 2017-004.doe COUNTY ATT0 P i%,;U Y