HomeMy WebLinkAbout2017-194 WORK ORDER NUMBER 16
Van Antwerp Property Water Supply Restoration
This Work Order Number 16 is entered into as of this 2.2._day of,p,,Tovembe017, pursuant to that certain
Extension and Amendment of Continuing Contract Agreement for Professional Services entered into as of
this 4th day of November, 2014, (collectively referred to as the "Agreement") and that certain Extension of
Continuing Contract Agreement for Professional Services entered into as of this 24th day of October, 2017
(collectively referred to as the"Agreement"),by and between INDIAN RIVER COUNTY, a political subdivision
of the State of Florida("COUNTY")and Kimley-Horn and Associates, Inc.("Consultant").
The COUNTY has selected the Consultant to perform the professional services set forth on Exhibit A
(Scope of Work), attached to this Work Order and made part hereof by this reference. The professional
services will be performed by the Consultant for the fee schedule set forth in Exhibit B (Fee Schedule),
attached to this Work Order and made a part hereof by this reference. The Consultant will perform the
professional services within the timeframe more particularly set forth in Exhibit A(Time Schedule),attached
to this Work Order and made a part hereof by this reference all in accordance with the terms and provisions
set forth in the Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work
Order shall conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF,the parties hereto have executed this Work Order as of the date first written
above.
............
g�ONERs.*..••�
CONSULTANT: BOARD OF COUNTY COMMISSIONERS,*
Kimley-Hort and Associates, Inc. OF INDIAN RIVER COUNTY IQIV.
. .••
.�o�.
.11
By• a 'Ps •
T•
t �
Brian Good, P.E. Peter D. O'Bryan, ha�jrm �an • •.,,
Title: Se�iior V.P. ••.. !NDiAN'i":••
Approved Date: November 21, 2017
Attest:Jeffrey R. Smith, ' erk of Court ana; : 'patroller
By:
10 e•uty lerk
Approved: Ai
Jason Bro n,County Administrator
Approved as to form and legal sufficiency:
ylan T. Reingold, County Attorney
Exhibit A
Indian River County Department of Utility Services
Van Antwerp Property (Countryside Citrus) Water Supply Restoration
and Well Addition
PROTECT UNDERSTANDING
Indian River County Utilities (IRCU) is in the process of mitigating water
withdrawal impacts to the Van Antwerps (VA) existing groundwater wells from the
Hobart wellfield. The following scope consists of meetings and discussions,
preparation of documents, coordination, and implementation of the construction of
one new supply well, wellpump, and retrofitting one of Van Antwerps (VA)
irrigation supply wells #1 with submersible pumps & motors. The intent is to
restore, improve and preserve capacity of these wells from future impacts from the
Hobart wellfield.
SCOPE OF WORK
Below is the anticipated scope of work for VA Farm (Countryside) raw water
supply and well addition.
TASK 1 - MEETINGS AND DISCUSSIONS
Consultant will attend meetings, participate in conference calls, and be available for
discussions with Indian River County Utilities (IRCU) staff, St Johns River Water
Management District (SJRWMD), the Van Antwerps, and others. Consultant will
prepare for these meetings, including preparation of documents, participate in pre-
meeting discussions, and provide follow up to the meetings and discussions.
Consultant will attend and participate in conference calls during design and
implementation of the work described herein. It is assumed that weekly conference
calls will be attended initially, with call frequency reducing to twice monthly
during implementation of the work.
TASK 2 - PREPARE DOCUMENTS FOR NEW SUPPLY WELL
Consultant will prepare design documents and technical specifications for one new
permanent 6-inch Floridan aquifer supply well #6 for the VAW property, and
installation of a new submersible well pump in the existing VAW well (#1).
C\Users\mark miller\Documents\IRCt1 Van Antwerp Water Supply Restoration 117 17 docs Page I of4
Consultant will prepare 90% review documents and submit electronic copies to
IRCU staff for review. Consultant will revise the documents to include IRCU
comments and prepare final documents to be used for bidding or procurement of a
contractor to construct and implement the work.
Consultant will prepare mechanical, civil, well and wellhead details, and electrical
drawings for the scope of work assuming up to six (6) to eight (8) drawings.
Consultant will select pump and motor sizes, and assist with pump system startup
and testing of well and pump assembly during startup.
Electronic copies of final drawings and technical specifications will be provided to
IRCU for bidding, including up to 6 copies of drawings (11x17) and specifications
booklet (8-1/2 x 11).
TASK 3 - COORDINATION
Consultant will provide coordination with FPL, Indian River County, and VAW in
the siting of the well and final sizing of the service.
Consultant will coordinate with pump and electrical equipment suppliers, local
drillers, and contractors.
Consultant will coordinate replacement of the existing end-suction well pump at
VAW well #1 and electrical upgrades which may be necessary.
TASK 4 - CONSTRUCTION PHASE, FINAL IMPLEMENTATION
Consultant will provide construction phase services consisting of bid and/or
procurement phase, review of bids/price proposals, on-site observation of well
drilling and mechanical installation activities, review of submittals, and operational
testing of designed system.
The Consultant shall have no responsibility for any contractor's means, methods,
techniques, equipment choice and usage, sequence, schedule, safety programs, or
safety practices.
Consultant will provide construction phase services including hydrogeological
services, performance testing of well, and preparation of a brief well completion
report for well. Consultant will utilize subconsultant services of JLA Geosciences,
Inc. for the Hydrogeologic Consulting Services (JLA).
C\Users\mark miller\Documents\IRCl1 Van Antwerp Water Supply Restoration 117 17 doc.e Page 2 of 4
Consultant will provide hydrogeological support and observation services during
construction of the new 6-inch well. Consultant will provide up to 64 hours of on-
site hydrogeological services (JLA) for the new well. Consultant will review
drilling, geologic and geophysical data and provide recommendations for casing
setting depths and completion intervals. Consultant will review pump test results
and provide recommendations for permanent pump setting depth. Consultant will
coordinate water quality testing.
Consultant will provide limited contract document interpretation, shop drawing
and pay request review and change order requests. Shop drawing submittal will be
reviewed for conformance with the intent of the contract documents.
JLA will prepare a brief well completion report, including a summary of the
lithologic logs, field logs, hydrologic and water quality data, and preparation of
figures, data, lithogic logs, and appropriate attachments. Four (4) final copies of the
report will be furnished to Owner.
The installation of the well pump, column piping, and electrical service for
operation of the well will be observed, including startup and operational testing.
Contractor to provide coordination of startup. Consultant will attend up to two (2)
progress meetings, review construction related issues, and provide coordination
where needed.
ITEMS FURNISHED BY OWNER
The following items will be furnished by the Owner and are necessary for
completion of the tasks described herein.
• Access to site
• Preparations of front-end bid documents
SCHEDULE
Consultant will provide these services as expeditiously as practical and mutually
agreed upon schedule. Consultant will strive to accommodate the following
schedule:
1. Prepare Documents 4 - 6 weeks
2. Bidding/Procurement 4 - 6 weeks
3. Award/Contractor Mobilize 4 - 6 weeks
4. Drill well 4 - 6 weeks
C\llsers\mark nnlier\Documents\IRCU Van Antwerp Water Supply Restoration 117 17 docx Page 3 of 4
5. Well pump/electrical 4 weeks
6. Operational testing 4 weeks
TOTAL ANTICIPATED 24 - 32 weeks (6 - 8 months)
FEE SCHEDULE
We will provide these services in accordance with our Continuing Services Contract
Agreement for Professional Services dated November 4th, 2014, and extension of
Continuing Contract Agreement for Professional Services entered into as of the 24th
day of October, 2017 with Indian River County. The Consultant will provide
professional services on a lump sum fee basis as follows:
Task No. Task Task Fee
TASK 1 MEETINGS AND DISCUSSIONS $13,310
TASK 2 PREPARE DOCUMENTS FOR NEW $12,513
SUPPLY WELL
TASK 3 COORDINATION $3,300
TASK 4 CONSTRUCTION PHASE $15,485
TOTAL $44,608
ADDITIONAL SERVICES
The following services are not included in the Scope of Services for this project, but
may be required depending on circumstances that may arise during the execution
of this project. Additional services include, but may not be limited to the following:
• Water use permitting& coordination with SJRWMD
• Groundwater modeling
C\Users\mark miller\Documents\IRCIJ Van Antwerp Water Supply Restoration 117 17 doex Page 4 ofd
EXHIBIT B
ESTIMATE FOR ENGINEERING SERVICES
PROJECT Van Antwerp Property Water Supply Restoration
CLIENT Indian River County Utilities
ESTIMATOR MDM
DESCRIPTION DIRECT LABOR (MAN-HOURS 1
Meetings,Discussions,Preparation of SEN PROF/ Reg Prof P3 Dir Exp LINE
Documents,Construction&Implementation PM PE TECH CLK EXP TOTAL
PRINC MDM FH NB/VH SUB
NO 1 TASK 0
I MEETINGS AND DISCUSSIONS
Conference calls 10 $2,250
Meetings 16 $200 $3,800
.TLA $7,260 $7,260
2 PREPARE DOCUMENTS
Prepare drawings(6-8) 6 38 $5,340
Specs 2 4 $870
Elec(C&W) 2 $3,500 $3,950
JLA $2,353 $2,353
3 COORDINATION
Pump,FPL,&vendors 6 6 $1,980
JLA $1,320 $1,320
4 CONSTRUCTION
Bidding/procurement 4 4 $1,200
onsite observations 4 2 $1,110
submittals 2 6 $1,080
contractor coordination 6 2 $1,560
JLA $10,535 $10,535
TOTAL HOURS 0 58 0 58_ 4 25168 $0 S44,608
LABOR ($/HOUR) 235 225 150 105_ 75 $0 $0
SUBTOTAL o 13050 0 6090 300 25168 544,008 $0