WORK ORDER NUMBER 6
REUSE SYSTEM EVALUATION REPORT
This Work Order Number 6 is entered into as of this 13thday of February _, 2018,
pursuant to that certain Extension and Amendment of Continuing Contract Agreement for Professional
Services entered into as of this 4th day of November, 2014 (collectively referred to as the "Agreement") and
that certain Extension of Continuing Contract Agreement for Professional Services entered into as of this 24th
day of October, 2017 (collectively referred to as the "Agreement"), by and between INDIAN RIVER COUNTY, a
political subdivision of the State of Florida ("COUNTY") and MASTELLER & MOLER, INC. ("Consultant").
The COUNTY has selected the Consultant to perform the professional Scope of Services for the Fee
Schedule and Timeframe set forth in Exhibit A (Scope of Work), attached to this Work Order and made part
hereof by this reference all in accordance with the terms and provisions set forth in the Agreement. Pursuant
to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall conflict with the terms of the
Agreement and the terms of the Agreement shall be deemed to be incorporated in each individual Work Order
as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first written
above.
CONSULTANT: BOARD OF COUNTY COMMISSIONERSX"pPj .COLI
MASTELLER & MOILER, INC O IAN RIVER COUNTY
BY ( J11 By.
Earl H. Masteller, PE, BCEE Peter D. O'Bryan, Chairman
Title: President 9?9�•.: , ,
BCC Approved Date: February_ 13, 2018 �y:,gCpiiniTY
Attest: Jeffrey R. Smith, Clerk of ourt and Comptroller
By: (an �0_ - �w 1�
Deput lerk
r
Approved: xz,�
Jason E Brow , County Administrator
Approved as to form and legal sufficiency:
Dylan T. Reingold, County Attorney
FXHIRIT "A"
WORK ORDER NUMBER 6
REUSE SYSTEM EVALUATION REPORT
GENERAL INFORMATION
Masteller & Moler, Inc. (MM) is pleased to present you with Work Order Number 6 which provides
Professional Engineering Services for preparation of a Reuse System Evaluation Report. The work order
also includes design and preparation of Construction Plans and Bid Documents, if required, for the
expansion and modification of the North County (Hobart Road) Reuse Pumping Facilities.
The Professional Engineering Services in this work order are needed at this time to provide for additional
reuse water supply to the John's Island Community on the Barrier Island as required by a recent
agreement between Indian River County and John's Island Water Management. In addition, the Reuse
System Evaluation Report will provide an evaluation of specific portions of the existing reuse system. A
brief description of the scope of services and deliverables for Work Order Number 6 is provided as
follows:
SCOPE OF SERVICES
Task A — Reuse System Evaluation Report
Masteller & Moler, Inc. will prepare and provide a Reuse System Evaluation Report. The proposed
report will include the following:
1. Barrier Island Reuse Expansion — Evaluation of existing Hobart Road Reuse Storage and Pumping
Facility; Provide recommendations to extend reuse service to the Barrier Island, including 1.0
MGD to John's Island and other existing customers; If required by results of report, design of
station upgrades, plans, specifications, and bid documents.
2. Evaluate existing County reuse system, including the following:
a. Reuse production, storage, and pumping capacity of the South, West, and Central
Plants.
b. Transmission system capacity, including evaluation of the current bottleneck at the
Landfill vicinity to West WWTP and also from the West WWTP to the Hobart Road Reuse
Pump Station site.
c. Recommendations for improvements, and related cost estimates.
The following information is requested from the Utilities Department:
1. Monthly treated effluent flows generated by the wastewater treatment plants from 2008 to
present.
Exhibit "A" - 1
2. The County's estimated future reuse water flow quantity to be directed to future reuse water
storage / disposal facilities other than the North County Storage and Pumping Facility.
3. Modeling information by Knight & McGuire of the proposed John's Island reuse pipeline from
Hobart Road and Old Dixie Highway to the pipeline termination on John's Island.
Task B — Expansion & Modification of the Hobart Road Reuse Water Pump Station and Storage
Facilities
If required, Masteller & Moler, Inc. will utilize the information generated in the above -referenced
"Report" to design and prepare Construction Plans, Specifications, and Bid Documents showing and
describing the expansion pumps, piping, valves, motors, electrical equipment and controls.
Task C — Services During Biddi
If required, Masteller & Moler, Inc. will assist the County during project bidding, bid review, and provide
the County with our recommendations regarding contract award.
Task D — Services During Construction
If required, Masteller & Moler, Inc. will provide contract administration and periodic observation of
construction of the project described in Task B on an as -needed basis to observe that construction is in
reasonable compliance with the Contract Plans and Specifications. We will also attend meetings, review
shop drawings and monthly pay estimates from the Contractor. Following successful completion of the
Contract work as evidenced by as-builts and testing by the selected Contractor, we shall prepare
Engineer's Certificates confirming that the project improvements have been constructed in substantial
conformance with design plans and specifications.
Deliverables — The ENGINEER shall provide the COUNTY:
a. Reuse System Evaluation Report
b. Preliminary Construction Plans (If Required)
C. Preliminary Specifications (If Required)
d. Final Construction Plans (If Required)
e. Final Specifications (If Required)
f. Related digital AutoCAD, DOC, and PDF files
TIME SCHEDULE
Project shall be completed as follows:
Reuse System Evaluation Report (after NTP Receipt)
Preliminary Design, If Required (after NTP Receipt)
Final Design, If Required (after Client Comments Receipt)
Exhibit "A" - 2
2 Copies
2 Sets
1 Copy
10 Sets
2 Copies
75 Working Days
30 Working Days
10 Working Days
FEE SCHEDULE
Masteller & Moler, Inc. proposes to provide the outlined Scope of Services based on the following lump
sum fees:
• Task A — Reuse System Evaluation Report $ 39,600.00
• Task B — Expansion of Pump System (If Required) $ 11,850.00
• Task C — Bidding Services (If Required) $ 5,310.00
• Task D — Services During Construction (If Required) $ 7,650.00
file#1762
(1762_W O#6_18-0201. docx)