HomeMy WebLinkAbout2018-116WORK AUTHORIZATION DIRECTIVE No. 2018-003 615` Drive Water Main Replacement BLUE GOOSE CONSTRUCTION DATE OF ISSUANCE: June 11, 2018 ATTACHMENT 2 EFFECTIVE DATE: June 19, 2018 OWNER: Indian River County CONTRACTOR: Blue Goose Construction CONTRACT: WATER, SEWER AND RECLAIM WATER LINE REPLACEMENT / EXTENSIONS AND MISCELLANEOUS LABOR CONTRACT, BID NO. 2015001, AWARDED September 9, 2014 PROJECT: 61" Drive Water Main Replacement COUNTY UTILITY PROJECT NO.: UCP N/A CONTRACTOR'S PROJECT NO.: N/A COUNTY WIP. No. 47123536-044699-1852 You are directed to proceed promptly with the following work: Description: Install 6" directional bore to replace failed existing water main along 61" Drive. Method of determining Contract Price: M Unit Prices: Bid Items as established pursuant to Bid No. 2015001, and awarded by the Board of County Commissioners on September 9, 2014 to Blue Goose Construction, Inc. M Lump Sum 0 Cost of the Work The Cost of Labor, Contingency and Contract Time is summarized below: Labor Cost = $27,775.00 Estimated 90 days from NTP Contract Time: ACCEPTED: By: J Blue Goose Construction Labor Contractor G Date: //f Zit RECOM �EDQ: By: John M. Boyer, P. . Utilities Engineer Date: APPROVED: By: / Tndian Ri-,Te-r Peter D. O'Bryan, C O 91 U 7:1 t~ ro 0 U 4A O x Q) U 2 44 Date: June 19, 218 nn��``��RCOU����" APPROVED AS TO Folk 4R .._-�.,.w AND LEGAL SUFFICIENO BY L')YLANI I EiI,!t ��LCJ COUNTY ATTORNEY F:\Utilities\UTILITY - Engineering\Projects - Capital Projects\18-0516 61stDR WaterRep\Agenda Item\18-0619 WA Approval\Work Authorization No. 2018-003.doc Indian River County Department of Utilities CONSTRUCTION BUDGET - Labor Contract & Direct Purchase Project: 61st Drive Water Main Replacement Attachment 1 By: John M. Boyer, P.E. Date: May 30, 2018 LABOR COSTS MATERIAL COSTS (IRC Direct Purchase) Bid Bid Item Estimated Unit of Labor Unit Total Labor Material Unit Total Material Item No. Description Quantity Measure Price Price Price Price 01c Install 6" PVC Water Main 40 LF $6.00 $240.00 $4.80 $192.00 07b Install 6" HDPE Horizontal Directional Drill (SDR -11) 200 LF $38.85 $7,770.00 $6.00 $1,200.00 including fusion of MJ adaptors 9 Install Mechanical Restrained Joint Ductile Iron Fitting 0.25 Ton $4,100.00 $1,025.00 $4,100.00 $1,025.00 10a Install Mechanical Restrained Joints on Existing Main, 3" 12 EA $60.00 $720.00 $70.00 $840.00 through 8" 13a Grout Pipe Abandoned and Left in Place, 3" through 8" 220 LF $12.00 $2,640.00 $12.00 $2,640.00 23 Test Holes / Potholes 4 EA $250.00 $1,000.00 $0.00 $0.00 28 Install Temporary Jumper and Remove after FDEP 1 EA $500.00 $500.00 $0.00 $0.00 Clearance 29a Fill, pressure test, chlorinate, and flush water main, 4" 240 LF $1.50 $360.00 $0.00 $0.00 through 8" 30b Install Sample Point per County Detail, Remove after 2 EA $275.00 $550.00 $0.00 $0.00 FDEP Clearance 67b Remove, Dispose of and/or Replace Rock Base Course, 5 Ton $20.00 $100.00 $50.00 $250.00 Compacted to County Specifications 67c Remove, Dispose of and/or Replace Stabilized Sub- 5 Ton $14.00 $70.00 $50.00 $250.00 Grade Course, Compacted to County Specifications 86a Lawn Restoration (Topsoil & Sod) Includes Watering 100 SY $2.25 $225.00 $2.75 $275.00 88a Well Point Dewatering Set Up, Tier Depth up to 25', 2 LS $3,500.00 $7,000.00 $0.00 $0.00 (Minimum 30'X 30' Work Area) 88b Well Point Dewatering, Additional Paints Needed for 30 EA $25.00 $750.00 $0.00 $0.00 Larger Area or Linear Work 91 Mobilization, Demobilization, MOT (based on 30% Labor 1 LS $2,300.00 $2,300.00 $0.00 $0.00 Cost): Subtotals: Labor: $25,250.00 Material: $6,672.00 Contingency: 10% $2,525.00 30% $667.20 Labor: $27,775.00 Material: $7,339.20 TOTAL CONSTRUCTION COST: $35,114.20 FDEP PERMIT FEE: n/r Eng. Design (by Staff): $0.00 Geotechnical Testing: $0.00 Stake -Out & As -Built Survey (by Staff): $0.00 TOTAL PROJECT BUDGET: $35,114.20 F:\Utilities\UTILITY-Engineering\Projects Capita l Projects\ 18-0516 61stDR WaterRep\Cost Estimate- 61stDr Water. As,