HomeMy WebLinkAbout2018-262© 2018 CDM Smith All Rights Reserved CHANGE ORDER Indian River County Landfill, 6706-221060 Issued for Bid/January 2018 No. 01 Project: Segment 3 Cell 2 Expansion, Segment 2 Partial Closure, and Landfill Gas System Expansion DATE OF ISSUANCE November 9, 2018 EFFECTIVE DATE November 5, 2018 OWNER Indian River County OWNER'S Contract No. IRC Bid No. 2018025 CDM Smith Project No. 6706- 228608 CONTRACTOR Thalle Construction Co., Inc. ENGINEER CDM Smith Inc. You are directed to make the following changes in the Contract Documents: Description: 105 day extension to the Milestone 1 time Reason for change order: Wet weather conditions. Attachments: (List documents supporting change) CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME O inal Contract Price Original Contract Times Milestone 1 - November 5, 2018 $ Substantial Completion: No change Ready for final payment: No Change Days or dates Net changes Chang rders Net change from previous Change Orders \mprevious No. to No No. to No. $ Not Applicable --days Contract Price prior to hi hange Order Contract Time prior to this Change Order Milestone 1 - February 18, 2019 $ Substantial Completion: No change Ready for final payment: No Change Days or dates Net Increase (d rease) in this C ge Order Net Increase in this Change Order $ Milestone 1 + 105 days days Contra Price with all approved Change rders Contract Time with all approved Change Orders $ N Chan a in Contract Price Sulllst Cpmpletion: No Change .R�+•fi7r•ff,' , yment: No Change '•'s Days or dates RP AlP VED: sAEPT By: ENGIN R (Aut rized Signature) OWNER (Autho' tature�;CANT CT (Authorized V, Signa e) Bob Solari, C an....\OP•...• H Date: Date: November 2�•;•� Date: EJCDC No. C-800 ( 007 Edition) Prepared by the Engineers Joint Contract DoWMENOW�y The Associated General CONTRACTORs of America. Conformed - May 2018BY rR Supplementary Conditions DYLAN RE.INGOLD 00800-33 COUNTY ATTORNEY aha