HomeMy WebLinkAbout2019-085AWORK ORDER NUMBER 2018029-4
SECTOR 5 (CITY OF VERO BEACH)
BEACH AND DUNE RESTORATION PROJECT
2019 CONSTRUCTION ADMINISTRATION
This Work Order Number 2018029-4 is entered into as of this 4th day of
June , 2019 pursuant to that certain Contract Agreement relating to Engineering
and Biological support services for Sector 5 (Vero Beach) Beach and Dune Renourishment
Project entered into as April 3, 2018 ("Agreement"), between Indian River County, a
political subdivision of the State of Florida ("COUNTY") and Aptim Environmental &
Infrastructure, LLC ("CONSULTANT").
The COUNTY has selected the CONSULTANT to perform the professional services
set forth on Exhibit 1, attached to this Work Order. and made part hereof by this reference.
The professional services will be performed by the CONSULTANT for the fee schedule set
forth in Exhibit 2, attached to this Work Order and made a part hereof by this reference.
The CONSULTANT will perform the professional services within the timeframe more
particularly set forth in Exhibit 2, attached to this Work Order and made a part hereof by
this reference all in accordance with the terms and provisions set forth in the Agreement.
Pursuant to paragraph 1.3 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to
be incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of
the date first written above.
CONSULTANT
Aptim Environmental & Infrastructure, LLC
By:
Title:
Date:
Thomas P. Pierro, P. ., D.CE
Director of Operations
5`23 /z0 l9
By:
By:
BOARD OF COUNTY COMMIS.,
OF INDIAN RIVER COUNTY
Bob Solari, Chairman
Attest: Jeffrey R. Smith, Clerk of Court and
Comptjsller
By:
4i0040
eal) Deputy Clerk
oved:
Jason E
Approved a
By:
, County Administrator.
A and legal su iency:
/1 I 1,�l
William K. DeBraal, Deputy County Attorney
A
APTIM
May 17, 2019
Ms. Kendra Cope
Coastal Resources Coordinator
Indian River County Public Works
1801 27th Street
Vero Beach, FL 32960
Subject: Indian River County, FL
Sector 5 — 2018029 — Work Order #4
Construction Administration
Dear Kendra:
Exhibit 1
Aptim Environmental & Infrastructure, LLC
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel: +1 561 391 8102
Fax: +1 561 391 9116
www.aptim.com
This proposal outlines a scope of work for Aptim Environmental & Infrastructure, LLC (APTIM), to provide
professional services to Indian River County (the County) in support of the Sector 5 Beach and Dune Restoration
Project. The scope of work described herein is to support the County in administering construction for the Sector
5 project including periodic site observations and project certification. This proposal is intended to follow WO#1
— Pre -Construction Services for the Sector 5 project, which includes services through the Bidding and Construction
Preparation Services phase. The tasks to perform this work are listed below and described on the following pages.
A breakdown of the hours and expenses to develop the cost is attached. The scope and fee was developed
following the provisions of the Professional Services Agreement between Indian River County and APTIM, dated
April 3, 2018, to provide engineering and biological support services in support of the Sector 5 Beach and Dune
Restoration Project (RFQ#2018029).
Task 1: Progress Meetings
APTIM will coordinate and conduct weekly construction progress meetings with the County and Contractor.
APTIM will direct the meeting, covering work progress and schedule, conformance to plans and specifications,
and other relevant issues that may need to be discussed. APTIM will also record and distribute meeting minutes
to the project team. APTIM will collect and incorporate meeting minute comments and distribute final meeting
minutes, if applicable. The proposed budget for this task includes up to twenty-three (23) construction progress
meetings, based on the tentative schedule in the project Feasibility Evaluation provided to the County under
separate cover.
Deliverable
APTIM will distribute the final meeting minutes in PDF format to the project team.
Schedule
APTIM will distribute the draft meeting minutes within two (2) days of the meeting date. APTIM will distribute the
final meeting minutes upon receipt of any comments from the project team, prior to the next meeting.
APTIM
Cost
The lump sum cost for this task is $16,501.50.
Task 2: Site Observations
May 17, 2019
Page 2 of 6
APTIM will assist the County with engineering services, technical assistance, and on-site observations during
construction in order to certify the project was constructed in compliance with the contract documents as
Engineer of Record. APTIM will perform site visits on days of active construction and will provide up to eight (8)
hours of observation per visit. It is assumed that one (1) site visit per week will be scheduled on the same day as
the weekly progress meeting described in Task 1. APTIM will coordinate with the Contractor to perform site visits
on days when on-site construction activities are scheduled. The activities, observations, photographs, discussions
with the Contractor, and other issues will be documented in a daily observation report and submitted to the
County. APTIM's on-site representative will:
• Observe construction activities at the beach and periodically visit the upland sand mine(s)
• Visually assess the quality of fill material delivered to the project site and placed on the beach
• Observe the Contractor's work for compliance with the contract documents and permits
• Photograph and document the project as the work progresses
• Communicate issues, deviations, and/or consistencies that may arise
• Attend progress meetings
Upon completion of sections of constructed beach, two (2) duplicate sand samples will be collected at each FDEP
Reference Monument profile line to assess the grain size, silt content, gravel content, and Munsell color for
compliance, in compliance with the approved Sediment QA/QC Plan. One (1) sample will be quantitatively tested
and the other archived for 120 days after project completion.
Deliverable
APTIM will prepare observation reports summarizing each site visit, which will be used to document the project
progress and events. APTIM will prepare aisummary table of the sediment samples and test results for the
sediment compliance parameters, and a complete set of laboratory testing results as required by the approved
Sediment QA/QC Plan. The sediment testing results will be included in the Project Completion Report.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress and construction
schedule.
Cost
The lump sum cost for this task is $167,988.64.
Task 3: Construction Administration
APTIM will provide necessary interpretations or clarifications of the contract documents requested by the
Contractor through the County. APTIM will also make determinations on non -conforming and unauthorized work
as described in the project plans and specifications. APTIM will assist the County to prepare field changes or
A APTIM
May 17, 2019
Page 3 of 6
change orders requested by the Contractor, recommended for approval by APTIM, and agreed to by the County.
These documents will be submitted electronically in PDF format unless they must be sealed, at which point a hard
copy will be provided along with an electronic copy at the time of issuance. This scope of work is based on the
assumption that there will be a maximum of three (3) change orders and three (3) field adjustments.
APTIM will review daily quality control reports and other submittals provided by the Contractor. APTIM will review
and respond to correspondence from the Contractor through the County on an as needed basis. APTIM will also
respond to Contractor questions via phone. If the questions are sufficiently technical or the response may deviate
from the plans and specifications, APTIM will document these conversations and circulate a summary to the
County and Contractor via email. APTIM may require that the Contractor submit an official contract change
request.
During construction, APTIM will confer with the County, the Contractor, and regulatory agency staff to review and
document that the County has fulfilled reporting requirements cited in the permits. APTIM will assist the County
with documentation of permit compliance.
Deliverable
APTIM will provide project -related documentation as described above.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress, construction
schedule, and any issues which may arise during construction. However, APTIM work with the project team to
administer construction through completion.
Cost
The lump sum cost for this task is $28,114.00.
Task 4: Payment Review
APTIM will review all invoices for payment submitted by the Contractor and determine the amounts of progress
payments due based on completion of work. APTIM will analyze the survey data and compare the requested
payment volume to APTIM's computed pay volume. APTIM will also assess whether the Contractor is eligible for
other pay items and the amount due.
Deliverable
A letter of payment recommendation will be submitted to the County along with the Contractor's pay request in
PDF format.
Schedule
Payment recommendations will be submitted to the County in accordance with the requirements of the County's
standard terms and conditions for the project.
APTIM
Cost
The lump sum cost for this task is $8,724.00.
Task 5: Project Closeout
May 17, 2019
Page 4 of 6
APTIM will conduct one (1) substantial completion site visit with the County and Contractor, which will be
conducted following dune and beach fill placement. Upon completion of the substantial completion site visit,
APTIM will assist the County in the preparation of a punch list of items to be completed by the Contractor prior to
final acceptance. APTIM will conduct one (1) final acceptance walkthrough with the County following site
restoration, installation of dune vegetation, and demobilization. This final site visit will be conducted to confirm
that the Contractor has completed the punch list items.
Deliverable
APTIM will prepare and distribute a punch list to the project team upon completion of the substantial completion
site visit. A letter summarizing recommendations for final payment to the Contractor and release of any retainage
will be prepared at the completion of the project.
Schedule
APTIM will conduct the substantial completion site visit within seven (7) days of the receipt of written notice from
the Contractor of substantial completion. APTIM will conduct the final walkthrough within seven (7) days of receipt
of written notice from the Contractor that all punch list items have been completion.
Cost
The lump sum cost for this task is 5,391.88.
Task 6: Project Report & Certification
After completion of the project and the Contractor has demobilized from the site, APTIM will provide a written
Project Completion Report to the County, which will include a summary of the work performed along with a
compilation of the pertinent correspondence and data. APTIM will provide a written statement of completion and
certification to satisfy permitting requirements noting any deviations from the permitted projects. This
certification will state whether the project was constructed in substantial compliance with the plans and
specifications. Our certification will be qualified and based on the extent of APTIM's involvement in construction
observation.
Deliverable
APTIM will provide one (1) hard copy of the Project Completion Report and written statement of completion to
the County; electronic copies in PDF format will also be provided.
Schedule
The Project Completion Report will provided within approximately sixty (60) days after completion and acceptance
of construction as required by the permit. The written statement of completion and certification will provided
within thirty (30) days after completion and acceptance of construction authorized by the permit.
APTIM
Cost
The lump sum cost for this task is $8,904.27.
Task 7: Check Surveys
May 17, 2019
Page 5 of 6
APTIM will conduct up to two (2) independent check surveys to evaluate discrepancies that may arise between
the Contractor's requested pay volume and APTIM's computed pay volume based on the construction plans. This
will allow for a prompt, independent check should questions arise regarding the data obtained by the surveyor
retained by the Contractor to perform pay surveys. The surveys will be conducted with land-based equipment and
extend to sufficient wading depth to complete the data check.
Deliverable
APTIM will include the check survey cross-sections in the Project Completion Report, if applicable.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress and pay survey
results. APTIM will mobilize in an expeditious manner according to construction progress.
Cost
The lump sum cost for this task is $6,116.71.
Summary
The total lump sum cost to perform the proposed work described herein for Sector 5 — 2018029 — Work Order #4
is $241,741.00. Please refer to Exhibit 2, attached to the end of this proposal, for a summary of the costs and labor
hours of each Task. APTIM will proceed with the tasks upon receipt of a signed work order from Indian River
County (unless stated otherwise in the schedule). It is noted that some aspects of this Work Order are dependent
upon Contractor performance and are outside the control of APTIM and the County. As such, the scope, schedule
and cost described herein is provided as an estimate. APTIM will strive to execute each phase of the work within
budget and in as expeditious a manner according to construction progress. We will coordinate with the County in
the event that the scope, schedule, or budget arise due to unforeseen issues or circumstances.
Thank you for the opportunity to serve Indian River County. We look forward to continuing to provide expert
professional services to the County. Please do not hesitate to call if you have any questions.
Sincerely,
1717\k)----
Jordon
n^y-
Jordon Cheifet, PE, CFM
Senior Project Engineer
Aptim Environmental & Infrastructure, LLC
cc: Thomas Pierro, P.E., D.CE, APTIM
Authorized Corporate Signature
Thomas P. Pierro, P.E., D.CE
Printed Name
Director of Operations
Title
A APTIM
EXHIBIT 2
Indian River County, FL
Sector 5 - 2018029 - Work Order #4
Construction Administration
Summary of Cost by Task
May 17, 2019
Page 6of6
Task Number
Task Name
Labor
Subcontractors
Equipment
Materials
Other ODCs
Mobilization)
Travel
Totals
Task 1
Progress Meetings
$ 15,840.00
$ -
$ -
$ -
Task
$ 661.50
$ 16,501.50
Task 2
Site Observations
$ 143,630.00
$ -
$ -
$ -
$ -
$ 24,358.64
$ 167,988.64
Task 3
Construction Administration
$ 28,114.00
$ -
$ -
$ -
$ -
$ -
$ 28,114.00
Task 4
Payment Review
$ 8,724.00
$ -
$ -
$ -
$ -
$ -
$ 8,724.00
Task 5
Project Closeout
$ 5,092.00
$ -
$ -
$ -
$ -
$ 299.88
$ 5,391.88
Task 6
Project Report & Certification
$ 8,642.00
$ -
$ -
$ -
$ 262.27
$ -
$ 8,904.27
Task 7
Check Surveys
$ • 5,060.00
$ -
$ 1,039.50
$ -
$ 17.21
$ -
$ 6,116.71
. Totals =
$ 215,102.00
$ -
$ 1,039.50
$ -
$ 279.48
$ 25,320.02
$ 241,741.00
Indian River County, FL
Sector 5 - 2018029 - Work Order #4
Construction Administration
Summary of Labor Hours and Cost
Labor Title
Labor Bill
Rate
Progress Meetings
Site Observations
Construction
Administration
Payment Review
Project Closeout
Project Report 8
Certification
Check Surveys
Totals
Task1
Task2
Task
Task4
Task5
Task
Task?
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Principal Engneer/Sr Proj Mngr
$ 250.00
$ -
0 -
41
$10,250.00
4
$ 1,000 00
-
$ -
4
0 1,000.00
-
$ -
49
$ 12,25000
Expert Witness (Testimony)
$ 30000
$ -
$ . -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$
Program Manager
$ 190.00
$ -
$ -
$ -
$ -
$ -
$ -
$ -
-
0 -
SrCoastal Engineer/Proll6rgr
$ 165.00
96
$ 15,840.00
352
$ 58,080.00
79
013,035.00
40
$ 6,600.00
30
$ 4,950.00
20
$ 3,30500
-
$ -
617
$ 101,805.00
Coastal Engneer 0
$ 15000
$ -
$ -
$ -
-
$ -
-
$ -
.
5 -
-
$ _
-
$ -
Coastal Engineer 9
$ 125.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
5 -
Coastal Engneerl
$ 105.00
$ -
756
$ 79,381.00
$ -
-
$ -
-
0 -
40
$ 4,200.00
-
$ -
796
$ 83,580.00
Coastal Modeler II
$ 130.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Coastal Abdelerl
$ 11000
$ -
0 -
0 -
-
$ -
-
$ -
-
$ -
-
5
-
$ -
Professional Surveyor 8 Mapper
$ 145.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
4
$ 580.00
4
$ 58000
Hydrographer
$ 135.00
$ -
$ -
$ -
-
$ -
-
$
-
$ -
-
$ -
-
$ -
Surveyor
$ 95.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Survey Technician
5 8000
$ .
$ -
$ -
-
$ -
-
$ -
-
$ -
56
$ 4,48500
56
$ 4,480.00
Senior Marino Biologist ,
$ 13500
$ -
$ -
29
5 3,915.00
-
$ -
-
$ -
-
$ -
-
$ -
29
$ 3,91500
Marine Biologist II
$ 9500
$ -
$ -
$ .
-
5 -
-
$ -
-
$ -
-
$ -
-
$ -
Marine Biologist I
$ 7200
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$
ProfesslonalGedogst
$ 150.00
$ -
12
$ 1,800.00
$ -
-
5 •
-
$ -
-
$ -
-
$ -
12
$ 1,80000
Geologist In
5 13000
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Geologist 0
$ 9500
$ -
46
$ 4,37000
$ -
-
s -
-
$ -
-
5 -
-
$ -
46
$ 4,37000
Geologist I
$ 80.00
$ -
$ -
$ -
-
$ -
-
$ -
-
5 -
-
$ -
-
$ -
Senior CAD Operator
$ 140.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
CAD Operator
$ 105.00
$ -
$ -
6
$ 63000
8
$ 840.00
-
$ -
-
$ -
-
$ -
14
$ 1,47500
GIS Operator
$ 105.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$
Boat Captain
$ 8000
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Bookkeeper
$ 80.00
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Clerical
$ 71.00
$ -
$ -
4
$ 284.00
4
$ 284.00
2
$ 142,00
2
0 142,00
-
$ -
12
$ 852,00
Technician
$ 6000
$ -
$ -
$ -
-
$ -
-
$ -
-
$ -
-
'$ -
-
$ -
Subcontractors
_
-
$ -
-
$ -
-
$ -
-
$ -
_
$ -
-
$ -
_
$ -
-
$ _ -
EQuipment
-
. -
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
_
$ 1,039.50
-
$ 1,03950
Materials
-
-
5 -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
-
$ -
Other ODCs
-
-
$ -
-
$ -
-
$ .
-
$ -
-
$ -
-
$ 262.27
-
$ 1721
-
$ 279.48
Mob1¢etioNfrevel
-
-
$ 661.50
-
$ 24,35864
-
$ -
-
$ -
-
$ 299.88
-
$ -
-
$ -
-
$ 2532002
TOTAL
-
96
$ 16,501.50
1,166
$ 167,98864
159
528,11400
56
$ 8,72400
32
$ 5,39188
66
$ 8,904.27
60
$ 6,116.71
1,635
$ 241,741.00