HomeMy WebLinkAbout2019-149WORK ORDER NUMBER 2018029-5
SECTOR 5 (CITY OF VERO BEACH) BEACH AND DUNE RESTORATION PROJECT
2020 IMMEDIATE POST CONSTRUCTION BIOLOGICAL MONITORING AND FY
20/21 LGFR APPLICATION
This Work Order Number 2018029-5 is entered into as of this 10th day of
September , 2019 pursuant to that certain Contract Agreement relating to Engineering and
Biological support services for Sector 5 (Vero Beach) Beach and Dune Renourishment Project
entered into as April 3, 2018 ("Agreement"), between Indian River County, a political
subdivision of the State of Florida ("COUNTY") and Aptim Environmental & Infrastructure,
L ("CONSULTANT").
The COUNTY has selected the CONSULTANT to perform the professional services
set forth on Exhibit 1, attached to this Work Order and made part hereof by this reference.
The professional services will be performed by the CONSULTANT for the fee schedule set
forth in Exhibit 2, attached to this Work Order and made a part hereof by this reference. The
CONSULTANT will perform the professional services within the timeframe more particularly
set forth in Exhibit 2, attached to this Work Order and made a part hereof by this reference all
in accordance with the terms and provisions set forth in the Agreement. Pursuant to
paragraph 1.3 of the Agreement, nothing contained in any Work Order shall conflict with the
terms of the Agreement and the terms of the Agreement shall be deemed to be incorporated in
each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the
date first written above. •' 'c o u r� rr'
.• .. •.
BOARD OF COUNTY COMMI r 1\1‘OF INDIAN RIVER C JNT
0.2-3
CONSULTANT
A.tim Environmental & I
structure LLC.
B
drews, CH, PSM
T. e: Director of Operations
Date: 9,S~)i f'
B
By:
Bob Solari, Chairman y �td'IDP•.•••'
Attest: Jeffrey R. Smith, Clerk of Court and
Com.tro ler
By.
•
6
Seal) Deputy Clerk
Jason Br wn, Coun y dministrator
Approved form end legal suffi ncy:
By:
William K. DeBraal, Deputy County Attorney
A
APTIM
August 8, 2019
Ms. Kendra Cope
Coastal Resources Coordinator
Indian River County Public Works
1801 27th Street
Vero Beach, FL 32960
Aptim Environmental & Infrastructure, LLC
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel: +1 561 391 8102
Fax: +1 561 391 9116
www.aptim.com
Subject: Indian River County, FL
Sector 5 — 2018029 — Work Order #5
LGFR and Immediate Post -Construction Environmental Monitoring
Dear Kendra:
This proposal outlines a scope of work for Aptim Environmental & Infrastructure, LLC (APTIM), to provide
professional services to Indian River County (the County) in support of the Sector 5 Beach and Dune Restoration
Project. The scope of work described herein is to support the County with the following items:
1. Submittal of the Sector 5 2020-21 Local Government Funding Request (LGFR)
2. To conduct the Immediate Post -Construction Nearshore Hardbottom Biological Monitoring
3. To conduct the Immediate Post -Construction Sea Turtle Monitoring
The tasks to perform this work are listed below and described on the following pages. A breakdown of the hours
and expenses to develop the cost is attached. The scope and fee was developed following the provisions of the
Professional Services Agreement between Indian River County and APTIM, dated April 3, 2018, to provide
engineering and biological support services in support of the Sector 5 Beach and Dune Restoration Project
(RFQ#2018029).
Task 1: Sector 5 2020-21 LGFR
In order to distribute state funds for shore protection and inlet management projects, the Florida Department of
Environmental Protection (FDEP) requests that local sponsors submit an annual LGFR for their projects. The FDEP
modified the LGFR application based on the updated 62B-36 Rule which was effective August 5, 2013 and fully
implemented in 2014.
Task 1: Scope of Work
This scope of work details the tasks required to assist the County with preparing and submitting the 2020-2021
LGFR to the FDEP and responding to both the FDEP's Application Review and Project Assessment for Indian River
County's Sector 5 Beach and Dune Restoration Project. The FDEP's ranking methodology document will serve as
a guide for the responses we formulate on behalf of the County.
AAPTIM
August 8, 2019
Page 2 of 5
Task 1: Deliverable
APTIM will provide the draft LGFR application to the County for review and comment prior to submittal to the
FDEP. If FDEP requests additional information, APTIM will respond and provide additional information in
conjunction with and on behalf of the County as needed. Once initial project rankings and initial project
assessments are provided by FDEP, we will review the initial project assessment on behalf of the County and, if
warranted, provide the County with a draft letter to the FDEP identifying the areas within the applications that
may provide additional points to the County.
Task 1: Schedule
APTIM will submit the LGFR application by the deadline.
Task 1: Cost
The lump sum cost for this task is $8,702.00.
Task 2: Immediate Post -Construction Nearshore Hardbottom Biological Monitoring
The Biological Monitoring Plan developed for the Sector 5 project during permitting requires post -construction
biological monitoring of the hardbottom resources adjacent to the project area to monitor for potential secondary
impacts. The scope for this task is based on the FDEP-approved Biological Monitoring Plan (0363427 -001 -JC). The
post -construction nearshore hardbottom monitoring shall include:
1) Hardbottom edge mapping
2) Monitoring permanent transects
Task 2: Scope of Work
1) Hardbottom Edge Mapping:
APTIM shall map the position of the nearshore hardbottom edge for the entire Sector 5 project area, including
1000 feet north (updrift) and 2000 feet south (downdrift) of the project area (R-69 to R-88) for a length of
approximately 3.6 miles. A buoy with a Differential Global Positioning System (DGPS) antenna linked to a
topside laptop computer running HYPACK navigational software will be towed by divers to record the position
of the nearshore hardbottom edge. The divers will follow the inshore contour of the most prominent
hardbottom-sand border. The purpose of the survey is to provide a comparison for pre- and all subsequent
post -construction edge delineations.
2) Monitoring Permanent Transects:
Twenty (20) transects were established along the length of project influence, which includes 1000 feet north
(updrift) and 2000 feet south (downdrift). This includes nine (9) biological monitoring transects and eleven
(11) sediment only transects. All transects were established perpendicular to the shoreline and extend from
the nearshore hardbottom edge to a maximum distance of 50 meters seaward. APTIM will conduct the
immediate post -construction biological survey of the hardbottom using quadrat assessments, sediment
measurements and video/photo documentation as detailed in the Biological Monitoring Plan.
Up to nine (9) 0.5-m2 quadrats will be sampled along each transect to quantify the benthic community.
Sediment data will be collected using line -intercept and 1-m interval sediment depth measurements, and
video documentation will also be collected for the length of each transect. It is anticipated that the effort to
A APTIM
August 8, 2019
Page 3 of 5
delineate the hardbottom edge and monitor the transects will take up to eight (8) field days.
The data will be compiled and incorporated into a GIS database and in situ data Will be entered into an Access
database. Time to complete data entry, reduction, analyses, and report production is included in the cost
estimate to address the data management and reporting requirements for those 8 days of field operations.
Task 2: Deliverable
Raw data will be provided to FDEP and the County within 45 days of completion of the survey. This includes a PDF
of the scanned datasheets, excel spreadsheets with quadrat data, interval sediment depth measurements and
line -intercept data, shapefiles of the hardbottom edge survey, video and photo documentation. Additionally,
APTIM will provide a map of the project area and adjacent hardbottom resources with the hardbottom edge
delineation and monitoring transects overlaid onto recent, clear aerial photographs (in digital format).
An immediate post -construction biological monitoring report will be generated for submittal to the County and
regulatory agencies.
Task 2: Schedule
The immediate post -construction monitoring event will take place during summer 2020. Raw data from field
operations will be submitted to the County and FDEP within 45 days and the monitoring report will be submitted
within 90 days of completion of the survey.
Task 2: Cost
The lump sum cost for this task is $77,875.30.
Task 3: Immediate Post -Construction Sea Turtle and Shorebird Monitoring
The Sector 5 immediate post -construction sea turtle and shorebird monitoring will be managed and coordinated
by APTIM, and conducted by APTIM's approved subconsultant, Ecological Associates, Inc. (EAI).
Task 3: Scope of Work
APTIM will oversee the scope of work proposed by EAI and provide the necessary administrative coordination to
the County. The 2020 sea turtle monitoring effort along the approximate 3.5 mile shoreline within the Sector 5
Project Area addresses permit -required post -construction sea turtle and shorebird monitoring. The monitoring
will comply with all applicable conditions set forth in the regulatory permits and related authorizations for the
project. EAI has provided the enclosed proposal and cost breakdown for sea turtle monitoring tasks, which are
summarized as follows:
A. Mobilization and Management
B. Sea Turtle Monitoring and Data Management
C. Nest Marking and Monitoring
D. Nesting Shorebird Monitoring
E. Post -Construction Escarpment Surveys
F. Lighting Surveys
G. Reporting
A APTIM
August 8, 2019
Page 4 of 5
Task 3: Deliverable
EAI will submit a nesting season summary report within 90 days of completion of all monitoring activities.
Additionally, an Excel spreadsheet summarizing all nesting activity and reproductive success will be prepared and
submitted electronically to JCP Compliance and FWC.
Task 3: Schedule..
The sea turtle and shorebird monitoring will commence in February 2020.
Task 3: Cost
The lump sum cost for this task is $99,154.36.
Summary
The total lump sum cost to perform the proposed work described herein for Sector 5 — 2018029 — Work Order #5
is $185,731.66. Please refer to Exhibit 2, attached to the end of this proposal, for a summary of the costs and labor
hours of each Task. APTIM will proceed with the tasks upon receipt of a signed work order from Indian River
County.
Thank you for the opportunity to serve Indian River County. We look forward to continuing to provide expert
professional services to the County. Please do not hesitate to call if you have any questions.
Sincerely,
Stacy Buck
Lead Marine Biologist
Aptim Environmental & Infrastructure, LLC
cc: Thomas Pierro, P.E., D.CE, APTIM
Jordon Cheifet, PE, CFM, APTIM
Authorized Corporate Signature
Thomas P. Pierro, P.E., D.CE
Printed Name
Director of Operations
Title
'oAPTIM
EXHIBIT 2
August 8, 2019
Page 5 of 5
Indian River County, Florida
Sector 5 - 2018029 - Work Order #5
LGFR Application, Immediate Post -Construction Nearshore Hardbottom Biological Monitoring and Sea Turtle & Shorebird Monitoring
Summary of Cost by Task
Task Number
Task Name
Labor
Equipment
Materials
Travel
Subcontractors
Total
Task 1
LGFRApplication
$ 8,702.00
$ -
$ -
$ -
$ -
$ 8,702.00
Task 2
Immediate Post -Construction Nearshore
Hardbottom Biological Monitoring
$56,822.00
$14,246.30
$2,175.00
$ 4,632.00
$ -
$ 77,875.30
Task 3
Immediate Post -Construction Sea Turtle &
Shorebird Monitoring
$ 2,025.00
Sr Coastal Engineer/Proj Mngr
$ 165.00
16
$ 97,129.36
$ 99,154.36
Totals =
$67,549.00
$14,246.30
$2,175.00
$ 4,632.00
$ 97,129.36
$ 185,731.66
Indian River County, Florida
Sector 5 - 2018029 - Work Order #5
LGFR Application, Immediate Post -Construction Nearshore Hardbottom Biological Monitoring and Sea Turtle & Shorebird Monitoring
Summary of Labor Hours and Cost
Labor Title
Labor
Bill Rate
LGFR Application
Hardbottom Biological
Monitoring
Post -Construction Sea Turtle
& Shorebird Monitoring
Totals
Task 1
Task 2
Task 3
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Labor
Hours
Cost
Principal Engineer/Sr Proj Mngr
$ 250.00
4
$ 1,000.00
$ -
$ -
4
$ 1,000.00
Sr Coastal Engineer/Proj Mngr
$ 165.00
16
$ 2,640.00
$ -
$ -
16
$ 2,640.00
Coastal Engineer I
$ 105.00
16
$ 1,680.00
$ -
$ -
16
$ 1,680.00
Senior Marine Biologist
$ 135.00
24
$ 3,240.00
96
$ 12,960.00
15
$ 2,025.00
135
$ 18,225.00
Marine Biologist II
$ 95.00
$ -
364
$ 34,580.00
$ -
364
$ 34,580.00
Senior CAD Operator
$ 140.00
$ -
1
$ 140.00
$ -
1
$ 140.00
GIS Operator
$ 105.00
$ -
8
$ 840.00
$ -
8
$ 840.00
Boat Captain
$ 80.00
$ -
100
$ 8,000.00
$ -
100
$ 8,000.00
Bookkeeper
$ 80.00
$ -
2
$ 160.00
$ -
2
$ 160.00
Clerical
$ 71.00
2
$ 142.00
2
$ 142.00
$ -
4
$ 284.00
Subcontractors
-
-
$ -
-_
$ -
-
$ 97,129.36
-
$97,129.36
Equipment
-
-
$ -
-
$ 14,246.30
-
$ -
-
$ 14,246.30
Materials
-
-
$ -
-
$ 2,175.00
-
$ -
-
$ 2,175.00
Other ODCs
-
-
$ -
-
$ 4,632.00
-
$ -
-
$ 4,632.00
Mobilization/Travel
-
-
$ -
-
$ -
-
$ -
-
$ -
TOTAL
-
62
$ 8,702.00
573
$ 77,875.30
15
$ 99,154.36
650
$ 185,731.66