HomeMy WebLinkAbout2019-177CCNA2018 WORK ORDER NUMBER 25
HOBART PARK RENOVATIONS,
RESTROOM CONNECTIONS AND UTILITY SERVICE PLANS
This Work Order Number 25 is entered into as of this 5th day of November
2019, pursuant to that certain Continuing Consulting Engineering Services Agreement for
Professional Services entered into as of this 17th day of April, 2018 (collectively referred to as
the "Agreement"), by and between INDIAN RIVER COUNTY, a political subdivision of the State
of Florida ("COUNTY") and KIMLEY-HORN AND ASSOCIATES, INC. ("Consultant").
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference.
The professional services will be performed by the Consultant for the fee schedule set forth in
Exhibit B (Fee Schedule), attached to this Work Order and made a part hereof by this reference.
The Consultant will perform the professional services within the timeframe more particularly
set forth in Exhibit C (Time Schedule), attached to this Work Order and made a part hereof by
this reference all in accordance with the terms and provisions set forth in the Agreement.
Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall conflict
with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
EXHIBIT A — SCOPE OF WORK
Task 1— Preparation of Plans
The COUNTY desires to install restroom facilities at the southern portion of Hobart Park along
with the supporting water and sewer utilities servicing the building. As part of this scope
Kimley Horn will design a gravity sanitary sewer connection and a water tie in to a prefabricated
restroom facility as well as grading in the immediate area.
Kimley-Horn will prepare a dimensional site plan that conforms to local agency having
jurisdiction permitting requirements which will depict the location of the proposed restrooms,
sidewalks and landings and existing surrounding features. This plan will include site data
showing increase of impervious area on the site with the proposed improvements.
Kimley-Horn will prepare a limited Paving and Grading plan showing the proposed finished floor
elevation of the proposed restroom facilities and surrounding grades of proposed sidewalks.
The plan will identify paved areas for proposed sidewalk and associated details.
Kimley-Horn will prepare a limited Utility plan showing the existing utilities provided by
COUNTY GIS data and asbuilts on 77th Street. The limited Utility plan will also consist of the
proposed connection of sanitary and water service to the proposed restroom facilities. Kimley
Work Order No. 25
Hobart Park
Restroom Connections and
Utility Service Plans
Horn will coordinate with the manufacturer of the COUNTY selected restroom facility to
identify the inverts of the water and sanitary inverts leaving the proposed restroom facility.
In summary, the following plans will be prepared by the Consultant:
• Site Plan • Utility Plan
• Paving and Grading Plan • Detail Sheets
Kimley-Horn will revise the plans to address up to one (1) round of comments from each of the
permitting agencies under Task 3.
Kimley-Horn will prepare quantity take offs to incorporate into an engineering opinion of
probable cost as part of this task. The unit costs estimates will be based on pricing information
provided by contractors for previous projects completed. The opinion of probable cost will also
be based on assumptions that will be outlined in the document.
Kimley-Horn anticipates that electric service to the proposed restroom facility can be run off of
the existing service line to the existing restroom facility on the west side of the park. Kimley-
Horn will conceptual show a single PVC conduit to house a single phase 200 amp service from
the existing restroom facility to the proposed restroom facility on the utility plan. This will not
be in the area of the limited topographic survey, and will be shown on the utility plan for
reference to the contractor.
Task 2 —Topographic Survey
As part of this scope Kimley-Horn will prepare a specific purpose survey of the proposed area of
buildings and utilities (location of limited area provided by the COUNTY). The utilities will be to
service both the new proposed restroom facilities and the existing restroom facilities on the
east side of the park. This specific purpose survey shall consist of above ground existing
improvements, perimeter boundary lines, existing tree locations. The ground elevations will be
obtained on a 10' grid throughout the limited area. Any above ground visible improvements
within the limited area will be located. All elevations will be referenced to the North American
Vertical Datum of 1988 (NAVD 88).
Kimley-Horn will survey the existing sanitary sewer information for both locations, as well as
call 811 to mark existing utilities to incorporate locations into the proposed Topographic
Survey.
The topographic survey will be performed in accordance with the Standards of Practice set
forth in Chapter 5J-17 of the Florida Administrative Code.
Kimley-Horn will provide a digital base map of the surveyed property defined above as a base
for Site Construction Plan preparation.
Page 2 of 6
Work Order No. 25
Hobart Park
Restroom Connections and
Utility Service Plans
Task 3 - Permitting
As part of this scope Kimley Horn will prepare applications and supporting documentation for
the necessary permits to construct the new restroom facility and utility services to both the
eastern existing restroom facility and the new restroom facilitiy.
Kimley-Horn will submit to the Indian River County Planning Department for administrative
approval for the addition of the proposed restroom facility.
Kimley-Horn will submit for a utility construction permit for potable water and sanitary sewer.
This application will consist the equivalent residential use determination, projected water and
sewer flows and associated plans.
Kimley-Horn will prepare the supporting documentation for a St Johns River Water
Management District environmental resource permit exemption. Kimley-Horn will then submit
and coordinate with the District for an exemption determination from the St John River Water
Management District for the proposed improvements.
Kimley-Horn will prepare the supporting documentation to submit for an Indian River County
Type A stormwater permit exemption.
Kimley-Horn will attend a pre -application meeting with the Indian River Farms Water Control
District on the proposed utility crossings on their canal. Kimley-Horn will prepare an application
for utility construction permit through the District for approval of a water and sewer crossing.
It is assumed at this time that the sanitary can tie into the proposed sanitary near the new
restroom and will not require a separate dedicated service to service the existing restroom
facility on the east.
Due to the limited nature of the work, Kimley Horn does not anticipate more then one round of
comments from each of the agencies having jurisdiction above. Kimley-Horn will respond to up
to one round of comments from the permitting jurisdictions above as part of this task.
In summary the following permits are anticipated:
Indian River County Administrative Site Plan Approval
Indian River County Utility Construction Permit for Potable Water and Sanitary Sewer
St Johns River Water Management District Environmental Resource Permit Exemption
Indian County Type A Stormwater Permit exemption
Indian River Farms Water Control District permit for utility crossing
EXHIBIT B — FEE SCHEDULE
Page 3 of 6
Work Order No. 25
Hobart Park
Restroom Connections and
Utility Service Plans
The COUNTY agrees to pay and the Consultant agrees to accept for services rendered
pursuant to this Agreement fees inclusive of expenses in accordance with the following:
A. Professional Services Fee
The basic compensation mutually agreed upon by the Consultant and the
COUNTY is as follows:
Lump Sum Components
Task Labor Fee
Preparation of Plans $ 5,000
Limited Topographic Survey $ 4,000
Permitting $ 3,500
TOTAL $ 12,500
Page 4 of 6
Work Order No. 25
Hobart Park
Restroom Connections and
Utility Service Plans
EXHIBIT C — TIME SCHEDULE
Upon authorization to proceed by the COUNTY, final design documents are expected
to take approximately thirty (30) days from the Notice to Proceed (NTP).
NTP
Plans Preparation
contingent upon BOCC approval
30 days following NTP
(THE REMAINDER OF THIS PAGE IS INTENTIONALLY BLANK)
Page 5 of 6
Work Order No. 25
Hobart Park
Restroom Connections and
Utility Service Plans
The COUNTY has selected the Consultant to perform the professional services set forth on
Exhibit A (Scope of Work), attached to this Work Order and made part hereof by this reference.
The professional services will be performed by the Consultant for the fee schedule set forth in
Exhibit B (Fee Schedule), attached to this Work Order and made a part hereof by this reference.
The Consultant will perform the professional services within the timeframe more particularly
set forth in Exhibit C (Time Schedule), attached to this Work Order and made a part hereof by
this reference all in accordance with the terms and provisions set forth in the Agreement.
Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall conflict
with the terms of the Agreement and the terms of the Agreement shall be deemed to be
incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date
first written above.
CONSULTANT: BOARD OF COUNTY COIVIMISSION�R&° •••,,,
KIMLEY-HORN AN OCIATES,
OF INDIAN RIVER COUNTY co ...rr0?� t
INC.
By: By:
Bri Goo P. E. Bob Solari, Chairman '•; .' ' �`
Title: Principal
BCC Approved Date: November 5, 2019
Attest: Jeffrey R. Smith, Clerk of Co rt and Comptroller
By:
eputy Clerk
Approved:
Approved as to form and legal sufficiency:
Jason E Br `vn, County Administrator
6y -Ian T. Reingold, County Attorney
Page 6 of 6