HomeMy WebLinkAbout2020-103XGD SYSTEMS INC. CHANGE ORDER 1, CHANGE ORDER 2 + CONTINGENCY
AGREEMENT BID NUMBER 2020017
JONES PIER WETLAND RESTORATION AND CONSERVATION IMPROVEMENTS
7770 JUNGLE TRAIL, VERO BEACH, FL 32960
No. g (Page 1 of 2)
DATE OF ISSUANCE: 5/19/20 EFFECTIVE DATE:5/19/20
OWNER: Indian River County CONTRACTORXGD SYSTEMS, INC.
Project:Jones Pier Wetland Restoration Project OWNER'S Bid No. 2020017
You are directed to make the following changes in the Contract Documents:
1. The following Bid Items have been added to the Contract to account for modifications necessary during project
construction:
Change Order 1
18A
Construct Restroom / Pavilion - Add one light fixture to each of the 2
$1,945.00
LS 1
$1,945.00
restrooms and add the add'I. cost due to the building slab change.
49A
Engineer Construction Coord. / Asbuilts / Certifications - Add the costs of
$3,500.00
LS 1
$3,500.00
passing compaction testing.
52A
Excavation of wetland creation area and north outfall ditch - Additional
$1,061.50
LS 1
$1,061.50
ditch work east of 53" x 34" ERCP Culvert.
53A
Construct 4' Bottom Width, 2:1 Slopes 3' Depth Influent Ditch Along S
$9,079.33
LS 1
$9,079.33
Property Line -Add revetment along north side of south ditch bank.
Construct 1.5' Above Grade Walking Trail - Add the shifting &
56A
reconstructing the North Path adjacent to ponds approx. V to the south in
$9,659.90
LS 1
$9,659.90
order to provide room to reconstruct & deepen the ditch.
Furnish & install 45"x29" RCP Culvert /w Inlet Protection - lower invert by
58A
4" and add 4" depth of bedding stone under culvert; add Rip -Rap at west
$4,506.34
LS 1
$4,506.34
end (rip -rap provided by county).
Furnish & install 60"x36" RCP Box Culvert /w Inlet Protection & Stop Logs -
60A
change to 53" x 34" ERCP Culvert, add 4" depth of bedding stone under
$0.00
LS 1
$0.00
culvert; add Rip -Rap at west end (rip -rap provided by county).
67A & Furnish & install 4' High Split Rail Fence (1180 LF @ $13.15/LF) and 4' High
68aA Black Vinyl Chain Link Fence (Option A) (830 LF @ $18.57/LF) - delete both ($2,469.94) LS 1 ($2,469.94)
items from contract and add new fencing from Adron Fence to contract
(note entrance and maintenance gates will be handled in a future CO).
69A Furnish & install Boardwalks - add 5 bulkheads. $2,502.00 LS 1 $2,502.00
Seed & Mulch (Seed Purchased By Owner) - Add the purchase of
73A Bahiagrass/Millet blend seed and add hydroseeding to stabilize pond $6,894.34 LS 1 $6,894.34
banks.
New item Additional bond cost associated with CO#1 net increase. $293.43 LS 1 $293.43
Change Order 001 Subtotal $36,971.90
Change Order 2
New
#80
FPL Directional Bore 2" (service line to pavilion)
$30.80
LF
205
$6,314.00
#81
FPL Directional Bore 2" (installation only - FPL to provide material)
$27.50
LF
220
$6,050.00
#82
AT&T Directional Bore 2" (primary)
$30.80
LF
220
$6,776.00
#83
AT&T Directional Bore 1.5" (service to house)
$30.80
LF
135
$4,158.00
#84
COMCAST Directional Bore 2" (service to house)
$30.80
LF
135
$4,158.00
#85
Site Electric Directional Bore 1.25" (pavilion to garage / pavilion to
house)
$28.60
LF
135
$3,861.00
#86
Site Electric Directional Bore 1" (house to start of dock)
$28.60
LF
145
$4,147.00
#87
Site Electric Directional Bore 2" (screw pump to pavilion)
$30.80
LF
290
$8,932.00
#88
Site Electric - Electrician pulling CU conductors between FPL
hand hole to pavilion, pavilion to south building and pavilion to staff house
$15,262.50
LS
1
$15,262.50
#gg
Additional bond cost associated with CO#2 increase
$477.27
LS
1
$477.27
Change Order 002 Subtotal
$60,135.77
10% Contingency $42,287.50
The total Contract cost has increased $139,395.17 from $1,393,951.68 to
$1,533,346.85 as a result of Change Order No. 1, Change Order 2 and the additional contingency difference
added.
CONTRACT QUANTITIES TABLE:
CHANGE IN CONTRACT PRICE:
Description
Amount
Original Contract Price
$1,393,951.68
Net increase of this Change Order:
$ 139,395.17
Contract Price with all approved
Change Orders:
$1,533,346.85
XGD SYSTEMS LLC
415 NW Fl aowAve., 1.16002, Stuart, F134994
Tel: 772.286.3419 Fax 772-286-2855
By:
Print N me:�
Title:
CHANGE IN CONTRACT TIMES
Description
Time
Original Contract Time:
(days or dates)
Substantial Completion:
June 30, 2020
Final Completion:
540 days
Net increase (decrease) this
Change Order:
(days or dates)
Substantial Completion:
0
Final Completion:
0
Contract Time with all approved
Change Orders:
(days or dates)
Substantial Completion:
July 15, 2020
Final Completion:
540 days
BOARD OF COUNTY COMMISSIONERS
OF INDIAN RIVER COUNTY
By -
Susan Adams, Chairman
��iiY�CO,�� •d.
BCC Approved Date: May 19 2Ei�ss�`
Attest: Jeffrey R. Smith, Clerk of l;j iurt a
Comptroller
;�� .•• .yep.. � •:
Deputy Clerk _
Approved:
Approved as to form and legal sufficiency: By:
Jason EI BroVin, Countv-Administrator
County Attorney
CARTER ASSOCIATES, INC.
CONSULTING ENGINEERS AND LAND SURVEYORS
1708 21x1 S'1'REE7' - VERO BEACH, FLORIDA 32960.3472 - 772.562.4191 - 772.562.7180 (FAX)
JOIIN IL BI.IIM, P.L., 11KINCIPAL
DAVID Ii LIJE9'IDE- I'.S.M.. PRINCIPAL
GEORGE A. SIMONS, P.E., PRINCIPAL.
PATRICK S. WALTHER. 1'.E.. PKINCIPAI
MARVIN L. CAR I'NR, P.S.M.. Conwhanl a, lire firm
DEAN F. L.IJ ,111k, P.E., e nr, C tmNullaal to the Him
May 8, 2020
Ms. Elizabeth Powell
Assistant Director, Parks & Conservation Resources
Indian River County
550077 th Street
Vero Beach, Florida 32967
Attachment 1
FRANK S. CUC'CURESE, P.S.M.
CLIN'I'ON J. RAHIES,141:.
TYLER N. SPENCER, P.E.
RE: Jones Pier Wetland Restoration and Conservation Improvements
Change Order Description
Dear Beth:
Please see below a brief description of the attached change order items provided by the contractor,
XGD Systems LLC:
Change Order 001
18A Bid plans by Architect did not provide for lighting in the restrooms but were added later
during the building permit approval process.
49A Statement on phase 1 drawings indicates all passing density tests shall be paid by the
County.
52A Phase 2 drawings provided for rip -rap rubble in bottom of north outfall ditch. Owner's
representatives revised this area to be stabilized with fiber mat and planted with native
grasses. The rip -rap rubble will be re -purposed on-site.
53A Add 60 lineal feet of rip -rap revetment along the north bank of the south ditch adjacent to
the parking lot entrance to stabilize ditch bank from adjacent stormwater runoff.
56A The existing grade transition from the rear yards of the homesites north of the north ditch
created a slope in the ditch bank that caused concerns for future erosion. The sloping along
with vegetation removal in this area made it necessary to shift the walking trail south to
allow more room to re -stabilize the ditch bank.
Sclvu��Fk)rid�l
_ SAI 5,�;« ��� � _
P:N8-39 Jones P1MConsWcbACorres rWence1C0P1-2 Narrative.dom Page 1 of 3
58A Added rip -rap endwall and pipe bedding to south culvert in Jungle Trail per IRC right-of-
way permit comments.
60A Revised north culvert in Jungle Trail from 60"06" box culvert to a 53"04" elliptical
reinforced concrete pipe due to fabrication delays with the box culvert. Added rip -rap
endwall and pipe bedding per IRC right-of-way permit comments.
67A Eliminated bid items for fencing and Owner direct purchased split -rail fencing. Hog wire
& 68A fencing, guard rail, and pole gate materials are being provided by the contractor / fence
contractor. The revision resulted in a credit from the original bid.
69A Added pressure treated bulkheads at ends of boardwalks for slope transition to walking
trail.
73A Supply for wild flower seed for purchase by Owner were not available as per bid.
Contractor purchased seed directly and hydroseeded garden, wetland top of bank, and ditch
banks to prevent erosion until wetland plantings are installed.
Change Order 002
The fees presented in change order 002 were a result of the coordination with FPL, AT&T, and
Comcast to remove the existing overhead lines that run through the center of the proposed parking
lot and install underground with services to the proposed restroom pavilion and existing structures.
It should be noted that the existing overhead facilities were not located within a recorded easement
on the property.
The following is a breakdown of the of the necessary materials to be installed for the utility
providers. All of the items presented in change order 002 were not part of the original scope of
work.
FPL
• 205 LF directional bore for 2 -inch conduit from handhole at new pole location to service
pavilion.
• 220 LF directional bore for 2 -inch conduit (material provided by FPL) for primary.
AT&T
• 220 LF directional bore 2 -inch conduit for primary.
• 135 LF directional bore 1.5 -inch conduit from handhole to service house
Comcast
• 135 LF directional bore 2 -inch conduit from handhole to service house
(: Sewn i�; I�lurici<<
P:118-39 Jones PieAConstrucbon%CorrespondencelCOP1-2 NarraGve.dom Page 2 of 3
'CAIsince 1911
Site Electric
• 135 LF directional bore 1.25 -inch conduit from pavilion to garage and from pavilion to
house.
• 145 LF directional bore 1 -inch conduit from house to start of dock.
o 290 LF directional bore 2 -inch from screw pump to pavilion.
• Services for an electrician to pull CU conductors between FPL handhole to pavilion,
pavilion to house, and pavilion to garage.
I have reviewed the fees associated with the change orders and recommend payment. Should you
have any questions, please do not hesitate to contact me at our office.
Sincerely,
C�RTER ASSOCIATES, INC.
1�
JoH. Blum, P.E.
rincipal
PA18-39 Jones PieAConstructionlCorrespondencelCOPr-2 Narra0ve.docn Page 3 of 3 CL 1� Since I4)I l
Attachment 2
XGD SYSTEMS LLC
415 NW Flagler Ave., Unit 302, Stuart, FL 34994
Tel: 772-286-3419 Fax: 772-286-2855
www.xgd.systems
Jones Pier Wetland Restoration Project
Contractor: XGD Systems, LLC
C.O.#1 and C.O.#2
Date: May 6, 2020
Item
Description
Contract
Unit Price Unit Quantity Amount
Base Bid
18
Construct Restroom / Pavilion
$132,000.00
LS
1
$132,000.00
49
Engineer Construction Coord. / Asbuilts / Certifications
$9,185.00
LS
1
$9,185.00
52
Excavation of wetland creation area and north outfall ditch
$3.82
CY
24,950
$95,309.00
53
Construct 4' Bottom Width, 2:1 Slopes 3' Depth Influent Ditch Along S
$9,30
CY
510
$4,743.00
Property Line
56
Construct 1.5' Above Grade Walking Trail
$0.94
CY
4,450
$4,183.00
58
Furnish & install 45"x29" RCP Culvert /w Inlet Protection
$249.10
LF
68
$16,938.80
60
Furnish & install 60"x36" RCP Box Culvert /w Inlet Protection & Stop Logs
$393.03
LF
64
$25,153.92
67 & 68a
Furnish & install 4' High Split Rail Fence (1180 LF @ $13.15/LF) and 4' High
$30,930.10
LS
1
$30,930.10
Black Vinyl Chain Link Fence (Option A) (830 LF @ $18.57/LF).
69
Furnish & install Boardwalks
$203,170.00
LS
1
$203,170.00
73
Seed & Mulch (Seed Purchased By Owner)
$2,874.96
Acre
6
$17,249.76
Base Bid Subtotal $538,862.58
Change Order 001
18A
Construct Restroom / Pavilion - Add one light fixture to each of the 2
$1,945.00
LS
1
$1,945.00
restrooms and add the add'I. cost due to the building slab change.
49A
Engineer Construction Coord. / Asbuilts / Certifications - Add the costs of
$3,500.00
LS
i
$3,500.00
passing compaction testing.
52A
Excavation of wetland creation area and north outfall ditch - Additional
$1,061.50
LS
1
$1,061.50
ditch work east of 53" x 34' ERCP Culvert.
53A
Construct 4' Bottom Width, 2:1 Slopes 3' Depth Influent Ditch Along S
$9,079.33
LS
1
$9,079.33
Property Line - Add revetment along north side of south ditch bank.
Construct 1.5' Above Grade Walking Trail - Add the shifting &
56A
reconstructing the North Path adjacent to ponds approx. 6' to the south in
$9,659.90
LS
1
$9,659.90
order to provide room to reconstruct & deepen the ditch.
Furnish & install 45"x29" RCP Culvert /w Inlet Protection - lower invert by
58A
4" and add 4" depth of bedding stone under culvert; add Rip -Rap at west
$4,506.34
LS
1
$4,506.34
end (rip -rap provided by county).
Furnish & install 60"06" RCP Box Culvert /w Inlet Protection & Stop Logs -
60A
change to 53" x 34" ERCP Culvert, add 4" depth of bedding stone under
$0.00
LS
1
$0.00
culvert; add Rip -Rap at west end (rip -rap provided by county).
' XGD /*,,TDi! /�,,ECOBLUE
'GOLF:; )SYSTEMS
XGD SYSTEMS LLC
415 NW Flagler Ave., Unit 302, Stuart, FL 34994
Tel: 772-286-3419 Fax: 772-286-2855
www.xgd.systems
XGD °TDI ,ECOBLUE
GOLF:SYSTEMS
Furnish & install 4' High Split Rail Fence (1180 LF @ $13.15/LF) and 4' High
67A & 68aA
Black Vinyl Chain Link Fence (Option A) (830 LF @ $18.57/LF) - delete both
($2,469.94)
LS
1
($2,469.94)
items from contract and add new fencing from Adron Fence to contract
(note entrance and maintenance gates will be handled in a future CO).
69A
Furnish & install Boardwalks - add 5 bulkheads.
$2,502.00
LS
1
$2,502.00
Seed & Mulch (Seed Purchased By Owner) - Add the purchase of
73A
Bahiagrass/Millet blend seed and add hydroseeding to stabilize pond
$6,894.34
LS
1
$6,894.34
banks.
New Item
Additional bond cost associated with C0#1 net increase.
$293.43
LS
1
$293.43
Change Order 001 Subtotal $36,971.90
Change Order 002
New Item
Phase 1
FPL Directional Bore 2" (service line to pavilion)
$30.80
LF
205
$6,314.00
Utilities
New Item
FPL Directional Bore 2" (installation only - FPL to provide
Phase 1
material)
$27,50
LF
220
$6,050.00
utilities
New Item
Phase 1
AT&T Directional Bore 2" (primary)
$30.80
LF
220
$6,776.00
Utilities
New Item
Phase 1
AT&T Directional Bore 1.5" (service to house)
$30.80
LF
135
$4,158.00
Utilities
New Item
Phase 1
COMCAST Directional Bore 2" (service to house)
$30.80
LF
135
$4,158.00
Utilities
New Item
l
Site Electric Directional Bore 1.25" (pavilion to garagePhase /
$28.60
LF
135
$3,861.00
Utilities
pavilion to house)
New Item
Phase 1
Site Electric Directional Bore 1" (house to start of dock)
$28.60
LF
145
$4,147.00
Utilities
New Item
Phase 1
Site Electric Directional Bore 2" (screw pump to pavilion)
$30.80
LF
290
$8,932.00
Utilities
New Item
Site Electric - Electrician pulling CU conductors between FPL
Phase 1
hand hole to pavilion, pavilion to south building and pavilion
$15,262.50
LS
1
$15,262.50
Utilities
to staff house
New Item
Phase 1
Additional bond cost associated with CO#2 increase
$477.27
LS
1
$477.27
Utilities
Change Order 002 Subtotal $60,135.77
Total $635,970.25
XGD °TDI ,ECOBLUE