HomeMy WebLinkAbout2020-163FOURTH AMENDMENT TO AGREEMENT FOR PROFESSIONAL
SERVICES BETWEEN INDIAN RIVER COUNTY AND BOWMAN
CONSULTING GROUP, LTD
THIS FOURTH AMENDMENT TO AGREEMENT FOR PROFESSIONAL
SERVICES BETWEEN INDIAN RIVER COUNTY AND BOWMAN CONSULTING
GROUP, LTD ("Fourth Amendment") is entered into as of the _ day of August, 2020 by and
between Indian River County, apolitical subdivision of the State of Florida, whose address is 1801
27th Street, Vero Beach, Florida, 32960 ("County"), and Bowman Consulting Group, LTD., a
Virginian corporation authorized to do business in Florida, whose address is 3863 Centerview
Drive, Suite 300, Chantilly, VA 20151 (the "Consultant").
RECITALS
WHEREAS, on May 23, 2018, County and Consultant entered into an Agreement for
Professional Services for design and construction services for 581h Avenue Pavement Reclamation
and Resurfacing from 57th Street to 85th Street (the "Agreement"); and
WHEREAS, on June 12, 2018, the County and Consultant entered into a First Amendment
to the Agreement for preparation of waterline designs; bid services, construction engineering
services and project turnover of utility relocations associated with the construction of 58th Avenue
Pavement Reclamation and Resurfacing from 57th Avenue to 85th Street/CR 510; and
WHEREAS, on December 11, 2018, the County and Consultant entered into a Second
Amendment to the Agreement for the design of a communication network throughout the project
limits with the construction of 58th Avenue Pavement Reclamation and Resurfacing from 57th
Avenue to 85th Street/CR 510; and
WHEREAS, on July 2, 2019, the County and Consultant entered into a Third Amendment to the
Agreement for the upgrades to design to 58th Avenue by way of roadway widening between 77th
Street and 81St Street to accommodate the addition of a center turn lane to assist with traffic flow
into County owned Fairgrounds;
WHEREAS, County and Consultant desire to amend the Agreement to provide design and
permitting services for modifications needed at 81" Street and 73`d Street associated with the
construction of 58th Avenue Pavement Reclamation and resurfacing from 57th Street to 85th
Street/CR510.
NOW THEREFORE, in consideration of the mutual undertakings herein and other good and
valuable consideration, the receipt and adequacy of which is hereby acknowledged, the parties
agree, as follows:
1. Recitals. The above recitals are true and correct and are incorporated herein.
2. Amendment of Section 5 Compensation. The first sentence of Section 5 — Compensation
is amended to read as follows:
Page 1 of 2
"The COUNTY shall pay to Consultant the mutually agreed professional fee of $11,840.00
for the work performed under this Fourth Amendment, bringing the total payment to
consultant of FIVE HUNDRED AND NINE THOUSAND AND TWENTY EIGHT
DOLLARS ($509,028.00) for Services rendered for the Project, to be paid in monthly
installments or a deliverable basis as set forth in the Exhibits."
3. All other provisions of the Agreement shall remain in full force and effect.
IN WITNESS WHEREOF, County and Consultant have executed this instrument this 18 day
of August, 2020,
BOWMAN CONSULTING GROUP, LTD
4450 W. Eau Gallie Boulevard, Suite 232
Melbourne, F orida 32934
By.
Robert A. Hickey, Secretary
WITNESSED BY:
&Ualji7 C_
Approved as to Form and Legal Suffic'ency
William K. Debraal
Deputy County Att
Jason If. Br wn,
CountAMministrator
Page 2 of 2
0.
INDIAN RIVER COUNTY, FLORIDA;' , .,
By: 2o9�R opo:
Sus Adams, Chairman "•�FRCOUN.�''
Bo of County Commissioners
Approved by BCC August 18,20
Attest:
Jeffrey R. Smith, Clerk of Circuit Court
and omptroller
B
Deputy Clerk
Design Services:
1. Prepare a design modification at 81St Street, involves the replacement of an
existing 54" CMP with a 48" RCP from the existing headwall for the 48" RCP crossing 58th
Avenue. The replacement 48" RCP shall be doweled into the existing headwall and collar used
to secure it into place. The replacement 48" RCP shall be extended east to the canal with a rip
rap headwall. Coordinate with Indian River Farms Water Control District. Prepare permit,
update, bid schedule, modify road plan and profile sheet, prepare detail of wall connection,
prepare new drainage plan and profile sheet. ($3,500 LS)
2. Prepare a design modification at 81St Street, a roadside drainage swale parallel
with 58`h Avenue, on the east side of the road should be designed that extends approximately
400' north and 1200-1400' south of the replacement 48" RCP at 81" Street. The drainage swale
should be sloped to drain to a sump estimated to be about 300' south of the replacement 48" RCP
at 81St Street. At the sump, a Type "E" drainage structure will be located with a 24" RCP pipe
extending east to the canal with a rip rap headwall. Coordinate with Indian River Farms Water
Control District. Prepare permit, update bid schedule, modify road plan and profile sheet,
prepare detail of wall connection, prepare new drainage plan and profile sheet. ($2,000 LS)
3. Prepare a design modification for replacement of failed pipes at 73rd Street, for the
existing drainage system which consists of four pipes and a sand -cement sack headwall on all
four sides. The sand sack -cement walls will be replaced with a box structure estimated to be 6' x
8' with Type 7 manhole top. To the west, going under 58th Avenue, is an existing 60" CMP that
will be removed and replaced with a 54" RCP. To the north is an existing 42" CMP that will be
removed and replaced with 42" HP (High Performance Polypropylene Pipe). To the east is an
existing 60" ADS N-12 that was recently constructed and will remain. To the south is an
existing 42" CMP that will be removed and replaced with 42" HP (High Performance
Polypropylene Pipe). Prepare permit, update bid schedule, modify road plan and profile sheet,
prepare detail of wall connection, prepare new drainage plan and profile sheet. ($4,500 LS)
4. Assist with submittal reviews, respond to RFIs, interpretation of the drawings and
other design support tasks is $1,840.
TOTAL L UMP SUM FEE................................................................ $11,840.00