HomeMy WebLinkAbout2020-166CCNA2018 AMENDMENT 1 TO WORK ORDER 15
IXORA PARK SEWER SYSTEM REHABILITATION
This Amendment —L to Work Order Number 15 is entered into as of this 18 day of August , 2020, pursuant
to that certain Continuing Consulting Engineering Services Agreement for Professional Services entered into as of
this 17th day of April, 2018 (collectively referred to as the "Agreement"), by and between INDIAN RIVER COUNTY,
a political subdivision of the State of Florida ("COUNTY") and Kimley Horn and Associates, Inc ("Consultant").
1. The COUNTY has selected the Consultant to perform the professional services set forth in existing Work Order
Number 11, , Effective Date September 17, 2019.
2. The COUNTY and the Consultant desire to amend this Work Order as set forth on Exhibit A (Scope of Work)
attached to this Amendment and made part hereof by this reference. The professional services will be performed
by the Consultant for the fee schedule set forth in Exhibit B (Fee Schedule), and within the timeframe more
particularly set forth in Exhibit C (Time Schedule), all in accordance with the terms and provisions set forth in the
Agreement.
3. From and after the Effective Date of this Amendment, the above -referenced Work Order is amended as set forth
in this Amendment. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order shall
conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to be incorporated in
each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date first written above.
CONSULTANT:
Print Name: Kevin Schanen, P.E.
Title: Sr. Vice President
BOARD OF COUNTY COMMISSIONERS
OF INDIAN RIVER COUNTY
By:
Susa"dams, Chairman
BCC Approved Date: August 18, 2020
Attest: frey R. Smith erk of Court and Comptroller
By:
Dep y Clerk
Approved:
Approved as to form and legal sufficiency:
Jason E. 71
County A-fthinistrator
Dylan T. Reingold, County Attorney
EXHIBIT A
Amendment to Work Order Number 15
Indian River County Department of Utility Services (IRCU)
Ixora Park Sewer System Rehabilitation
PROJECT UNDERSTANDING
Kimley-Horn and Associates, Inc. (the Consultant) completed a Sewer System
Evaluation Survey (SSES) of the condition of the existing Ixora Park sewer
infrastructure and recommended improvements to rehabilitate or replace
components of the system.
In response to the recommendations, IRCU has opted to replace the entire Ixora
Park gravity sewer system. This amendment to Work Order 15 serves to adjust the
scope appropriately.
AMENDED SCOPE OF WORK
TASK 1 - PHASE 2 SSES
The Phase 2 SSES is complete, but additional funds are required for assessing the
feasibility of a vacuum sewer system and review of documents provided by AirVac.
The Consultant will provide a summary of findings and recommendations to IRCU
based on our assessment of the vacuum sewer system.
TASK 2 -PIPE LINING AND LATERAL REHABILITATION
Approximately 4,100 LF of gravity sewer pipe was recommended to be cleaned and
lined using cast -in-place pipe (CIPP) and nine (9) laterals on these pipes were
recommended for rehabilitation. These pipes will instead be fully replaced, and the
funds previously attributed to Task 2 will be allocated to Task 3.
TASK 3 - FULL SEWER PIPE REPLACEMENT
Task 3.1 - Survey
Previous survey of the Ixora Park neighborhood was completed by the Consultant
in 2016. In addition to being outdated, this survey was solely topographic and did
KAWPB_Civil\044572055 - Ixora Sewer Rehab\MIS\Amendment I.doex Page 1 of 3
not include survey data necessary to design a full replacement of the sewer system
or roadway improvements.
William B. Zentz and Associates, Inc. will serve as a Subconsultant on this project to
provide an updated survey to include survey data necessary for design by the
Consultant. The proposal is attached as Attachment 1.
Task 3.2 - Prepare Design Drawings and Specifications
Consultant will develop construction plans and technical specifications for full
replacement of the gravity sewer pipes in the Ixora Park sanitary sewer system
using survey provided by Subconsultant. Consultant will design roadway
improvements for excavated areas to address depressions in the roadway above
failed sewer pipe.
Consultant will prepare 60%, 90%, and final design drawings and specifications.
Consultant will attend a review meeting, respond to IRCU comments, and
incorporate agreed upon adjustments for the 90% and final plan sets.
Consultant will provide digitally signed and sealed electronic copies in PDF format
to comply with regulations put in place for the Coronavirus pandemic.
Consultant will prepare and provide an opinion of probable construction cost
(OPC) based on final design documents.
Consultant will apply for a Right -Of -Way permit on behalf of IRCU using the final
design documents.
Task 3.3 - Bidding Assistance
Consultant will prepare bid documents for IRCU to publicly advertise. Front-end
documents will be prepared and provided by IRCU. Consultant will provide
digitally signed and sealed electronic copies in PDF format.
Consultant will provide written responses to contractor requests for information
(RFI) related to the bid documents. Consultant will attend pre-bid meeting.
Consultant will review submitted contractor bids and prepare a written award
recommendation to IRCU.
KA\VPB_Civi1\044572055 - Ixora Sewer Rehab\MIS\Amendment Ldocx Page 2 of 3
ASSUMPTIONS
• Since this work is a direct replacement, permits from FDEP are not
anticipated.
• Contractor(s) will obtain any necessary Maintenance of Traffic (MOT).
• Contractor(s) will obtain any necessary Dewatering Permit from the South
Florida Water Management District (SFWMD).
• Road reconstruction will be limited to the area of sewer pipe replacement.
• IRCU will be responsible for all permit fees and advertising costs.
ADDITIONAL SERVICES
Any services not specifically provided for in the above scope will be billed as
Additional Services and performed at then -current hourly rates. Additional services
we can provide include but are not limited to construction phase services.
SCHEDULE
In general, the following schedule is anticipated from Notice to Proceed (NTP):
Task 3 FULL SEWER PIPE REPLACEMENT 4 - 6 months
FEE SCHEDULE
We will provide these services in accordance with our Continuing Services Contract
Agreement for Professional Services dated April 17th, 2018, with Indian River
County.
The Consultant will provide the following adjustments to the lump sum fees
indicated in Work Order 15:
Task No. Task
Adjustment to Task Fee
TASK 1 PHASE 2 SSES
+$2,118
TASK 2 PIPE LINING AND LATERAL REHAB
-$15,889
TASK 3 FULL SEWER PIPE REPLACEMENT
+$47,421
TOTAL FEE ADJUSTMENT
+$33,651
NEW WORK ORDER 15 TOTAL
$113,870
K:\1APB_Civil\044572055 - Ixora Sewer Rehab\MIS\Amendment l.docx Page 3 of 3
VNZ
William B. Zent7 & Associates, Inc.
Professional Surveying & Mapping
684 Old Dixie Highway Vero Beach, Florida 32962
Phone: (772) 567-7552 Fax, (772) 567-1751
June 23, 2020
To : Kimley-born & Assoc.
1920 Wekiva Way, Ste, 200
West Palm Beach, FI 33431
Attn: Ms. Vaughn Hyduk, P.B.
Proposal
Proposal 20-26
For : Survey Work
lxora Park Sanitary project
Vero Beach, 171
Indian River County, FI
Scope of work:
Task 1— Obtain location and NAVD'88 elevations of 39 sanitary manholes with invert elevations and roadway
elevations in Ixora Park and P,astview Gardens subdivisions and per attached aerial outlined in green. Locations
to be shown relative to platted right-of-way line tie-in.
Approximate total roadway length = 11,000 feet.
Deliverables: survey drawing depicting manhole locations/elevations and pavement locations relative to platted
rights-of-way.
Datums: Ilori ontal-NAD 83/90 or newer (to be noted on survey).
Vertical-NAVD `88
Associated fees:
Task 1 — lump sum fee....................................................................... $12,000.00
Total this proposal ...............................................$12,000.00
'Thank you for your request for survey services.
Please submit Purchase Order to Validate Proposal.