HomeMy WebLinkAbout2020-244CHANGE ORDER
No, 001
pROIECT: 240 X 80 Concrete pad
DATE OF ISSUANCE 11/05/20
EFFECTIVE DACE 11/07/20
OWNER; Indian River County - SWDD
OWNER'S Contract/gid No. 2020050
CONTRACTOR; Summit Construction of Vero Reach ITC
ENGINEER: Ronnie T. Jones, BSCE SWDD dt loan Fuentes, P,E, Kimley-Horn
You are directed to snake the fallowing changes In the Contract Documents:
Description: per proposal dated 10/02/2020 from Summit Construction; Vapor Barrier under stab,
Additional dirt work and install (2) 2' x 31-6" x 10" footings for Big Top `Cent stature (rib #1)
Reason for change order: Andersen Andre Oeotech recommendation for vapor barrier, relocation of Big
Top Tent atop concrete pad requires additional time, separate footings and dirt work
Attachments: (List documents supporting change)
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times 60 Days
S 183,000
Substantial Completion; 45 days
Ready for final payment: 60 days
Days or dates
Net changes from previous Change Orders
Net change from previous Change Orders No,
to No. none
No. to No. none
0 days
$ 0.00
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$ 153,000
Substantial Completion; 45 days
Ready for final payment; 60 days
Das or dates
Net Increase (decrease) in this Change Order
Net Increase in this Change Order
$ 7,015
90 days due to weather and permit requirements
Contract Price with all approved Change Orders
Contract `Gime with all approved Change Orders
$ 190,015
Substantial Completion; 120
Ready for final payment; ISO
Days or dates
r Date °:�t'ER COU
Attest: Jeffrey R. Smith, Clerk of
Cis t Court and Comptroller
Deputy Cleric
AiMD LL -GAL SUFFiOMNC`t
BY �a .
DYLAN �EililG" Lr
COUNTY ATTORNEY