Sector 3 — 2018006 — Work Order #8
Construction Administration
Dear Eric:
Aptim Environmental & Infrastructure, LLC
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel: +1 561 391 8102
Fax: +1 561 391 9116
www.aptim.com
This proposal outlines a scope of work for Aptim Environmental & Infrastructure, LLC (APTIM), to provide
professional services to Indian River County (the County) in support of the Sector 3 Beach and Dune
Restoration Project. The scope of work described herein is to support the County in administering
construction for the Sector 3 project including periodic site observations and project certification.
This proposal is intended to follow WO#7 — Pre -Construction Services for the Sector 3 project, which
includes services through the Bidding and Pre -Construction Services phase. The tasks to perform this
work are listed below and described on the following pages. A breakdown of the hours and expenses to
develop the cost is attached. The scope and fee proposal were developed following the provisions of the
Professional Services Agreement between Indian River County and APTIM, dated January 9, 2018, to
provide engineering and biological support services in support of the Sector 3 (Wabasso Beach) Beach
and Dune Restoration Project (RFQ#2018006).
Task 1: Progress Meetings
APTIM will coordinate and conduct weekly construction progress meetings with the County and
Contractor. APTIM will direct the meeting, covering work progress and schedule, conformance to plans
and specifications, and other relevant issues that may need to be discussed. APTIM will also record and
distribute meeting minutes to the project team. APTIM will collect and incorporate meeting minute
comments and distribute final meeting minutes, if applicable. The proposed budget for this task includes
up to twenty-one (21) construction progress meetings, based on the tentative schedule.
Deliverable
APTIM will distribute the final meeting minutes in PDF format to the project team.
Schedule
APTIM will distribute the draft meeting minutes within two (2) days of the meeting date. APTIM will
distribute the final meeting minutes upon receipt of any comments from the project team, prior to the next
meeting.
AAPTIM November 13, 2020
Page 2 of 8
Cost
The lump sum cost for this task is $20,076.00.
Task 2: Site Observations — Truck Haul
APTIM will assist the County with engineering services, technical assistance, and on-site observations
during construction in order to certify the project was constructed in compliance with the contract
documents as Engineer of Record. APTIM will perform site visits on days of active construction, which
are assumed to be 6 days per week, and will provide up to eight (8) hours of observation per visit. It is
assumed that one (1) site visit per week will be scheduled on the same day as the weekly progress
meeting described in Task 1. APTIM will coordinate with the Contractor to perform site visits on days
when on-site construction activities are scheduled. The activities, observations, photographs, discussions
with the Contractor, and other issues will be documented in a daily observation report and submitted to
the County. APTIM's on-site representative will:
• Observe construction activities at the beach and periodically visit the upland sand mine(s)
• Visually assess the quality of fill material delivered to the project site and placed on the beach
• Observe the Contractor's work for compliance with the contract documents and permits
• Photograph and document the project as the work progresses
• Communicate issues, deviations, and/or consistencies that may arise
• Attend progress meetings
The proposed budget for this task includes up to 98 days of construction observations, based on the
tentative schedule.
Upon completion of sections of constructed beach, two (2) duplicate sand samples will be collected at
each FDEP Reference Monument profile line to assess the grain size, silt content, gravel content, and
Munsell color for compliance, in compliance with the approved Sediment QA/QC Plan. One (1) sample
will be quantitatively tested and the other archived for 120 days after project completion.
Deliverable
APTIM will prepare observation reports summarizing each site visit, which will be used to document the
project progress and events. APTIM will prepare a summary table of the sediment samples and test
results for the sediment compliance parameters, and a complete set of laboratory testing results as
required by the approved Sediment QA/QC Plan. The sediment testing results will be included in the
Project Completion Report.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress and
construction schedule.
Cost
The lump sum cost for this task is $207,028.40.
,>,APTIM
Task 3: Site Observations — Dredge
November 13, 2020
Page 3 of 8
APTIM will assist the County with engineering services, technical assistance, and on-site observations
during construction in order to certify the project was constructed in compliance with the contract
documents as Engineer of Record. APTIM will perform site visits on days of active construction, which
are assumed to be 7 days per week, and will provide up to twelve (12) hours of observation per visit. It is
assumed that one (1) site visit per week will be scheduled on the same day as the weekly progress
meeting described in Task 1. APTIM will coordinate with the Contractor to perform site visits on days
when on-site construction activities are scheduled. The activities, observations, photographs, discussions
with the Contractor, and other issues will be documented in a daily observation report and submitted to
the County. APTIM's on-site representative will:
• Observe construction activities at the beach and/or dredge as needed
• Visually assess the quality of fill material delivered to the project site and placed on the beach
• Observe the Contractor's work for compliance with the contract documents and permits
• Photograph and document the project as the work progresses
• Communicate issues, deviations, and/or consistencies that may arise
• Attend progress meetings
The proposed budget for this task includes up to 42 days of construction observations, based on the
tentative schedule.
Upon completion of sections of constructed beach, two (2) duplicate sand samples will be collected at
each FDEP Reference Monument profile line to assess the grain size, silt content, gravel content, and
Munsell color for compliance, in compliance with the approved Sediment QA/QC Plan. One (1) sample
will be quantitatively tested and the other archived for 120 days after project completion.
Deliverable
APTIM will prepare observation reports summarizing each site visit, which will be used to document the
project progress and events. APTIM will prepare a summary table of the sediment samples and test
results for the sediment compliance parameters, and a complete set of laboratory testing results as
required by the approved Sediment QA/QC Plan. The sediment testing results will be included in the
Project Completion Report.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress and
construction schedule.
Cost
The lump sum cost for this task is $127,890.40.
Task 4: Construction Administration
APTIM will provide necessary interpretations or clarifications of the contract documents requested by the
Contractor through the County. APTIM will also make determinations on non -conforming and
unauthorized work as described in the project plans and specifications. APTIM will assist the County to
prepare field changes or change orders requested by the Contractor, recommended for approval by
$,APT I M November 13, 2020
Page 4 of 8
APTIM, and agreed to by the County. These documents will be submitted electronically in PDF format
unless they must be sealed, at which point a hardcopy will be provided along with an electronic copy at
the time of issuance. This scope of work is based on the assumption that there will be a maximum of four
(4) change orders and four (4) field adjustments.
APTIM will review daily quality control reports and other submittals provided by the Contractor. APTIM
will review and respond to correspondence from the Contractor through the County on an as needed
basis. APTIM will also respond to Contractor questions via phone. If the questions are sufficiently
technical or the response may deviate from the plans and specifications, APTIM will document these
conversations and circulate a summary to the County and Contractor via email. APTIM may require that
the Contractor submit an official contract change request.
During construction, APTIM will confer with the County, the Contractor, and regulatory agency staff to
review and document that the County has fulfilled reporting requirements cited in the permits. APTIM will
assist the County with documentation of permit compliance.
Deliverable
APTIM will provide project -related documentation as described above.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress, construction
schedule, and any issues which may arise during construction. However, APTIM work with the project
team to administer construction through completion.
Cost
The lump sum cost for this task is $26,873.00.
Task 5: Payment Review
APTIM will review all invoices for payment submitted by the Contractor and determine the amounts of
progress payments due based on completion of work. APTIM will analyze the survey data and compare
the requested payment volume to APTIM's computed pay volume. APTIM will also assess whether the
Contractor is eligible for other pay items and the amount due.
Deliverable
A letter of payment recommendation will be submitted to the County along with the Contractor's pay
request in PDF format.
Schedule
Payment recommendations will be submitted to the County in accordance with the requirements of the
County's standard terms and conditions for the project.
Cost
The lump sum cost for this task is $10,390.00.
,`APTIM
Task 6: Project Closeout
November 13, 2020
Page 5 of 8
APTIM will conduct one (1) substantial completion site visit with the County and Contractor, which will be
conducted following dune and beach fill placement. Upon completion of the substantial completion site
visit, APTIM will assist the County in the preparation of a punch list of items to be completed by the
Contractor prior to final acceptance. APTIM will conduct one (1) final acceptance walkthrough with the
County following site restoration, installation of dune vegetation, and demobilization. This final site visit
will be conducted to confirm that the Contractor has completed the punch list items.
Deliverable
APTIM will prepare and distribute a punch list to the project team upon completion of the substantial
completion site visit. A letter summarizing recommendations for final payment to the Contractor and
release of any retainage will be prepared at the completion of the project.
Schedule
APTIM will conduct the substantial completion site visit within seven (7) days of the receipt of written
notice from the Contractor of substantial completion. APTIM will conduct the final walkthrough within
seven (7) days of receipt of written notice from the Contractor that all punch list items have been
completion.
Cost
The lump sum cost for this task is $6,949.10.
Task 7: Project Report & Certification
After completion of the project and the Contractor has demobilized from the site, APTIM will provide a
written Project Completion Report to the County, which will include a summary of the work performed
along with a compilation of the pertinent correspondence and data. APTIM will provide a written statement
of completion and certification to satisfy permitting requirements noting any deviations from the permitted
projects. This certification will state whether the project was constructed in substantial compliance with
the plans and specifications. Our certification will be qualified and based on the extent of APTIM's
involvement in construction observation.
Deliverable
APTIM will provide one (1) hardcopy of the Project Completion Report and written statement of
completion to the County; electronic copies in PDF format will also be provided.
Schedule
The Project Completion Report will be provided within approximately sixty (60) days after completion and
acceptance of construction as required by the permit. The written statement of completion and
certification will be provided within thirty (30) days after completion and acceptance of construction
authorized by the permit.
Cost
The lump sum cost for this task is $16,334.00.
AAPTIM
Task 8: Check Surveys
November 13, 2020
Page 6 of 8
APTIM will conduct up to two (2) independent check surveys to evaluate discrepancies that may arise
between the Contractor's requested pay volume and APTIM's computed pay volume based on the
construction plans. This will allow for a prompt, independent check should questions arise regarding the
data obtained by the surveyor retained by the Contractor to perform pay surveys. The surveys will be
conducted with land-based equipment and extend to sufficient wading depth to complete the data check.
Deliverable
APTIM will include the check survey cross-sections in the Project Completion Report, if applicable.
Schedule
A fixed timeline cannot be provided because it is dependent upon the Contractor's progress and pay
survey results. APTIM will mobilize in an expeditious manner according to construction progress.
Cost
The lump sum cost for this task is $6,050.00
Task 9: Construction Phase Sea Turtle and Shorebird Monitoring
APTIM will oversee the scope of work proposed by EAI and provide the necessary administrative
coordination to the County. EAI has provided the enclosed proposal and cost breakdown for sea turtle
and shorebird monitoring tasks, which states:
Construction -phase sea turtle and shorebird monitoring and ancillary professional services in
support of the Sector 3 Beach and Dune Nourishment project. This scope of work was developed
based on conditions and requirements set forth in standard regulatory permits and the following
documents:
• Florida Department of Environmental Protection (FDEP) Joint Coastal Permit (JCP) No.
0285993 -009 -JC
• U.S. Fish and Wildlife Service (USFWS) Revised Statewide Programmatic Biological
Opinion (BO) dated March 13, 2015
The following tasks will be performed under this work order include:
• Task 1: Pre -construction Meeting
• Task 2: Daily Sea Turtle Monitoring and Data Management
• Task 3: Nighttime Sea Turtle Monitoring
• Task 4: Sea Turtle Nest Protection
• Task 5: Construction -phase Nesting Shorebird Monitoring and Protection
Cost
The lump sum cost for this task is $91,938.67.
Summary
The total lump sum cost to perform the proposed work described herein for Sector 3 — 2018006 — Work
Order #8 is $385,639.17 if the project is constructed via truck haul (omitting Task 3) or $306,501.17
,A APTIM
November 13, 2020
Page 7 of 8
(omitting Task 2) if constructed via dredge. Please refer to Exhibit 2, attached to the end of this proposal,
for a summary of the costs and labor hours of each Task. APTIM will proceed with the tasks upon receipt
of a signed work order from Indian River County (unless stated otherwise in the schedule). It is noted that
some aspects of this Work Order are dependent upon Contractor performance and are outside the control
of APTIM and the County. As such, the scope, schedule and cost described herein is provided as an
estimate. APTIM will strive to execute each phase of the work within budget and in as expeditious a
manner according to construction progress. We will coordinate with the County in the event that the
scope, schedule, or budget arise due to unforeseen issues or circumstances.
Thank you for the opportunity to serve Indian River County. We look forward to continuing to provide
expert professional services to the County. Please do not hesitate to call if you have any questions.
Sincerely,
Nicole S. Sharp, P.E.
Coastal Restoration & odeling Program Manager
Aptim Environmental Infrastructure, LLC
Aut Corporate Signature
Beau C. Suthard
Printed Name
Program Director
Title
September 9, 2020
Date
cc: Beau Suthard, PG, APTIM
Debbie Neese, APTIM
Printed Name
Chairman
Title
AND LEGAL I1�=�=� "`�� tip '-,,,
WILLIAM K. Di;14 AL
DEPUTY COUNTY AT T ORNEY
Attest: Jeffrey R. Smith, Clerk of
Circuit Court and Comptroller
Deputy Clerk
AAPTIM November 13, 2020
Page 8 of 8
EXHIBIT 2
Indian River County, FL
Sector 3 - 2018006 - Work Order #8
Construction Administration
Summary of Cost by Task
Task Number
Task Name
Labor
Subcontractors
Equipment
Materials
OtherODCs
Mobilization/
Demob
Totals
Task 1
Progress Meetings
$ 20,076.00
$ -
$
$
$
$ 20,076.00
Task 2
Site Observations - Truck Haul
$ 159,220.00
$ 10,500.00
$
$
$
$ 37,308.40
$ 207,028.40
Task 3
Site Observations - Dredging
$ 98,740.00
$ 10,500.00
$
$
$
$ 18,650.40
$ 127,890.40
Task
Construction Administration
$ 26,873.00
$ -
$
$
$
$ 26,873.00
Task
Payment Review
$ 10,390.00
$
$
$
$
$ -
$ 10,390.00
Task 6
Project Closeout
$ 6,614.00
$
$
$
$
$ 335.10
$ 6,949.10
Task 7
Project Report & Certification
$ 16,134.00
$
$
$
$ 200.00
$ -
$ 16,334.00
Task 8
Check Surveys
$ 5,060.00
$
$ 990.00
$
$ -
$
$ 6,050.00
Task 9
Construction Phase Sea Turtle
and Shorebird Monitoring
$ -
$ 91,938.67
$ -
$
$ -
$
$ 91,938.67
Totals =
$ 343,107.00
$ 112,938.67
$ 990.00
$
$ 200.00
$ 56,293.90
$ 513,529.57
Indian River County, FL
Sector 3 - 2018006 - Work Order #8
Construction Administration